Bombay HC to monitor Aurangabad water supply project progress
WATER & WASTE

Bombay HC to monitor Aurangabad water supply project progress

The Aurangabad bench of Bombay high court will now be monitoring the progress of the upcoming Aurangabad water supply project.

While listening to a plea filed by affected residents, the two-member bench of Justice Ravindra Ghuge and Justice SG Dighe said that the petition concerned would be taken up for hearing once in two weeks to monitor the progress of the new pipeline.

The court observed in an order dated April 20 that there is no dispute that in most of the Aurangabad localities, drinking water is supplied once in seven days and in some areas, once in eight days.

The bench said there is an acute shortage in water supply, mainly during summer, though there is adequate water storage in the Jayakwadi irrigation project due to the lack of a proper water distribution system.

While only the Aurangabad Municipal Corporation (AMC) was made a party in the case earlier, the court asked for making the ministry of environment, forest and climate change (MoEFCC), Maharashtra Jeevan Pradhikaran (MJP), state urban development department, state forest department, and National Highway Authority of India (NHAI), among others as.

To begin with, the court has directed the ministry of environment to approve the pump house construction at the Jayakwadi project, which also houses a bird sanctuary, before May 31.

Immediately the MJP would begin the pump house construction, the court said, asking the MJP to create a team of officers who would oversee the progress being made under the water supply project and record the daily progress details for production before the court as and when directed.

The Rs 1,680 crore new water pipeline scheme for Aurangabad has still not achieved the expected momentum despite one-third of the specified period being over.

Advocate Sambhaji Tope while representing the AMC before the court, said the work order for the new water supply project was issued in February 2021, and the expected time within which the project would be finished is about three years.

Image Source

Also read: SPML Infra receives Rs 1157.08 cr of Isarda water supply project

The Aurangabad bench of Bombay high court will now be monitoring the progress of the upcoming Aurangabad water supply project. While listening to a plea filed by affected residents, the two-member bench of Justice Ravindra Ghuge and Justice SG Dighe said that the petition concerned would be taken up for hearing once in two weeks to monitor the progress of the new pipeline. The court observed in an order dated April 20 that there is no dispute that in most of the Aurangabad localities, drinking water is supplied once in seven days and in some areas, once in eight days. The bench said there is an acute shortage in water supply, mainly during summer, though there is adequate water storage in the Jayakwadi irrigation project due to the lack of a proper water distribution system. While only the Aurangabad Municipal Corporation (AMC) was made a party in the case earlier, the court asked for making the ministry of environment, forest and climate change (MoEFCC), Maharashtra Jeevan Pradhikaran (MJP), state urban development department, state forest department, and National Highway Authority of India (NHAI), among others as. To begin with, the court has directed the ministry of environment to approve the pump house construction at the Jayakwadi project, which also houses a bird sanctuary, before May 31. Immediately the MJP would begin the pump house construction, the court said, asking the MJP to create a team of officers who would oversee the progress being made under the water supply project and record the daily progress details for production before the court as and when directed. The Rs 1,680 crore new water pipeline scheme for Aurangabad has still not achieved the expected momentum despite one-third of the specified period being over. Advocate Sambhaji Tope while representing the AMC before the court, said the work order for the new water supply project was issued in February 2021, and the expected time within which the project would be finished is about three years. Image Source Also read: SPML Infra receives Rs 1157.08 cr of Isarda water supply project

Next Story
Real Estate

The Only Way is Up!

In 2025, India’s real-estate market will be driven by a confluence of economic, demographic and policy-driven factors. Among these, Boman Irani, President, CREDAI National, counts rapid urbanisation, the rise of the middle class, policy reforms like RERA and GST rationalisation, and the Government’s decision to allow 100 per cent FDI in construction development projects (including townships, housing, built-up infrastructure, and real-estate broking services).In the top metros, especially Bengaluru, followed by Hyderabad and Pune, the key drivers will continue to be job creation a..

Next Story
Building Material

Organisations valuing gender diversity achieve higher profitability

The building materials industry is projected to grow by 8-12 per cent over the next five years. How is Aparna Enterprises positioning itself to leverage this momentum and solidify its market presence?The Indian construction and building materials industry is projected to witness significant expansion, with estimates suggesting an 8-12 per cent compound annual growth rate (CAGR) over the next five years. This growth is fuelled by rapid urbanisation, increased infrastructure investments and sustainability-focused policies. With India's real-estate market expected to reach $ 1 trillion by 2030, t..

Next Story
Real Estate

Dealing with Delays

Delays have beleaguered many a construction project in India, hampering the country from building to its ability and potential, and leading to additional costs incurred by the contractor. The reasons for delayIn India, delays mainly occur owing to obtaining statutory approvals, non-provisioning of right of way, utility diversion and approval of drawings and design. Delays are broadly classified based on responsibility and effect. Excusable delays arise from factors beyond the contractor’s control, such as force majeure events or employer-induced delays. These delays generally entitle th..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?