Underwater tunnel works of Mumbai’s coastal road project delayed
ROADS & HIGHWAYS

Underwater tunnel works of Mumbai’s coastal road project delayed

The Brihanmumbai Municipal Corporation’s (BMC) ruling party has claimed that at least one section of Mumbai’s coastal road project’s underwater tunnel will be delayed.

So far, the Tunnel Boring Machine (TBM) has only drilled 800 m, far less than the 2.072 km expected.

Chief Minister Uddhav Thackeray had flagged the construction on the coastal road project's southbound tunnel in January. It was expected to be finished by October of this year.

The Shiv Sena chief, along with Yuva Sena chief and Cabinet Minister Aaditya Thackeray, have been seen inaugurating various works carried out by the Brihanmumbai Municipal Corporation (BMC) and other agencies in the city, in preparation for civic elections expected early next year. The plan was to finish one tunnel before the election code of conduct took effect, in order to demonstrate to the city the ruling party's accomplishments.

Apart from sea reclamation and the construction of a sea wall, the Rs 12,000 crore project also includes two underwater tunnels, one southbound and one northbound. Both tunnels are approximately 2.072 km long. These tunnels will be one of the project's highlights, as they will be the first time work of this magnitude has been carried out in the country. TBM will be dismantled and re-installed and brought back to the Priyadarshini Garden work site for boring the second tunnel after the first tunnel is completed, which will take at least another two to three months.

This was supposed to happen early next year. There appears to be a chance of a delay now.

While only 80% of the sea wall work has been completed, nearly 90% of the reclamation work has been completed.

The total cost of Mumbai's Coastal Road Project is Rs 12 thousand crore.

Image Source


Also read: Mumbai coastal road project 36% completed: BMC

Also read: Mumbai’s coastal road project: BMC completes 330 m of tunnelling work

The Brihanmumbai Municipal Corporation’s (BMC) ruling party has claimed that at least one section of Mumbai’s coastal road project’s underwater tunnel will be delayed. So far, the Tunnel Boring Machine (TBM) has only drilled 800 m, far less than the 2.072 km expected. Chief Minister Uddhav Thackeray had flagged the construction on the coastal road project's southbound tunnel in January. It was expected to be finished by October of this year. The Shiv Sena chief, along with Yuva Sena chief and Cabinet Minister Aaditya Thackeray, have been seen inaugurating various works carried out by the Brihanmumbai Municipal Corporation (BMC) and other agencies in the city, in preparation for civic elections expected early next year. The plan was to finish one tunnel before the election code of conduct took effect, in order to demonstrate to the city the ruling party's accomplishments. Apart from sea reclamation and the construction of a sea wall, the Rs 12,000 crore project also includes two underwater tunnels, one southbound and one northbound. Both tunnels are approximately 2.072 km long. These tunnels will be one of the project's highlights, as they will be the first time work of this magnitude has been carried out in the country. TBM will be dismantled and re-installed and brought back to the Priyadarshini Garden work site for boring the second tunnel after the first tunnel is completed, which will take at least another two to three months. This was supposed to happen early next year. There appears to be a chance of a delay now. While only 80% of the sea wall work has been completed, nearly 90% of the reclamation work has been completed. The total cost of Mumbai's Coastal Road Project is Rs 12 thousand crore. Image Source Also read: Mumbai coastal road project 36% completed: BMC Also read: Mumbai’s coastal road project: BMC completes 330 m of tunnelling work

Next Story
Infrastructure Energy

REC Transfers HVDC Project to Power Grid

REC Limited has successfully handed over the Special Purpose Vehicle (SPV) for a High-Voltage Direct Current (HVDC) transmission project to Power Grid Corporation of India Limited (PGCIL). This strategic move aligns with the nation's objectives to strengthen its power transmission network. Key Highlights: Project Overview: The HVDC project, under the inter-state transmission system (ISTS) initiative, is a critical component of India's push toward robust and efficient electricity transmission. It aims to handle bulk power transfer across long distances while ensuring minimal losses. Role of RE..

Next Story
Infrastructure Transport

NF Railway Collaborates with IIT Guwahati

The Northeast Frontier (NF) Railway has signed strategic Memorandums of Understanding (MoUs) with IIT Guwahati to foster technological advancements and improve railway operations in the region. This partnership focuses on innovative solutions to enhance safety, efficiency, and sustainability in rail infrastructure. Key Highlights: Purpose of MoUs: The collaboration aims to leverage IIT Guwahati's expertise in technology and research for implementing cutting-edge solutions across railway operations. Key areas of focus include: Automation and digitization in maintenance. Sustainability initiati..

Next Story
Infrastructure Transport

Danapur Division Modernization Plans Revealed

The Railway Board has unveiled ambitious plans for the expansion and modernization of the Danapur Division, a critical hub under the East Central Railway. The initiative focuses on infrastructure development, enhanced passenger amenities, and operational efficiency. Key Highlights: Scope of Modernization: The Railway Board's blueprint emphasizes: Upgrading existing infrastructure to accommodate more passenger and freight traffic. Improving station facilities, such as platforms, waiting areas, and connectivity. Introducing advanced signal systems for safer and smoother operations. Freig..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000