Namma Metro Phase II delays; cost surges to Rs 400 billion
RAILWAYS & METRO RAIL

Namma Metro Phase II delays; cost surges to Rs 400 billion

The cost of Bengaluru Metro?s Phase-2 network has surged to nearly Rs 400 billion, marking a 52% increase from the original estimate a decade ago. Approved in 2014, the project initially spanned 72 km at a cost of Rs 264.05 billion, with an additional 3 km later incorporated, and was set for completion by 2019. By 2021, the cost had escalated to Rs 306.95 billion. The revised proposal has now been sent by Bangalore Metro Rail Corporation Ltd (BMRCL) to the State Finance Department for approval through the Urban Development Department (UDD).

Additional Chief Secretary of UDD, SR Umashankar, cited several factors for the increased costs, including revised land acquisition costs, extension of kilometres, inflation, pandemic-related delays, and fluctuations in international currencies. The primary reason for the cost hike is attributed to delays. Phase-II, initially set for completion in 2019, remains unfinished five years later. A senior UDD official noted that adhering to the original timeline would have prevented such a massive escalation. Land acquisition delays were a significant contributing factor.

BMRCL has undertaken several extensions and additions, contributing to the increased costs. The Reach-2 extension, originally terminating at Kengeri, now extends to Challaghatta. A new depot has been added at Kadugodi (Whitefield) on the eastern side. Additionally, 128.36 hectares of land have been acquired versus the initially planned 84.33 hectares, raising compensation costs to nearly Rs 63 billion, up by Rs 4.38 billion.

Road-widening projects near many metro stations, including the stretches from Baiyappanahalli to Kadugodi and Yelachenahalli to Silk Institute, have also added to the costs. Additional land was acquired for the Reach-5 line (R V Road-Bommasandra). Following approval from the State Finance Department, the revised proposal will be sent to the Centre?s Urban Development Department. (Source: TNIE)

The 14th RAHSTA Expo, part of the India Construction Festival, will be held on October 9 and 10, 2024, at the Jio Convention Centre in Mumbai. For more details, visit: https://rahstaexpo.com

The cost of Bengaluru Metro?s Phase-2 network has surged to nearly Rs 400 billion, marking a 52% increase from the original estimate a decade ago. Approved in 2014, the project initially spanned 72 km at a cost of Rs 264.05 billion, with an additional 3 km later incorporated, and was set for completion by 2019. By 2021, the cost had escalated to Rs 306.95 billion. The revised proposal has now been sent by Bangalore Metro Rail Corporation Ltd (BMRCL) to the State Finance Department for approval through the Urban Development Department (UDD). Additional Chief Secretary of UDD, SR Umashankar, cited several factors for the increased costs, including revised land acquisition costs, extension of kilometres, inflation, pandemic-related delays, and fluctuations in international currencies. The primary reason for the cost hike is attributed to delays. Phase-II, initially set for completion in 2019, remains unfinished five years later. A senior UDD official noted that adhering to the original timeline would have prevented such a massive escalation. Land acquisition delays were a significant contributing factor. BMRCL has undertaken several extensions and additions, contributing to the increased costs. The Reach-2 extension, originally terminating at Kengeri, now extends to Challaghatta. A new depot has been added at Kadugodi (Whitefield) on the eastern side. Additionally, 128.36 hectares of land have been acquired versus the initially planned 84.33 hectares, raising compensation costs to nearly Rs 63 billion, up by Rs 4.38 billion. Road-widening projects near many metro stations, including the stretches from Baiyappanahalli to Kadugodi and Yelachenahalli to Silk Institute, have also added to the costs. Additional land was acquired for the Reach-5 line (R V Road-Bommasandra). Following approval from the State Finance Department, the revised proposal will be sent to the Centre?s Urban Development Department. (Source: TNIE)

Next Story
Infrastructure Energy

Monsoon Rains Impact Diesel Sales in India

Impact of Monsoon: Recent monsoon rains in India have led to a decline in diesel sales across several states. The heavy rains have disrupted economic activities and logistics, affecting the demand for diesel. Sales Data: Data from state retailers indicates a noticeable drop in diesel consumption during the monsoon period. This trend is attributed to lower transportation activity and reduced agricultural operations due to adverse weather conditions. Regional Variations: The impact on diesel sales varies by region, with states experiencing more intense rains seeing a sharper decline. Ret..

Next Story
Real Estate

Delhi's rural residents protest at Jantar Mantar over unresolved issues

Residents from rural areas of Delhi organised a demonstration at Jantar Mantar to express their frustration over unresolved issues related to infrastructure and land. The mahapanchayat included participants from all 360 villages in Delhi and several neighboring Haryana villages. They presented ten demands, such as tax exemptions, amendments to the land pooling policy, and the transformation of Delhi's villages into smart villages. Chaudhary Surender Solanki, the head of Palam 360 Khap and leader of the protest, stated that rural communities have made significant contributions to Delhi's deve..

Next Story
Infrastructure Transport

Second airport proposed near Nelamangala

With the state government actively searching for a second airport location in Bengaluru, the final site appears to be near Nelamangala. According to sources, after extensive evaluation and consideration, the state government has chosen a site near Nelamangala-Kunigal along National Highway 75 for the construction of the proposed second international airport. Aiming to address Bengaluru's growing development needs, increasing passenger traffic, and cargo pressure, the state initiated the process of building a second international airport, following the examples of Delhi and Mumbai. The governm..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000