Thane Bhiwandi Metro Line 5 Delayed and Now Set for March 2025 Completion
RAILWAYS & METRO RAIL

Thane Bhiwandi Metro Line 5 Delayed and Now Set for March 2025 Completion

The Thane-Bhiwandi Metro Line-5, initially scheduled for completion in March 2022, has been delayed, with a revised deadline now set for March 31, 2025. This three-year delay has raised concerns about project management efficiency within the Mumbai Metropolitan Region Development Authority (MMRDA).

The contract for the 24.90 km-long elevated metro corridor was awarded to Afcons Infrastructure on September 1, 2019. Designed to enhance connectivity between Thane, Bhiwandi, and Kalyan, the metro line will consist of 15 stations along its route. Despite the delay, the estimated project cost remains unchanged at Rs 8.98 billion. However, the penalty imposed for the delay is ?20.88 lakh, a figure considered minimal compared to the scale and impact of the extended timeline.

Once completed, Metro Line-5 is expected to play a crucial role in improving public transportation in the region. It will integrate with Metro Line-4 (Wadala-Kasarvadavali), the proposed Metro Line-12 (Kalyan-Taloja), and the Central Railway network, thereby offering seamless connectivity for commuters. The improved infrastructure is projected to reduce travel time by 50 to 75 per cent, benefiting both commercial and government employees who regularly commute along these corridors.

The delay is a setback for Mumbai’s metro expansion efforts, which aim to alleviate traffic congestion and promote the use of public transportation. The revised timeline has led to increased demands for stricter oversight and enhanced accountability to ensure timely execution of such critical infrastructure projects. With the new deadline set for 2025, residents and commuters in the affected areas anticipate that the metro line will be completed as planned, significantly improving the region’s transportation network.

News source: Urban Acres

The Thane-Bhiwandi Metro Line-5, initially scheduled for completion in March 2022, has been delayed, with a revised deadline now set for March 31, 2025. This three-year delay has raised concerns about project management efficiency within the Mumbai Metropolitan Region Development Authority (MMRDA). The contract for the 24.90 km-long elevated metro corridor was awarded to Afcons Infrastructure on September 1, 2019. Designed to enhance connectivity between Thane, Bhiwandi, and Kalyan, the metro line will consist of 15 stations along its route. Despite the delay, the estimated project cost remains unchanged at Rs 8.98 billion. However, the penalty imposed for the delay is ?20.88 lakh, a figure considered minimal compared to the scale and impact of the extended timeline. Once completed, Metro Line-5 is expected to play a crucial role in improving public transportation in the region. It will integrate with Metro Line-4 (Wadala-Kasarvadavali), the proposed Metro Line-12 (Kalyan-Taloja), and the Central Railway network, thereby offering seamless connectivity for commuters. The improved infrastructure is projected to reduce travel time by 50 to 75 per cent, benefiting both commercial and government employees who regularly commute along these corridors. The delay is a setback for Mumbai’s metro expansion efforts, which aim to alleviate traffic congestion and promote the use of public transportation. The revised timeline has led to increased demands for stricter oversight and enhanced accountability to ensure timely execution of such critical infrastructure projects. With the new deadline set for 2025, residents and commuters in the affected areas anticipate that the metro line will be completed as planned, significantly improving the region’s transportation network. News source: Urban Acres

Next Story
Resources

CRISIL Upgrades DCCDL’s Rating to AAA (Stable)

CRISIL Ratings has upgraded DLF Cyber City Developers (DCCDL) to CRISIL AAA (Stable) from CRISIL AA+ (Stable), citing sustained strong business fundamentals, high occupancy, and an improving financial risk profile.Sriram Khattar, Vice Chairman & Managing Director, DCCDL, said, “This milestone reflects our commitment to maintaining the highest standards of corporate governance and financial discipline whilst ensuring that our assets meet global benchmarks suitable for our tenant partners.”DCCDL operates a commercial real estate portfolio of 40.4 million square feet (msf), with a 93 per ..

Next Story
Real Estate

New Housing Supply Drops 34% in India’s Top-9 Cities

India’s residential real estate market experienced a 34% decline in new housing supply during the January-March 2025 period, with only 80,774 units launched, compared to 1,22,365 units in the same period last year, according to data from PropEquity.Among the top nine cities, Bengaluru was the only market to record an increase, with new housing supply rising 17% to 20,227 units, up from 17,303 in the year-ago period. In contrast, other major cities witnessed a significant decline. Chennai saw a 46% drop to 3,946 units, while Hyderabad recorded a 38% decline to 8,773 units. Kolkata was among t..

Next Story
Infrastructure Transport

TBM ‘Parvati’ Begins Tunneling on Kanpur Metro Line 2

The Kanpur Metro Project has reached another milestone as Kalpataru Projects International Ltd. (KPIL) – Gulermak JV deployed its third Tunnel Boring Machine (TBM) ""Parvati"" at Rawatpur Station for Line 2. This 8.38 km corridor stretches from Agriculture University to Barra-8.About TBM ParvatiTBM Type: Herrenknecht Earth Pressure Balance (EPB) Machine (Refurbished, Ø6.5m) 7th TBM commissioned for Kanpur Metro Phase 1 3rd TBM for Package KNPCC-11, following TBMs Gomati (S-1408A) and Saraswati (S-839C)Tunneling Assignments First Task: Construct a 750m tunnel for the upline fr..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?