Over 400 Mumbai infra projects hit by cost and time overruns
SMART CITIES

Over 400 Mumbai infra projects hit by cost and time overruns

As many as 442 infrastructure projects in Mumbai, each worth Rs 150 crore or more, have taken a hit due to cost overruns of more than Rs 4.34 lakh crore.

All infrastructure projects that are worth Rs 150 crore or more are monitored by the Ministry of Statistics and Programme Implementation. Of a total of 1,671 projects, nearly 442 witnessed cost overruns and 536 have suffered postponement.

The total original cost of implementation of nearly 1,671 projects was calculated as Rs 21.21 lakh crore. The expected completion cost is Rs 25.56 lakh crore. It reflects the overall cost overruns of nearly Rs 4.34 lakh crore. It is 20.49% of its original cost.

During November 2020, the expenditure incurred on these projects was Rs 11.94 lakh crore, which is 46.71% of the anticipated costs.

If a delay is calculated based on the latest schedule of completion, then the number of delayed projects gets reduced to 412. For 942 projects, neither the year of commissioning nor the tentative gestation period has been reported.

Of 536 delayed projects, close to 120 have an overall delta of 1-12 months. Whereas, 13 projects are likely to see 13-24 months. Also, 162 indicate delay for 25-60 months and nearly 120 reflect a delay of 61 months and more. Hence, the average time overrun for 536 delayed projects is 44.15 months.

The reasons behind the time overruns:

  • Delay in tie-up for project financing
  • Delays in finalisation of detailed engineering
  • Change in scope
  • Delay in tendering
  • Ordering and equipment supply
  • Law and order issues
  • Delays in land acquisition
  • Delays in obtaining forest and environmental clearances
  • Lockdown in various states in the country

Various project agencies have not reported revisited cost estimates and commissioning schedules for projects. It indicates the time and cost overrun figures to be under-reported.

Image Source

As many as 442 infrastructure projects in Mumbai, each worth Rs 150 crore or more, have taken a hit due to cost overruns of more than Rs 4.34 lakh crore. All infrastructure projects that are worth Rs 150 crore or more are monitored by the Ministry of Statistics and Programme Implementation. Of a total of 1,671 projects, nearly 442 witnessed cost overruns and 536 have suffered postponement. The total original cost of implementation of nearly 1,671 projects was calculated as Rs 21.21 lakh crore. The expected completion cost is Rs 25.56 lakh crore. It reflects the overall cost overruns of nearly Rs 4.34 lakh crore. It is 20.49% of its original cost. During November 2020, the expenditure incurred on these projects was Rs 11.94 lakh crore, which is 46.71% of the anticipated costs. If a delay is calculated based on the latest schedule of completion, then the number of delayed projects gets reduced to 412. For 942 projects, neither the year of commissioning nor the tentative gestation period has been reported. Of 536 delayed projects, close to 120 have an overall delta of 1-12 months. Whereas, 13 projects are likely to see 13-24 months. Also, 162 indicate delay for 25-60 months and nearly 120 reflect a delay of 61 months and more. Hence, the average time overrun for 536 delayed projects is 44.15 months. The reasons behind the time overruns: Delay in tie-up for project financing Delays in finalisation of detailed engineering Change in scope Delay in tendering Ordering and equipment supply Law and order issues Delays in land acquisition Delays in obtaining forest and environmental clearances Lockdown in various states in the country Various project agencies have not reported revisited cost estimates and commissioning schedules for projects. It indicates the time and cost overrun figures to be under-reported. Image Source

Next Story
Infrastructure Energy

REC Transfers HVDC Project to Power Grid

REC Limited has successfully handed over the Special Purpose Vehicle (SPV) for a High-Voltage Direct Current (HVDC) transmission project to Power Grid Corporation of India Limited (PGCIL). This strategic move aligns with the nation's objectives to strengthen its power transmission network. Key Highlights: Project Overview: The HVDC project, under the inter-state transmission system (ISTS) initiative, is a critical component of India's push toward robust and efficient electricity transmission. It aims to handle bulk power transfer across long distances while ensuring minimal losses. Role of RE..

Next Story
Infrastructure Transport

NF Railway Collaborates with IIT Guwahati

The Northeast Frontier (NF) Railway has signed strategic Memorandums of Understanding (MoUs) with IIT Guwahati to foster technological advancements and improve railway operations in the region. This partnership focuses on innovative solutions to enhance safety, efficiency, and sustainability in rail infrastructure. Key Highlights: Purpose of MoUs: The collaboration aims to leverage IIT Guwahati's expertise in technology and research for implementing cutting-edge solutions across railway operations. Key areas of focus include: Automation and digitization in maintenance. Sustainability initiati..

Next Story
Infrastructure Transport

Danapur Division Modernization Plans Revealed

The Railway Board has unveiled ambitious plans for the expansion and modernization of the Danapur Division, a critical hub under the East Central Railway. The initiative focuses on infrastructure development, enhanced passenger amenities, and operational efficiency. Key Highlights: Scope of Modernization: The Railway Board's blueprint emphasizes: Upgrading existing infrastructure to accommodate more passenger and freight traffic. Improving station facilities, such as platforms, waiting areas, and connectivity. Introducing advanced signal systems for safer and smoother operations. Freig..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000