BMRCL launches first U-girder on Outer Ring Road
RAILWAYS & METRO RAIL

BMRCL launches first U-girder on Outer Ring Road

The Namma Metro's first U-girder was installed at Doddanekundi on Outer Ring Road (ORR) early on Sunday morning.

Bangalore Metro Rail Corporation Limited (BMRCL), along with contractor Shankaranarayana Constructions (SNC), began work on erecting the U-girder near Bagmane World Technology Centre in Doddanekundi on ORR. The first U-girder was established on top of pillars between 473 and 474 at about 4 am.

The U-girder was transported on a 43 m long trailer to the pier area from Lowry Junction close to KR Puram at 2.25 am. Traffic police had barricaded the road area to enable the work.

Each U-girder is 4.6 m wide, 28 m long, and weighs 165 metric tonnes (mt). It is lifted and installed with two hydraulic cranes, one with a capacity of 700 mt and another with 400 mt.

This is the first time U-girders are being utilised in Bengaluru to speed up the metro construction work.

BMRCL decided to employ U-girders for building the viaduct on Silk Board-KR Puram (19.5 km) on Outer Ring Road and KR Puram-Kempegowda International Airport (36 km) areas.

The U-girders will be used for nearly 80% of the corridor's length in the ORR-KIA route. The U-girders will involve casting the whole span of a viaduct between two piers in a single piece, whereas box-girders will have many parts between two piers. One U-girder between two pillars can be erected overnight, against 5-6 days needed in case of box girders.

Experts said U-girders would also save time as well as lower construction expenses. The much longer U-girders drastically decrease construction time. However, due to their length, they need absolute precision during construction. Also, their length makes ferrying them from the casting yard to the location a difficult task.

Image Source

Also read: RITES submits DPR for Namma Metro's phase 3 corridors to BMRCL

The Namma Metro's first U-girder was installed at Doddanekundi on Outer Ring Road (ORR) early on Sunday morning. Bangalore Metro Rail Corporation Limited (BMRCL), along with contractor Shankaranarayana Constructions (SNC), began work on erecting the U-girder near Bagmane World Technology Centre in Doddanekundi on ORR. The first U-girder was established on top of pillars between 473 and 474 at about 4 am. The U-girder was transported on a 43 m long trailer to the pier area from Lowry Junction close to KR Puram at 2.25 am. Traffic police had barricaded the road area to enable the work. Each U-girder is 4.6 m wide, 28 m long, and weighs 165 metric tonnes (mt). It is lifted and installed with two hydraulic cranes, one with a capacity of 700 mt and another with 400 mt. This is the first time U-girders are being utilised in Bengaluru to speed up the metro construction work. BMRCL decided to employ U-girders for building the viaduct on Silk Board-KR Puram (19.5 km) on Outer Ring Road and KR Puram-Kempegowda International Airport (36 km) areas. The U-girders will be used for nearly 80% of the corridor's length in the ORR-KIA route. The U-girders will involve casting the whole span of a viaduct between two piers in a single piece, whereas box-girders will have many parts between two piers. One U-girder between two pillars can be erected overnight, against 5-6 days needed in case of box girders. Experts said U-girders would also save time as well as lower construction expenses. The much longer U-girders drastically decrease construction time. However, due to their length, they need absolute precision during construction. Also, their length makes ferrying them from the casting yard to the location a difficult task. Image Source Also read: RITES submits DPR for Namma Metro's phase 3 corridors to BMRCL

Next Story
Real Estate

Varun Malik Joins ANAROCK as MD, Head of Capital Markets, APAC

ANAROCK Capital has appointed Varun Malik as Managing Director, Head of Capital Markets (APAC), marking a strategic move to expand its presence across Asia-Pacific. Based in Singapore, Malik will drive ANAROCK’s capital markets initiatives in the region.A real estate finance veteran, Malik brings over 18 years of experience in structuring complex cross-border transactions across South-East Asia and Australia. He has led debt and equity deals for REITs, fund managers, and developers, delivering strong returns and driving investor value.“We will redefine real estate capital solutions across ..

Next Story
Real Estate

Patra Chawl lottery held, 663 families allotted homes

Mumbai's Siddharth Nagar (Patra Chawl) Co-operative Housing Society members in Goregaon (West) saw their 15-year wait come to a close as MHADA conducted a successful computerised lottery for 663 eligible members under its redevelopment scheme.The Mumbai Housing and Area Development Board conducted the draw using the RAT (Randomised Allotment of Tenement) system at Sardar Vallabhbhai Patel Hall. The lottery, overseen by Mr. Milind Borikar, Chief Officer of Mumbai Board, ensured transparency by digitally allotting each member a building, wing, and floor.The project, located on Plot R-9, received..

Next Story
Infrastructure Transport

BLR Airport crosses 41 million passengers, 500,000 MT cargo

Kempegowda International Airport, Bengaluru (BLR Airport), has recorded key operational milestones in FY 2024-25, crossing 41.88 million passengers and handling 502,480 metric tonnes of cargo. This marks a year-on-year passenger growth of 11.6 per cent and a 14 per cent rise in cargo volumes.Domestic footfall reached 36.05 million, up 10 per cent, while international traffic saw a robust 25 per cent jump to 5.83 million, aided by Indigo’s global expansion and added frequencies by international carriers. BLR Airport now connects to 76 domestic and 33 international destinations, with Hanoi set..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?