90% of sewerage, infra work done in Smart City
SMART CITIES

90% of sewerage, infra work done in Smart City

Imagine Panaji Smart City Development Ltd (IPSCDL) announced that significant strides have been made in the sewerage and road infrastructure projects across Panaji, with completion rates reaching 90%. Notably, central Panaji, Fontainhas, Mala, and the Miramar-Caranzalem area stand out with completion rates of 99%, while St Inez and Ribandar closely follow at 97% and 96%, respectively. However, Altinho trails behind with 78% of its projects finalised.

In central Panaji, IPSCDL has achieved the installation of 7.4km of sewerage pipeline, with 250 out of 251 manholes completed. Additionally, road infrastructure spanning 3.5km has been finished, with ongoing efforts for restoration. Similarly, St Inez has seen the completion of the entire 3km sewerage pipeline and 72 out of 75 manholes. Road construction is nearing completion, with just 150m left to finish.

Ribandar boasts a fully installed 9.6km sewerage pipeline, complemented by the construction of 280 out of 300 manholes. Roadwork covering 4km has been accomplished, with restoration work on-going on a 1km stretch. Fontainhas reports the successful completion of a 2.2km sewerage pipeline project, along with all 73 manholes. Efforts are now focused on road restoration. In Mala, a 3.3km stretch of sewerage pipeline is fully operational, with 109 out of 110 manholes constructed. Road restoration efforts are also in progress.

Similarly, in the Miramar-Caranzalem area, a 2.8km sewerage pipeline has been completed, along with 89 out of 90 manholes. Road restoration is actively underway. In Altinho, progress has been made on the sewerage pipeline project, with 450m laid, and 10 out of 18 manholes finished, while work continues on the rest. (Source: ET Infra)

Imagine Panaji Smart City Development Ltd (IPSCDL) announced that significant strides have been made in the sewerage and road infrastructure projects across Panaji, with completion rates reaching 90%. Notably, central Panaji, Fontainhas, Mala, and the Miramar-Caranzalem area stand out with completion rates of 99%, while St Inez and Ribandar closely follow at 97% and 96%, respectively. However, Altinho trails behind with 78% of its projects finalised. In central Panaji, IPSCDL has achieved the installation of 7.4km of sewerage pipeline, with 250 out of 251 manholes completed. Additionally, road infrastructure spanning 3.5km has been finished, with ongoing efforts for restoration. Similarly, St Inez has seen the completion of the entire 3km sewerage pipeline and 72 out of 75 manholes. Road construction is nearing completion, with just 150m left to finish. Ribandar boasts a fully installed 9.6km sewerage pipeline, complemented by the construction of 280 out of 300 manholes. Roadwork covering 4km has been accomplished, with restoration work on-going on a 1km stretch. Fontainhas reports the successful completion of a 2.2km sewerage pipeline project, along with all 73 manholes. Efforts are now focused on road restoration. In Mala, a 3.3km stretch of sewerage pipeline is fully operational, with 109 out of 110 manholes constructed. Road restoration efforts are also in progress. Similarly, in the Miramar-Caranzalem area, a 2.8km sewerage pipeline has been completed, along with 89 out of 90 manholes. Road restoration is actively underway. In Altinho, progress has been made on the sewerage pipeline project, with 450m laid, and 10 out of 18 manholes finished, while work continues on the rest. (Source: ET Infra)

Next Story
Infrastructure Urban

World-class sports complex in Tirupati soon

A new world-class sports complex will soon be developed in Tirupati, following a meeting between Animeni Ravi Naidu, Chairman of the Sports Authority of Andhra Pradesh (SAAP), G Narasimha Yadav, TDP Parliamentary President of Tirupati, and District Collector Dr. S Venkateswar. The new sports policy, recently approved by Chief Minister Nara Chandrababu Naidu, aims to elevate the standards of sports infrastructure in the region. During the meeting, the team discussed various components of the sports policy and highlighted plans to enhance Tirupati’s sports landscape. A key focus was the propo..

Next Story
Infrastructure Urban

Centre sets up five working groups to transform city management

The Union Ministry of Housing and Urban Affairs (MoHUA) has established five working groups to recommend reforms aimed at transforming urban governance across India. The groups will focus on areas such as political and administrative reforms, redefining the role of parastatals, rural-urban continuity, and enhancing local capacity building. These working groups will examine key issues like enhancing accountability among elected officials in project execution, the direct election of mayors, and the creation of participatory budgeting processes. The groups will submit their findings within three ..

Next Story
Infrastructure Transport

US Nagar highway to be realigned for Pantnagar airport expansion

A major highway realignment project has been announced in Udham Singh Nagar to facilitate the expansion of Pantnagar International Airport. The National Highway (NH) 109 will be relocated by 7 km behind the airport to accommodate the airport’s expansion plans. Vikas Mittal, Project Director at the National Highways Authority of India (NHAI), confirmed that a detailed project report (DPR) for the realignment is being prepared and will be submitted by December 22. The realigned stretch will curve near the Anandi Mata Temple, follow the railway line, and reconnect with the main highway near Sa..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000