Final Cross-Passage Completed in East-West Metro's Subsidence Zone
RAILWAYS & METRO RAIL

Final Cross-Passage Completed in East-West Metro's Subsidence Zone

The final cross-passage in the East-West Metro's Esplanade-to-Sealdah subsidence zone has been successfully completed, paving the way to link the two disjointed sections of the Green Line. With the construction of cross-passages on this section now finished, the work on the Esplanade-Sealdah stretch is expected to wrap up soon. Following this, the two currently operational sections "one between Sector V and Sealdah and the other between Howrah Maidan and Esplanade" will be connected, allowing services on the entire 16.6km corridor to commence.

"We made sure there was no ground settlement and damage to the buildings in the vicinity," an engineer involved in the project stated. Contractors ITD-ITD Cementation and the Kolkata Metro Rail Corporation (KMRC) had to proceed cautiously, taking a month to complete the last of the cross-passages, 5B, in the cave-in zone due to the need for heightened alertness and vigilance.

On April 18, water seepage was detected at two spots during micro-tunnelling to build a cross-passage below Hind on Ganesh Chandra Avenue, prompting an immediate halt to construction. Expensive chemical and cement grouting were carried out over three days, and micro-tunnelling resumed on April 22. As a precaution, a high-rise at 1A, Subodh Mullick Square was evacuated for a week starting April 22.

Cross-passages, small tunnels built at intervals of 250m on underground metro lines, allow passengers to cross from one main tunnel to another during emergencies, such as a fire. Although these smaller tunnels are crucial for safety in an underground metro corridor, KMRC had to abandon three of the eight originally planned cross-passages in the Esplanade-Sealdah section after the subsidence incident on October 14, 2022. The East-West Metro project between Esplanade and Sealdah has experienced three such incidents from 2019 to 2022.

Over the past month, alongside micro-tunnelling, the construction team also concretized small tunnel rings to create these smaller tunnels connecting the larger twin tunnels. The original site for cross-passage 5B under Nirmal Chunder Street proved to be as porous as three proposed sites beyond this area. After several months of grouting failed to stabilize the soil, the location was shifted to a more stable ground condition below the cinema. However, this new site also required extensive chemical and concrete grouting.

On April 16, hi-tech micro-tunnelling using the New Austrian Tunnel Method (NATM) commenced. "In less than four days, water seepage was detected at two spots and the work was stopped. A high-rise with a weak foundation was evacuated. From April 22, we worked slowly, lest there was subsidence. Thankfully, there was none," the engineer added.

The final cross-passage in the East-West Metro's Esplanade-to-Sealdah subsidence zone has been successfully completed, paving the way to link the two disjointed sections of the Green Line. With the construction of cross-passages on this section now finished, the work on the Esplanade-Sealdah stretch is expected to wrap up soon. Following this, the two currently operational sections one between Sector V and Sealdah and the other between Howrah Maidan and Esplanade will be connected, allowing services on the entire 16.6km corridor to commence. We made sure there was no ground settlement and damage to the buildings in the vicinity, an engineer involved in the project stated. Contractors ITD-ITD Cementation and the Kolkata Metro Rail Corporation (KMRC) had to proceed cautiously, taking a month to complete the last of the cross-passages, 5B, in the cave-in zone due to the need for heightened alertness and vigilance. On April 18, water seepage was detected at two spots during micro-tunnelling to build a cross-passage below Hind on Ganesh Chandra Avenue, prompting an immediate halt to construction. Expensive chemical and cement grouting were carried out over three days, and micro-tunnelling resumed on April 22. As a precaution, a high-rise at 1A, Subodh Mullick Square was evacuated for a week starting April 22. Cross-passages, small tunnels built at intervals of 250m on underground metro lines, allow passengers to cross from one main tunnel to another during emergencies, such as a fire. Although these smaller tunnels are crucial for safety in an underground metro corridor, KMRC had to abandon three of the eight originally planned cross-passages in the Esplanade-Sealdah section after the subsidence incident on October 14, 2022. The East-West Metro project between Esplanade and Sealdah has experienced three such incidents from 2019 to 2022. Over the past month, alongside micro-tunnelling, the construction team also concretized small tunnel rings to create these smaller tunnels connecting the larger twin tunnels. The original site for cross-passage 5B under Nirmal Chunder Street proved to be as porous as three proposed sites beyond this area. After several months of grouting failed to stabilize the soil, the location was shifted to a more stable ground condition below the cinema. However, this new site also required extensive chemical and concrete grouting. On April 16, hi-tech micro-tunnelling using the New Austrian Tunnel Method (NATM) commenced. In less than four days, water seepage was detected at two spots and the work was stopped. A high-rise with a weak foundation was evacuated. From April 22, we worked slowly, lest there was subsidence. Thankfully, there was none, the engineer added.

Next Story
Infrastructure Urban

Shoals' Q3 2024 revenue falls 23.9% due to project delays, supply chain

Shoals Technologies Group, a U.S.-headquartered manufacturer of electrical balance of systems (EBOS) for solar, energy storage, and e-mobility, reported a 23.9% year-over-year (YoY) decline in revenue, which dropped to $102.2 million in the third quarter (Q3) of 2024. This decline was mainly attributed to project delays and supply chain disruptions. The company posted a net loss of $300,000, a significant improvement compared to the $9.8 million net loss in Q3 2023. Adjusted net income was reported at $13.9 million, reflecting a 58.2% YoY decrease. Adjusted EBITDA stood at $24.5 million, a 4..

Next Story
Infrastructure Energy

FTC Solar sees 67% YoY decline in Q3 revenue from lower volumes

FTC Solar, a U.S.-based provider of solar tracker systems, reported a revenue of $10.14 million in the third quarter (Q3) of 2024, surpassing analyst expectations by $240,680. However, this figure marked a 66.8% year-over-year (YoY) decline compared to the same quarter in 2023, primarily attributed to reduced product volumes. The decline in solar tracker revenue was mainly due to an 82% decrease in the amount of MW produced, which was negatively impacted by delays in customer projects. This was partially offset by an increase in the average selling price (ASP), which led to better pricing an..

Next Story
Infrastructure Urban

Dilip Buildcon wins bid for BharatNet Phase III broadband project

Dilip Buildcon announced on Tuesday, November 12, that its STL-DBL consortium had submitted the lowest bid for BSNL's BharatNet Phase III broadband connectivity project. The USOF-funded project, which aims to provide middle and last-mile connectivity in Jammu Kashmir and Ladakh, is valued at Rs.1,625.36 Crore. Dilip Buildcon holds a 70.23% stake in the implementation of the project. The project is expected to be completed in three years, and the corporation will secure a 10-year maintenance contract. In recent days, BSNL has awarded several contracts for the BharatNet project. On Monday, No..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000