Afcons creates milestone by excavating 7.32 km of Tunnel T49 in J&K
RAILWAYS & METRO RAIL

Afcons creates milestone by excavating 7.32 km of Tunnel T49 in J&K

Afcons Infrastructure Limited creates significant milestones by excavating 7.32 km of 12.75 km-long tunnel under extreme conditions in Jammu & kashmir. Milestone was attained on the Udhampur Srinagar Baramulla Rail Link project (USBRL) on Feb 15, 2022, with the advancement of Tunnel T49 between Sumber and Arpinchala Stations on the Katra-Banihal Section.

T49 is a 12.75 km-long tunnel and to be the longest tunnel of the Indian Railways surpassing the Peer Panjal Tunnel of 11.2 km on the Banihal-Qazigund section. The south portal of Tunnel T49 is located in the picturesque Sumber Village at an altitude of 1,400 m, while the north portal of the tunnel is situated near Arpinchala Village at an altitude of 1,600 m.

Afcons, a critical player in the strategic project, made it to the breakthrough point from the north portal despite considerable geological challenges.

While executing the tunnel from the north portal, Afcons' engineers excavated 4.07 km from a single audit. It is the most critical and longest length implemented by any agency from a single audit. No other agency in the entire USBRL project has excavated such a long distance from a single phase. Amidst the challenge of working in extremely cold conditions (as low as -10 degrees centigrade) during the winter months, the team faced another significant hurdle. There was water ingress of 40-50 litres per second which made tunnelling extremely challenging.

Since they were operating on a downward gradient, on average, they had to dewater nearly 2 lakh kWh units per month.

The water ingress was due to multiple aquifers and nullahs crossing the tunnel alignment, the Project Manager said. Over 60% of the tunnel length was implemented in very poor rock class. But extremely high deformation was noticed in a 1.5 km stretch of the tunnel.

To overcome this, the team adapted different construction techniques such as enlargement of tunnel profile and introduced steel fibre reinforced concrete to speed up the progress. They commenced an excavation in 2015 and throughout excavated under particularly poor geology.

The original scope was later updated to accommodate an additional 3.6 km escape tunnel which brought about a change in alignment. But we were able to complete the entire project within schedule. This tunnel is a significant achievement for Indian Railways and Afcons. From heavy snowfall and heavy rains, which restricted vehicle movement every year, to local issues and extremely poor geology, they are happy to have passed them all and complete a significant assignment for the nation.

Afcons Infrastructure Limited is a construction and engineering firm headquartered in Mumbai and part of Shapoorji Pallonji (SP) Group, which has a legacy of more than 150 years.

Image Source

Also read: Railways connects longest tunnel T-49 on Katra-Banihal section
Redefine the future of urban mobility! Join us at the Metro Rail Conference 2025 to explore groundbreaking ideas and insights. 👉 Register today!

Afcons Infrastructure Limited creates significant milestones by excavating 7.32 km of 12.75 km-long tunnel under extreme conditions in Jammu & kashmir. Milestone was attained on the Udhampur Srinagar Baramulla Rail Link project (USBRL) on Feb 15, 2022, with the advancement of Tunnel T49 between Sumber and Arpinchala Stations on the Katra-Banihal Section. T49 is a 12.75 km-long tunnel and to be the longest tunnel of the Indian Railways surpassing the Peer Panjal Tunnel of 11.2 km on the Banihal-Qazigund section. The south portal of Tunnel T49 is located in the picturesque Sumber Village at an altitude of 1,400 m, while the north portal of the tunnel is situated near Arpinchala Village at an altitude of 1,600 m. Afcons, a critical player in the strategic project, made it to the breakthrough point from the north portal despite considerable geological challenges. While executing the tunnel from the north portal, Afcons' engineers excavated 4.07 km from a single audit. It is the most critical and longest length implemented by any agency from a single audit. No other agency in the entire USBRL project has excavated such a long distance from a single phase. Amidst the challenge of working in extremely cold conditions (as low as -10 degrees centigrade) during the winter months, the team faced another significant hurdle. There was water ingress of 40-50 litres per second which made tunnelling extremely challenging. Since they were operating on a downward gradient, on average, they had to dewater nearly 2 lakh kWh units per month. The water ingress was due to multiple aquifers and nullahs crossing the tunnel alignment, the Project Manager said. Over 60% of the tunnel length was implemented in very poor rock class. But extremely high deformation was noticed in a 1.5 km stretch of the tunnel. To overcome this, the team adapted different construction techniques such as enlargement of tunnel profile and introduced steel fibre reinforced concrete to speed up the progress. They commenced an excavation in 2015 and throughout excavated under particularly poor geology. The original scope was later updated to accommodate an additional 3.6 km escape tunnel which brought about a change in alignment. But we were able to complete the entire project within schedule. This tunnel is a significant achievement for Indian Railways and Afcons. From heavy snowfall and heavy rains, which restricted vehicle movement every year, to local issues and extremely poor geology, they are happy to have passed them all and complete a significant assignment for the nation. Afcons Infrastructure Limited is a construction and engineering firm headquartered in Mumbai and part of Shapoorji Pallonji (SP) Group, which has a legacy of more than 150 years. Image Source Also read: Railways connects longest tunnel T-49 on Katra-Banihal section

Next Story
Infrastructure Transport

Atal Setu Records Daily Traffic Below Projections in First Year

India’s longest sea bridge, Atal Setu, which connects Sewri in Mumbai to Chirle in Navi Mumbai, has reported an average daily traffic of 22,689 vehicles in its first year, falling short of the initial projection of 56,000 vehicles per day. The 22-kilometer bridge, inaugurated by Prime Minister Narendra Modi on January 12, 2024, was constructed at a cost of Rs 178.4 billion and is hailed as a milestone in Maharashtra’s infrastructure development. According to the Mumbai Metropolitan Region Development Authority (MMRDA), the Atal Setu, formerly known as the Mumbai Trans Harbour Link (MT..

Next Story
Infrastructure Transport

Railway Board Tightens Rules for Bridge Design After Pamban Lapses

The Railway Board has mandated all zones to inform the Commissioner of Railway Safety (CRS) about the special features of significant and innovative bridges during the design phase. This directive, issued on January 10, follows findings from Southern Circle Railway Safety Commissioner AM Chowdhary, who identified critical lapses in the construction of the newly built Pamban Bridge. The Pamban Bridge, India’s first vertical-lift rail bridge, connects the mainland to Rameswaram Island in Tamil Nadu. Its construction came under scrutiny last November when the CRS flagged issues prior to gr..

Next Story
Infrastructure Urban

IISc and Tata Group to Launch Rs 5 Billion Medical School in Bengaluru

The Indian Institute of Science (IISc), Bengaluru, and the Tata Group have announced a partnership to establish the Tata IISc Medical School on the IISc Bengaluru campus. As part of the collaboration, the Tata Group will contribute Rs 5 billion to support the development of the institution. The Tata IISc Medical School is envisioned as a centre of excellence that combines basic science and engineering with clinical research and medical education. It will specialize in areas such as oncology, cardiology, neurology, nephrology, diabetes and metabolic disorders, infectious diseases, integrat..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000