Kochi Metro Phase II faces delays over land acquisition
RAILWAYS & METRO RAIL

Kochi Metro Phase II faces delays over land acquisition

The Kochi Metro Rail Limited's (KMRL) Phase II expansion, connecting JLN Stadium to Kakkanad, has been delayed due to prolonged land acquisition processes. Revenue authorities have extended the validity of the 11(1) land acquisition notification by six months, delaying the issuance of the 19(1) notification for several key stations. While the 11(1) notification has been issued for stations at Palarivattom, Kakkanad, CSEZ, Chitethukara, and Kinfra, only CSEZ and Chitethukara have moved forward with the 19(1) notification. According to the revenue department's order, the notification's validity has been extended until April 2025 for stations along the 11.2 km route. Construction activities had begun in September, including piling works for the viaduct and CEZ Metro station. KMRL initially projected completion of the project within 20 months and had undertaken preparatory work, including soil tests and topographical surveys, along the route. The proposed line will include new stations at Palarivattom Junction, Palarivattom Bypass, Chembumukku, Vazhakkala, Padamughal, Kakkanad Junction, Cochin SEZ, Chittethukara, KINFRA, and InfoPark. However, disputes over land ownership have caused setbacks, slowing the progress of this critical infrastructure project. (ET)

The Kochi Metro Rail Limited's (KMRL) Phase II expansion, connecting JLN Stadium to Kakkanad, has been delayed due to prolonged land acquisition processes. Revenue authorities have extended the validity of the 11(1) land acquisition notification by six months, delaying the issuance of the 19(1) notification for several key stations. While the 11(1) notification has been issued for stations at Palarivattom, Kakkanad, CSEZ, Chitethukara, and Kinfra, only CSEZ and Chitethukara have moved forward with the 19(1) notification. According to the revenue department's order, the notification's validity has been extended until April 2025 for stations along the 11.2 km route. Construction activities had begun in September, including piling works for the viaduct and CEZ Metro station. KMRL initially projected completion of the project within 20 months and had undertaken preparatory work, including soil tests and topographical surveys, along the route. The proposed line will include new stations at Palarivattom Junction, Palarivattom Bypass, Chembumukku, Vazhakkala, Padamughal, Kakkanad Junction, Cochin SEZ, Chittethukara, KINFRA, and InfoPark. However, disputes over land ownership have caused setbacks, slowing the progress of this critical infrastructure project. (ET)

Next Story
Real Estate

Pune Records 11% Drop in Property Registrations in Nov

Property registrations in Pune saw a decline of 11 percent year-on-year in November, totaling 13,371 units, despite robust demand, according to a report by Knight Frank India. The real estate consultancy revealed that the total registrations in November 2024 generated a revenue of Rs 475 crore for the state. This marked a fall from last year's figure of 14,988 units in the same month. Compared to October 2024, when 20,894 units were registered, November’s figures represent a 36 percent decrease. Shishir Baijal, Chairman and Managing Director of Knight Frank India, stated that Pune’s proper..

Next Story
Infrastructure Energy

Oriana Power Signs MoU with Rajasthan in Clean Energy

Oriana Power, a publicly-listed company on the NSE, announced on Monday that it has entered into a Memorandum of Understanding (MoU) with the Rajasthan government to invest Rs 10,000 crore in a series of clean energy projects. The projects will focus on solar energy, floating solar, green hydrogen, and energy storage solutions. The agreement was finalized in Jaipur during the recently concluded Rising Rajasthan Global Summit 2024. Oriana Power has identified six key locations in the state for these projects, including one in Bikaner, two in Churu, and three in Phalodi districts. Rupal Gupta, M..

Next Story
Infrastructure Energy

PM Surya Ghar Scheme Set to Surpass 10 Years of Solar Growth

The PM Surya Ghar Muft Bijli Yojana has achieved a remarkable milestone, surpassing 6.85 lakh solar installations within a year and poised to exceed a decade's worth of solar growth. The scheme, launched in February 2024, has already achieved 86 percent of the solar installations made in the last ten years. The 3-5 kW segment accounted for the majority of installations, at 77 percent, while 14 percent of installations were in the 5kW+ category. Gujarat led the charge with 2,86,545 installations, followed by Maharashtra with 1,26,344, Uttar Pradesh with 53,423, and Kerala. The scheme, which now..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000