Over 400 Mumbai infra projects hit by cost and time overruns
SMART CITIES

Over 400 Mumbai infra projects hit by cost and time overruns

As many as 442 infrastructure projects in Mumbai, each worth Rs 150 crore or more, have taken a hit due to cost overruns of more than Rs 4.34 lakh crore.

All infrastructure projects that are worth Rs 150 crore or more are monitored by the Ministry of Statistics and Programme Implementation. Of a total of 1,671 projects, nearly 442 witnessed cost overruns and 536 have suffered postponement.

The total original cost of implementation of nearly 1,671 projects was calculated as Rs 21.21 lakh crore. The expected completion cost is Rs 25.56 lakh crore. It reflects the overall cost overruns of nearly Rs 4.34 lakh crore. It is 20.49% of its original cost.

During November 2020, the expenditure incurred on these projects was Rs 11.94 lakh crore, which is 46.71% of the anticipated costs.

If a delay is calculated based on the latest schedule of completion, then the number of delayed projects gets reduced to 412. For 942 projects, neither the year of commissioning nor the tentative gestation period has been reported.

Of 536 delayed projects, close to 120 have an overall delta of 1-12 months. Whereas, 13 projects are likely to see 13-24 months. Also, 162 indicate delay for 25-60 months and nearly 120 reflect a delay of 61 months and more. Hence, the average time overrun for 536 delayed projects is 44.15 months.

The reasons behind the time overruns:

  • Delay in tie-up for project financing
  • Delays in finalisation of detailed engineering
  • Change in scope
  • Delay in tendering
  • Ordering and equipment supply
  • Law and order issues
  • Delays in land acquisition
  • Delays in obtaining forest and environmental clearances
  • Lockdown in various states in the country

Various project agencies have not reported revisited cost estimates and commissioning schedules for projects. It indicates the time and cost overrun figures to be under-reported.

Image Source

As many as 442 infrastructure projects in Mumbai, each worth Rs 150 crore or more, have taken a hit due to cost overruns of more than Rs 4.34 lakh crore. All infrastructure projects that are worth Rs 150 crore or more are monitored by the Ministry of Statistics and Programme Implementation. Of a total of 1,671 projects, nearly 442 witnessed cost overruns and 536 have suffered postponement. The total original cost of implementation of nearly 1,671 projects was calculated as Rs 21.21 lakh crore. The expected completion cost is Rs 25.56 lakh crore. It reflects the overall cost overruns of nearly Rs 4.34 lakh crore. It is 20.49% of its original cost. During November 2020, the expenditure incurred on these projects was Rs 11.94 lakh crore, which is 46.71% of the anticipated costs. If a delay is calculated based on the latest schedule of completion, then the number of delayed projects gets reduced to 412. For 942 projects, neither the year of commissioning nor the tentative gestation period has been reported. Of 536 delayed projects, close to 120 have an overall delta of 1-12 months. Whereas, 13 projects are likely to see 13-24 months. Also, 162 indicate delay for 25-60 months and nearly 120 reflect a delay of 61 months and more. Hence, the average time overrun for 536 delayed projects is 44.15 months. The reasons behind the time overruns: Delay in tie-up for project financing Delays in finalisation of detailed engineering Change in scope Delay in tendering Ordering and equipment supply Law and order issues Delays in land acquisition Delays in obtaining forest and environmental clearances Lockdown in various states in the country Various project agencies have not reported revisited cost estimates and commissioning schedules for projects. It indicates the time and cost overrun figures to be under-reported. Image Source

Next Story
Infrastructure Energy

EDF Eyes Renewable Partnerships with NTPC, CIL, and Actis

EDF India has signed non-binding term sheets with NTPC, Coal India Ltd (CIL), and global investor Actis to advance renewable energy projects in India. Under this collaboration, NTPC will develop, own, and operate pumped storage projects (PSPs), standalone hydropower, and hybrid renewable energy projects. EDF has proposed a 50:50 joint venture with NTPC and a separate JV with CIL to pursue PSPs and renewable projects in India and neighboring countries. India’s National Electricity Plan 2023 estimates a need for 74 GW/411 GWh of energy storage systems by 2031-32, including 27 GW/175 GWh from ..

Next Story
Infrastructure Energy

West Bengal Seeks O&M Bids for 1.891 MW Solar Project

The West Bengal Power Development Corporation (WBPDCL) has invited bids for the comprehensive operation and maintenance (O&M) of a 1.891 MW rooftop solar project at Kolaghat Thermal Power Station for two years. Bids must be submitted by March 29, 2025, and will be opened on April 2. An earnest money deposit of Rs 89,332 is required, and successful bidders must provide a performance bank guarantee of 10% of the contract value within 30 days of the work order issuance. If the accepted bid value is 80% or lower than the estimated value, an additional performance security of 10% is mandatory. ..

Next Story
Infrastructure Energy

EDF Eyes Renewable Partnerships with NTPC, CIL, and Actis

EDF India has signed non-binding term sheets with NTPC, Coal India Ltd (CIL), and global investor Actis to advance renewable energy projects in India. Under this collaboration, NTPC will develop, own, and operate pumped storage projects (PSPs), standalone hydropower, and hybrid renewable energy projects. EDF has proposed a 50:50 joint venture with NTPC and a separate JV with CIL to pursue PSPs and renewable projects in India and neighboring countries. India’s National Electricity Plan 2023 estimates a need for 74 GW/411 GWh of energy storage systems by 2031-32, including 27 GW/175 GWh from ..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?