Bombay HC to monitor Aurangabad water supply project progress
WATER & WASTE

Bombay HC to monitor Aurangabad water supply project progress

The Aurangabad bench of Bombay high court will now be monitoring the progress of the upcoming Aurangabad water supply project.

While listening to a plea filed by affected residents, the two-member bench of Justice Ravindra Ghuge and Justice SG Dighe said that the petition concerned would be taken up for hearing once in two weeks to monitor the progress of the new pipeline.

The court observed in an order dated April 20 that there is no dispute that in most of the Aurangabad localities, drinking water is supplied once in seven days and in some areas, once in eight days.

The bench said there is an acute shortage in water supply, mainly during summer, though there is adequate water storage in the Jayakwadi irrigation project due to the lack of a proper water distribution system.

While only the Aurangabad Municipal Corporation (AMC) was made a party in the case earlier, the court asked for making the ministry of environment, forest and climate change (MoEFCC), Maharashtra Jeevan Pradhikaran (MJP), state urban development department, state forest department, and National Highway Authority of India (NHAI), among others as.

To begin with, the court has directed the ministry of environment to approve the pump house construction at the Jayakwadi project, which also houses a bird sanctuary, before May 31.

Immediately the MJP would begin the pump house construction, the court said, asking the MJP to create a team of officers who would oversee the progress being made under the water supply project and record the daily progress details for production before the court as and when directed.

The Rs 1,680 crore new water pipeline scheme for Aurangabad has still not achieved the expected momentum despite one-third of the specified period being over.

Advocate Sambhaji Tope while representing the AMC before the court, said the work order for the new water supply project was issued in February 2021, and the expected time within which the project would be finished is about three years.

Image Source

Also read: SPML Infra receives Rs 1157.08 cr of Isarda water supply project

The Aurangabad bench of Bombay high court will now be monitoring the progress of the upcoming Aurangabad water supply project. While listening to a plea filed by affected residents, the two-member bench of Justice Ravindra Ghuge and Justice SG Dighe said that the petition concerned would be taken up for hearing once in two weeks to monitor the progress of the new pipeline. The court observed in an order dated April 20 that there is no dispute that in most of the Aurangabad localities, drinking water is supplied once in seven days and in some areas, once in eight days. The bench said there is an acute shortage in water supply, mainly during summer, though there is adequate water storage in the Jayakwadi irrigation project due to the lack of a proper water distribution system. While only the Aurangabad Municipal Corporation (AMC) was made a party in the case earlier, the court asked for making the ministry of environment, forest and climate change (MoEFCC), Maharashtra Jeevan Pradhikaran (MJP), state urban development department, state forest department, and National Highway Authority of India (NHAI), among others as. To begin with, the court has directed the ministry of environment to approve the pump house construction at the Jayakwadi project, which also houses a bird sanctuary, before May 31. Immediately the MJP would begin the pump house construction, the court said, asking the MJP to create a team of officers who would oversee the progress being made under the water supply project and record the daily progress details for production before the court as and when directed. The Rs 1,680 crore new water pipeline scheme for Aurangabad has still not achieved the expected momentum despite one-third of the specified period being over. Advocate Sambhaji Tope while representing the AMC before the court, said the work order for the new water supply project was issued in February 2021, and the expected time within which the project would be finished is about three years. Image Source Also read: SPML Infra receives Rs 1157.08 cr of Isarda water supply project

Next Story
Resources

Madhya Pradesh Champions Inclusive Tourism at Heritage Sites

On the occasion of World Heritage Day, Madhya Pradesh is taking a significant step toward inclusive tourism by making its historical sites accessible to all — especially persons with disabilities. The state is rolling out its ‘Accessibility Infrastructure and Development’ project at Maheshwar, Mandu, Dhar, and Orchha, aiming to create a more welcoming experience at these iconic cultural destinations.The initiative, under the leadership of Chief Minister Dr Mohan Yadav and Tourism Minister Shri Dharmendra Bhav Singh Lodhi, includes infrastructure upgrades such as ramps, Braille signage, w..

Next Story
Resources

Runwal Realty Onboards Sonam Kapoor as Brand Ambassador

Real estate major Runwal has unveiled a refreshed identity as Runwal Realty, signalling a renewed commitment to crafting spaces that stand the test of time. With this refresh, the brand unveils its new philosophy: “Building for Generations to Come” and welcomes Bollywood star and global fashion icon Sonam Kapoor as its brand ambassador. This evolved identity reflects Runwal Realty’s commitment to creating not just homes, but heirlooms—crafted through visionary design, meticulous planning, global design expertise and an unwavering focus on quality. With the customer at its core, each de..

Next Story
Infrastructure Urban

Emerging Trends in Infrastructure and Transport 2025: KPMG

KPMG’s latest report, The Great Reset: Emerging Trends in Infrastructure and Transport 2025 edition, sheds light on the profound changes transforming the global infrastructure landscape. As industries adapt to the challenges posed by climate change, economic pressures, and technological advancements, the report identifies key trends and provides actionable insights for leaders in infrastructure and transport sectors. “In today’s interconnected world, the lack of standardized supply chain practices is not just an operational challenge—it’s an environmental and economic one. We’..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?