Mumbai-Ahmedabad bullet train project running behind schedule
RAILWAYS & METRO RAIL

Mumbai-Ahmedabad bullet train project running behind schedule

The Mumbai-Ahmedabad high-speed rail project, which is India's first bullet train, is running behind schedule, with only 33.68% of physical progress achieved against a target of 35.97% as of May 2023.

The project was initially estimated to cost Rs 108,000 crore, but the total cost has risen to almost Rs 2 Lakh crore due to delays and fluctuations in yen value. The high-speed rail line will connect Mumbai and Ahmedabad through 12 stations at a cost of Rs 1.1 lakh crore, with a deadline of December 2023. Trains on the line will operate at a speed of 320 kmph on an elevated viaduct, except in Mumbai where it will be built underground.

The Vapi-Sabarmati section is expected to be commissioned in August 2027, although the project may face agitation from executives of Coal India, which is unrelated to the project.

The Mumbai-Ahmedabad high-speed rail project, which is India's first bullet train, is running behind schedule, with only 33.68% of physical progress achieved against a target of 35.97% as of May 2023.The project was initially estimated to cost Rs 108,000 crore, but the total cost has risen to almost Rs 2 Lakh crore due to delays and fluctuations in yen value. The high-speed rail line will connect Mumbai and Ahmedabad through 12 stations at a cost of Rs 1.1 lakh crore, with a deadline of December 2023. Trains on the line will operate at a speed of 320 kmph on an elevated viaduct, except in Mumbai where it will be built underground.The Vapi-Sabarmati section is expected to be commissioned in August 2027, although the project may face agitation from executives of Coal India, which is unrelated to the project.

Next Story
Real Estate

Signature Global Awards Rs 5.6737 Billion Contract for Daxin Vistas

Signature Global (India), a leading real estate brand, has awarded construction contracts worth Rs 5.6737 billion (bn) for Daxin Vistas, an integrated township in Sohna, South of Gurugram. The announcement came during the Bhoomi Pujan ceremony, where the sample flat was also unveiled.The contracts were secured by B. L. Gupta Construction (P) Ltd. for Rs 4.82 bn to develop 2,792 independent floors in 36 months, while Shri Balaji Construction will execute external works, including sewage treatment, stormwater drainage, irrigation, and rainwater harvesting, for Rs 853.7 million.Lalit Kumar Aggarw..

Next Story
Resources

SOCOMEC Unveils High-efficiency UPS Delphys XM & DIRIS A-100/A-200 Meters

Socomec, a leading global specialist in LV power management solutions, proudly announces the launch of its latest solutions – the DELPHYS XM, an advanced Uninterruptible Power Supply (UPS) system ranging from 300 to 800 kVA/kW, and the DIRIS A-100/A-200, the ultimate all-purpose panel-mounted power quality meters, specifically designed to meet the demands of modern Data Centres and other critical infrastructures. With the DELPHYS XM offering advanced power management capabilities and the DIRIS A-100/A-200 providing intuitive energy monitoring, these products are set to revolutionize how indu..

Next Story
Infrastructure Urban

ASI Begins Underwater Archaeological Exploration in Dwarka

A team of five archaeologists from the Archaeological Survey of India (ASI), led by Prof. Alok Tripathi, Additional Director-General (Archaeology), has launched a new underwater exploration off the coast of Dwarka. The team, which includes H.K. Nayak, Dr. Aparajita Sharma, Ms. Poonam Vind, and Rajkumari Barbina, has chosen an area near the Gomati Creek for initial investigations. Notably, this marks the first time ASI has deployed a team with significant female representation for underwater research. The exploration is part of the revived Underwater Archaeology Wing (UAW) of ASI, which ha..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?