What does India need to take its tunnelling to the next level?
ROADS & HIGHWAYS

What does India need to take its tunnelling to the next level?

One thing is clear. The past decade or so has seen a drastic change in the machinery used for tunnelling construction in India. “Whereas conventional blasting methods used to prevail, which made for very slow progress, now the most prevalent method in the Himalayan region is the New Austrian Tunnelling Method (NATM),which helps adjust to site conditions and has significantly sped up the implementation of projects,” observes Ranvir Singh, Manager (Projects)and Contracts Management Expert (Tunnelling), PEMS Engineering Consultants. “Cost comparisons of the two prominent tunnel construction methods nowadays and geological conditions, particularly in the Himalayan region, favour the NATM overtunnel boring machines (TBMs).”

“TBMs in general haven’tbeen successful in Himalayan geology owing to heterogeneous rock strata,” agrees Col Deepak Patil, General Manager (Project), Silkyara Tunnel, National Highways & Infrastructure Development Corporation. “For tunnelling in the Himalayan region, India mostly uses machinesthat can perform activities associated with the NATM, such asboomers/jumbos, shotcreting, various kinds of grouting, strengtheningthe ground, rather than TBMs.”

In cities where metro projects are being implemented, TBMs are being extensively used. Going forward, to take tunnelling to the next level, we must think of tunnelling methods beyond TBMs, NATM and conventional methods, based on rock mechanics and properties, advises Dr B C Mandal, Executive Director (Technical), BPC Consultant India.

Improving techniques

To ensure that proper methods and machinery are engaged, we need geological engineers to lead tunnelling projects instead of the civil engineers who are currently at the forefront of tunnelling projects, says Dr Mandal.

To read the full version, CLICK HERE.

One thing is clear. The past decade or so has seen a drastic change in the machinery used for tunnelling construction in India. “Whereas conventional blasting methods used to prevail, which made for very slow progress, now the most prevalent method in the Himalayan region is the New Austrian Tunnelling Method (NATM),which helps adjust to site conditions and has significantly sped up the implementation of projects,” observes Ranvir Singh, Manager (Projects)and Contracts Management Expert (Tunnelling), PEMS Engineering Consultants. “Cost comparisons of the two prominent tunnel construction methods nowadays and geological conditions, particularly in the Himalayan region, favour the NATM overtunnel boring machines (TBMs).” “TBMs in general haven’tbeen successful in Himalayan geology owing to heterogeneous rock strata,” agrees Col Deepak Patil, General Manager (Project), Silkyara Tunnel, National Highways & Infrastructure Development Corporation. “For tunnelling in the Himalayan region, India mostly uses machinesthat can perform activities associated with the NATM, such asboomers/jumbos, shotcreting, various kinds of grouting, strengtheningthe ground, rather than TBMs.” In cities where metro projects are being implemented, TBMs are being extensively used. Going forward, to take tunnelling to the next level, we must think of tunnelling methods beyond TBMs, NATM and conventional methods, based on rock mechanics and properties, advises Dr B C Mandal, Executive Director (Technical), BPC Consultant India. Improving techniques To ensure that proper methods and machinery are engaged, we need geological engineers to lead tunnelling projects instead of the civil engineers who are currently at the forefront of tunnelling projects, says Dr Mandal. To read the full version, CLICK HERE.

Next Story
Infrastructure Transport

Railway stations in Prayagraj undergo major passenger facility expansion

The Railway Board Chairman and CEO, Satish Kumar, conducted an extensive inspection on Saturday alongside the General Manager of Northern Railway and the officiating General Manager of North Central Railway. Their visit focused on various ongoing projects at multiple stations across the Northern and North Central Railway zones, with particular attention to enhancing facilities for the upcoming Maha Kumbh. During the inspection, Chairman Kumar reviewed the construction of a vital bridge over the River Ganga, specifically between Jhunsi and Prayagraj Rambagh. This bridge is expected to significa..

Next Story
Infrastructure Transport

Madurai-Thoothukudi broad gauge line works under review

The construction of the Madurai-Thoothukudi broad gauge line, which includes the crucial Melmarudur-Tiruparankundram project, is currently under careful review. This update comes from Southern Railway's assistant public information officer, J Kumarasubramanian, following an RTI inquiry made by a concerned citizen, Dayanand Krishnan. The new broad gauge line is projected to cover a total length of 143.5 km, with the initial 18 km stretch between Milavittan and Melmarudur completed and sanctioned by the Commission of Railway Safety on March 8, 2022. While substantial progress has been made on t..

Next Story
Real Estate

DLF expects Rs 26,000 cr from super luxury project in Gurugram

Realty giant DLF is projecting impressive revenue of Rs 26,000 crore from its newly unveiled super-luxury project, The Dahlias, situated in the heart of Gurugram. Ashok Tyagi, the Managing Director of DLF, shared these insights during a recent conference call with market analysts, highlighting the project's potential amidst rising demand for high-end residential properties. The Dahlias project spans an expansive 17 acres and is set to feature approximately 420 ultra-luxury apartments, each boasting a minimum size of 10,300 square feet. This ambitious development has already garnered significan..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000