360 projects report cost overruns of Rs 3.88 tn
PORTS & SHIPPING

360 projects report cost overruns of Rs 3.88 tn

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for June 2019, according to which, out of a total 1,608 projects, more than 360 have shown cost overruns to the tune of Rs 3.88 trillion.

The report states that the original estimated cost of all the projects is approximately Rs 19.18 trillion. Completion cost is now expected to be around Rs 23.05 trillion. This amounts to cost overruns of around 20.23 per cent from the original cost. Additionally, the report included the number of projects that had crossed their deadlines; these amounted to 550. The average time overrun for all 550 projects was reported to be 39.24 months.

Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints because of funding, geographical conditions, labour issues and court cases, among other reasons.

“Project implementation in certain infrastructure sectors continues to remain challenging, with many projects witnessing significant time and cost overruns,” says Shubham Jain, Group Head & Senior Vice-President, Corporate Ratings, ICRA. “As per the recent data available, the aggregate cost overrun for all major ongoing infrastructure projects as a percentage of original cost had increased to over 20 per cent—the highest in about eight years. Two key sectors—railways and power—have contributed to the majority of the cost overruns. This is despite the various reform measures undertaken by the Government. Delays in land acquisition, the difficulty faced in project financing, and increasing cost of land acquisition have been some of the key reasons behind the time and cost overruns.”

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for June 2019, according to which, out of a total 1,608 projects, more than 360 have shown cost overruns to the tune of Rs 3.88 trillion. The report states that the original estimated cost of all the projects is approximately Rs 19.18 trillion. Completion cost is now expected to be around Rs 23.05 trillion. This amounts to cost overruns of around 20.23 per cent from the original cost. Additionally, the report included the number of projects that had crossed their deadlines; these amounted to 550. The average time overrun for all 550 projects was reported to be 39.24 months. Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints because of funding, geographical conditions, labour issues and court cases, among other reasons. “Project implementation in certain infrastructure sectors continues to remain challenging, with many projects witnessing significant time and cost overruns,” says Shubham Jain, Group Head & Senior Vice-President, Corporate Ratings, ICRA. “As per the recent data available, the aggregate cost overrun for all major ongoing infrastructure projects as a percentage of original cost had increased to over 20 per cent—the highest in about eight years. Two key sectors—railways and power—have contributed to the majority of the cost overruns. This is despite the various reform measures undertaken by the Government. Delays in land acquisition, the difficulty faced in project financing, and increasing cost of land acquisition have been some of the key reasons behind the time and cost overruns.”

Next Story
Infrastructure Energy

REC Transfers HVDC Project to Power Grid

REC Limited has successfully handed over the Special Purpose Vehicle (SPV) for a High-Voltage Direct Current (HVDC) transmission project to Power Grid Corporation of India Limited (PGCIL). This strategic move aligns with the nation's objectives to strengthen its power transmission network. Key Highlights: Project Overview: The HVDC project, under the inter-state transmission system (ISTS) initiative, is a critical component of India's push toward robust and efficient electricity transmission. It aims to handle bulk power transfer across long distances while ensuring minimal losses. Role of RE..

Next Story
Infrastructure Transport

NF Railway Collaborates with IIT Guwahati

The Northeast Frontier (NF) Railway has signed strategic Memorandums of Understanding (MoUs) with IIT Guwahati to foster technological advancements and improve railway operations in the region. This partnership focuses on innovative solutions to enhance safety, efficiency, and sustainability in rail infrastructure. Key Highlights: Purpose of MoUs: The collaboration aims to leverage IIT Guwahati's expertise in technology and research for implementing cutting-edge solutions across railway operations. Key areas of focus include: Automation and digitization in maintenance. Sustainability initiati..

Next Story
Infrastructure Transport

Danapur Division Modernization Plans Revealed

The Railway Board has unveiled ambitious plans for the expansion and modernization of the Danapur Division, a critical hub under the East Central Railway. The initiative focuses on infrastructure development, enhanced passenger amenities, and operational efficiency. Key Highlights: Scope of Modernization: The Railway Board's blueprint emphasizes: Upgrading existing infrastructure to accommodate more passenger and freight traffic. Improving station facilities, such as platforms, waiting areas, and connectivity. Introducing advanced signal systems for safer and smoother operations. Freig..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000