Metro corporation restores roads as Phase I nears completion
RAILWAYS & METRO RAIL

Metro corporation restores roads as Phase I nears completion

The Metro construction in the city has significantly improved local infrastructure. Almost all road sections temporarily used for Phase I of the Metro 3 station work have now been restored. Roads surrounding Marol, Santacruz, and BKC were the most impacted among the 10 stations in this phase. While road barricades have been removed, minor surface work in a few areas is ongoing and expected to conclude soon.

“Old facilities, including street furniture and pavements, are being reinstated,” said MMRCL Managing Director Ashwini Bhide. “Roads along the Aarey-BKC stretch have already been restored, and similar efforts are underway for the remaining route from Dharavi to Cuffe Parade.”

One of the main challenges remains at BKC, where road restoration has been slower due to ongoing civil work. Bhide noted that improvements are being made and stated, “As the civil work progresses, we are clearing the roads in this area.” The MMRCL plans to replace the steel deck currently at BKC with a concrete surface, a process expected to take two to three weeks. Despite this, traffic flow in the area has seen improvements.

The construction of the 33.5 km underground Metro 3 corridor, which used a combination of the cut-and-cover method and other technologies at 19 stations, impacted about 11 km of roadways, affecting a total of 97,000 square meters of road surface. This construction method involves excavating stretches of roads, which are then reinstated after work is completed. While the MMRCL aimed to minimise disruptions to the city’s road network, some areas were blocked to create shafts for launching tunnel boring machines.

Roadwork in Girgaum has reached a critical stage along the Phase II stretch, as construction began later than planned. A steel deck has been installed in the area, and road restrictions remain. In Worli, particularly along Acharya Atre Marg, road handover has been delayed due to multiple underground utilities. The MMRCL expects civil work for Phase II to be completed by December, after which road restoration will follow in a phased manner.

Reassuring residents, Bhide stated, “All trees removed during construction are being replanted at their original locations near each station. Additionally, facilities provided outside the stations will be maintained by Metro 3.”

(ET)

The Metro construction in the city has significantly improved local infrastructure. Almost all road sections temporarily used for Phase I of the Metro 3 station work have now been restored. Roads surrounding Marol, Santacruz, and BKC were the most impacted among the 10 stations in this phase. While road barricades have been removed, minor surface work in a few areas is ongoing and expected to conclude soon. “Old facilities, including street furniture and pavements, are being reinstated,” said MMRCL Managing Director Ashwini Bhide. “Roads along the Aarey-BKC stretch have already been restored, and similar efforts are underway for the remaining route from Dharavi to Cuffe Parade.” One of the main challenges remains at BKC, where road restoration has been slower due to ongoing civil work. Bhide noted that improvements are being made and stated, “As the civil work progresses, we are clearing the roads in this area.” The MMRCL plans to replace the steel deck currently at BKC with a concrete surface, a process expected to take two to three weeks. Despite this, traffic flow in the area has seen improvements. The construction of the 33.5 km underground Metro 3 corridor, which used a combination of the cut-and-cover method and other technologies at 19 stations, impacted about 11 km of roadways, affecting a total of 97,000 square meters of road surface. This construction method involves excavating stretches of roads, which are then reinstated after work is completed. While the MMRCL aimed to minimise disruptions to the city’s road network, some areas were blocked to create shafts for launching tunnel boring machines. Roadwork in Girgaum has reached a critical stage along the Phase II stretch, as construction began later than planned. A steel deck has been installed in the area, and road restrictions remain. In Worli, particularly along Acharya Atre Marg, road handover has been delayed due to multiple underground utilities. The MMRCL expects civil work for Phase II to be completed by December, after which road restoration will follow in a phased manner. Reassuring residents, Bhide stated, “All trees removed during construction are being replanted at their original locations near each station. Additionally, facilities provided outside the stations will be maintained by Metro 3.” (ET)

Next Story
Infrastructure Energy

REC Transfers HVDC Project to Power Grid

REC Limited has successfully handed over the Special Purpose Vehicle (SPV) for a High-Voltage Direct Current (HVDC) transmission project to Power Grid Corporation of India Limited (PGCIL). This strategic move aligns with the nation's objectives to strengthen its power transmission network. Key Highlights: Project Overview: The HVDC project, under the inter-state transmission system (ISTS) initiative, is a critical component of India's push toward robust and efficient electricity transmission. It aims to handle bulk power transfer across long distances while ensuring minimal losses. Role of RE..

Next Story
Infrastructure Transport

NF Railway Collaborates with IIT Guwahati

The Northeast Frontier (NF) Railway has signed strategic Memorandums of Understanding (MoUs) with IIT Guwahati to foster technological advancements and improve railway operations in the region. This partnership focuses on innovative solutions to enhance safety, efficiency, and sustainability in rail infrastructure. Key Highlights: Purpose of MoUs: The collaboration aims to leverage IIT Guwahati's expertise in technology and research for implementing cutting-edge solutions across railway operations. Key areas of focus include: Automation and digitization in maintenance. Sustainability initiati..

Next Story
Infrastructure Transport

Danapur Division Modernization Plans Revealed

The Railway Board has unveiled ambitious plans for the expansion and modernization of the Danapur Division, a critical hub under the East Central Railway. The initiative focuses on infrastructure development, enhanced passenger amenities, and operational efficiency. Key Highlights: Scope of Modernization: The Railway Board's blueprint emphasizes: Upgrading existing infrastructure to accommodate more passenger and freight traffic. Improving station facilities, such as platforms, waiting areas, and connectivity. Introducing advanced signal systems for safer and smoother operations. Freig..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000