Sikkim to get first train service
RAILWAYS & METRO RAIL

Sikkim to get first train service

By 2024, Sikkim is predicted to join the national network and the nation would receive "infrastructure of strategic importance" in the Himalayan state that borders China, with more than half of the Sivok-Rangpo railway line project already built.

There will be 14 tunnels and 22 bridges on the 45-kilometer, all-weather train track that is now being built from Siliguri, West Bengal, to Rangpo, Sikkim. This route crosses mountains, ravines, and the Teesta River. Though work is being done with great caution because the entire project is located in seismic zones four and five, it is being done on a war footing.

Additionally, landslides and flash floods are a constant concern, according to Project Director Mohinder Singh of ICON International, a government PSU under the Ministry of Railways. The representative of the Indian Railway Construction (IRCON) International Limited assured that safety procedures are in place and being followed.

He added that there are future plans to include Gangtok in the itinerary.

Redefine the future of urban mobility! Join us at the Metro Rail Conference 2025 to explore groundbreaking ideas and insights. 👉 Register today!

By 2024, Sikkim is predicted to join the national network and the nation would receive infrastructure of strategic importance in the Himalayan state that borders China, with more than half of the Sivok-Rangpo railway line project already built. There will be 14 tunnels and 22 bridges on the 45-kilometer, all-weather train track that is now being built from Siliguri, West Bengal, to Rangpo, Sikkim. This route crosses mountains, ravines, and the Teesta River. Though work is being done with great caution because the entire project is located in seismic zones four and five, it is being done on a war footing. Additionally, landslides and flash floods are a constant concern, according to Project Director Mohinder Singh of ICON International, a government PSU under the Ministry of Railways. The representative of the Indian Railway Construction (IRCON) International Limited assured that safety procedures are in place and being followed. He added that there are future plans to include Gangtok in the itinerary.

Next Story
Infrastructure Energy

Orb Energy Achieves Rs 3 Bn Milestone in Solar Financing Success

Orb Energy, a vertically integrated solar energy solutions provider, has achieved a significant milestone by surpassing Rs 3 billion in financing disbursements through its in-house finance facility that requires no collateral or down payment. This accomplishment underscores its dedication to supporting small and medium enterprises (SMEs) and micro, small, and medium enterprises (MSMEs) in India in transitioning to cost-effective solar energy solutions. The company has installed approximately 350 MW of solar photovoltaic systems nationwide, with a strong foothold in southern and western India...

Next Story
Infrastructure Energy

90% Defaulters Yet to Settle Rs 3.17 Bn Power Dues in Noida

Out of a total of 1.31 lakh defaulters in Noida, only 13,500 consumers availed of the one-time settlement (OTS) scheme during its first phase. The Uttar Pradesh Power Corporation (UPPCL) launched the scheme in three phases, from December 15, 2024, to January 31, 2025. These consumers cleared dues amounting to Rs 300.40 million out of a total Rs 3.47 billion owed. Officials emphasized that stricter enforcement of the scheme would be implemented in the coming phases. During a recent weekend meeting with the technical team of the power department, the Noida zone's chief engineer instructed that..

Next Story
Infrastructure Energy

NER Invites Bids for 10 MW Rooftop Solar Projects in Uttar Pradesh

The Varanasi division (electrical) of Northeastern Railway has recently issued four tenders for a total of 10.4 MW on-grid rooftop solar systems to be installed at various buildings in Gorakhpur, Uttar Pradesh. The tenders include different project capacities, with submission deadlines set between January 31 and February 3, 2025. Bidders are required to submit earnest money deposits (EMDs) ranging from Rs 0.89 million to Rs 1.2 million depending on the tender, with the expected project costs varying between Rs 148 million and Rs 174.08 million. The selected contractors will be tasked with sup..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000