360 projects report cost overruns of Rs 3.88 tn
PORTS & SHIPPING

360 projects report cost overruns of Rs 3.88 tn

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for June 2019, according to which, out of a total 1,608 projects, more than 360 have shown cost overruns to the tune of Rs 3.88 trillion.

The report states that the original estimated cost of all the projects is approximately Rs 19.18 trillion. Completion cost is now expected to be around Rs 23.05 trillion. This amounts to cost overruns of around 20.23 per cent from the original cost. Additionally, the report included the number of projects that had crossed their deadlines; these amounted to 550. The average time overrun for all 550 projects was reported to be 39.24 months.

Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints because of funding, geographical conditions, labour issues and court cases, among other reasons.

“Project implementation in certain infrastructure sectors continues to remain challenging, with many projects witnessing significant time and cost overruns,” says Shubham Jain, Group Head & Senior Vice-President, Corporate Ratings, ICRA. “As per the recent data available, the aggregate cost overrun for all major ongoing infrastructure projects as a percentage of original cost had increased to over 20 per cent—the highest in about eight years. Two key sectors—railways and power—have contributed to the majority of the cost overruns. This is despite the various reform measures undertaken by the Government. Delays in land acquisition, the difficulty faced in project financing, and increasing cost of land acquisition have been some of the key reasons behind the time and cost overruns.”

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for June 2019, according to which, out of a total 1,608 projects, more than 360 have shown cost overruns to the tune of Rs 3.88 trillion. The report states that the original estimated cost of all the projects is approximately Rs 19.18 trillion. Completion cost is now expected to be around Rs 23.05 trillion. This amounts to cost overruns of around 20.23 per cent from the original cost. Additionally, the report included the number of projects that had crossed their deadlines; these amounted to 550. The average time overrun for all 550 projects was reported to be 39.24 months. Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints because of funding, geographical conditions, labour issues and court cases, among other reasons. “Project implementation in certain infrastructure sectors continues to remain challenging, with many projects witnessing significant time and cost overruns,” says Shubham Jain, Group Head & Senior Vice-President, Corporate Ratings, ICRA. “As per the recent data available, the aggregate cost overrun for all major ongoing infrastructure projects as a percentage of original cost had increased to over 20 per cent—the highest in about eight years. Two key sectors—railways and power—have contributed to the majority of the cost overruns. This is despite the various reform measures undertaken by the Government. Delays in land acquisition, the difficulty faced in project financing, and increasing cost of land acquisition have been some of the key reasons behind the time and cost overruns.”

Next Story
Infrastructure Energy

Sri Lanka Adani Power Deal Still on as Government Confirms Lower Costs

The Sri Lankan government is engaged in negotiations with India’s Adani Group to reduce the cost of power from two wind power projects planned for the country’s Northern province. These discussions are part of a broader effort to ensure affordable and sustainable energy production as the nation works towards stabilising its power sector. The projects, backed by an investment of $442 million from the Adani Group, are expected to generate 500 MW of renewable energy. This initiative aligns with Sri Lanka’s long-term strategy to enhance its renewable energy capacity, reduce dependence on f..

Next Story
Infrastructure Energy

Hygenco Green Energies Pre-certified for RFNBO Ammonia Exports

Hygenco Green Energies is preparing to export green ammonia from India to Europe after securing Renewable Fuel of Non-Biological Origin (RFNBO) pre-certification from Bureau Veritas under the CertifHy scheme. This certification, officially recognized by the European Commission, facilitates access to green or low-carbon hydrogen for end-users across the EU. The CertifHy scheme provides a structured framework for certifying renewable hydrogen and e-fuels, ensuring compliance with EU regulations and international standards. Hygenco's upcoming green ammonia plant, located at Tata Steel’s Spe..

Next Story
Infrastructure Transport

11 NH Projects in Telangana Stalled over Pending Forest Clearance

As many as 11 National Highway projects in the state have been stalled due to the lack of forest clearance from the central government. The state government is coordinating with the Union government to secure the necessary environmental approvals. Efforts are underway by the state government, the Ministry of Road Transport and Highways, and the National Highways Authority of India (NHAI) to compile and submit all required details to the Ministry of Environment, Forest and Climate Change (MoEF&CC) for approval. Chief Minister A Revanth Reddy recently discussed the issue with Union Forest an..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000