Timely completion of Jammu-Akhnoor 4-lane road project is uncertain
ROADS & HIGHWAYS

Timely completion of Jammu-Akhnoor 4-lane road project is uncertain

The much-hyped Jammu-Akhnoor 4-laning road project, which the Union Government approved in 2015, has missed numerous deadlines and won't be finished until 2023. In flagrant violation of the "contract agreement," the contractor, M/s Tarmat Limited, which has sublet work to local contractors, has failed to provide adequate and concrete service lanes along this road that is still being built.

When transporting patients from the Akhnoor, Khour, Jourian, Sunderbani, Nowshera, Kalakote, Rajouri, and Poonch areas to Jammu and back, commuters and especially the patients have been experiencing a great deal of difficulty due to the very bumpy and rough drive on the broken road patches at many locations along this under construction road. Even the District Magistrate of Jammu, the Regional Officer of the National Highway Authority of India (NHAI) in Jammu, and senior NHIDCL officials in the area have done nothing to stop the open breach of the contract agreement or the suffering of the road users.

Although the project was sanctioned in 2015 as part of the Prime Minister's Development Package Projects, according to official sources, actual ground work on the 26.35 km road project from Bhagwati Nagar/Canal Head Jammu up to Khati Chowk, a crossing near new Chenab bridge near Akhnoor town along bypass road, began in 2018.

Even though NHIDCL gave the contractor a completion deadline of July 31, 2023, the Rs 9.17 billion project known as NH-144-A is far from finished. Construction was done in stages, and because of bureaucracy and the slow speed of the contractors' work, many locations have not yet seen a resumption of the project. While work on five other bridges is progressing slowly, work on the bridge spanning Ranbir Canal at Suyya No. 1 (Bypass) has been abandoned for the past eight months.

Redefine the future of urban mobility! Join us at the Metro Rail Conference 2025 to explore groundbreaking ideas and insights. 👉 Register today!

The much-hyped Jammu-Akhnoor 4-laning road project, which the Union Government approved in 2015, has missed numerous deadlines and won't be finished until 2023. In flagrant violation of the contract agreement, the contractor, M/s Tarmat Limited, which has sublet work to local contractors, has failed to provide adequate and concrete service lanes along this road that is still being built. When transporting patients from the Akhnoor, Khour, Jourian, Sunderbani, Nowshera, Kalakote, Rajouri, and Poonch areas to Jammu and back, commuters and especially the patients have been experiencing a great deal of difficulty due to the very bumpy and rough drive on the broken road patches at many locations along this under construction road. Even the District Magistrate of Jammu, the Regional Officer of the National Highway Authority of India (NHAI) in Jammu, and senior NHIDCL officials in the area have done nothing to stop the open breach of the contract agreement or the suffering of the road users. Although the project was sanctioned in 2015 as part of the Prime Minister's Development Package Projects, according to official sources, actual ground work on the 26.35 km road project from Bhagwati Nagar/Canal Head Jammu up to Khati Chowk, a crossing near new Chenab bridge near Akhnoor town along bypass road, began in 2018. Even though NHIDCL gave the contractor a completion deadline of July 31, 2023, the Rs 9.17 billion project known as NH-144-A is far from finished. Construction was done in stages, and because of bureaucracy and the slow speed of the contractors' work, many locations have not yet seen a resumption of the project. While work on five other bridges is progressing slowly, work on the bridge spanning Ranbir Canal at Suyya No. 1 (Bypass) has been abandoned for the past eight months.

Next Story
Infrastructure Urban

Osaka Expo 2025 to Feature World’s Largest Wooden Structure

Osaka Expo 2025 will showcase the world’s largest wooden structure—a spectacular canopy encircling the 155-hectare exhibition grounds. Designed by architect Sou Fujimoto, the structure combines cutting-edge technology with Japan’s thousand-year tradition of wooden construction to create a futuristic yet sustainable landmark.“This is the biggest wooden construction in the world, so we used the latest technology alongside Japan's ancient craftsmanship to achieve a futuristic design,” Mr Fujimoto said. Rigorous testing ensured the strength of the beams and joints for the immense structu..

Next Story
Infrastructure Energy

India ranks 6th globally with 127 Net-zero firms

India has secured the sixth position globally in corporate climate action, with 127 companies committing to net-zero targets under the Science- Based Targets initiative (SBTi), according to the latest report from ICRA ESG Ratings.Although India contributes approximately 7 per cent of global emissions, its corporate commitments reflect a growing awareness of climate concerns. However, high-emission sectors such as power, energy, and cement are lagging in adopting these goals.The report reveals that fewer than 10 per cent of firms in these high-emission sectors, which contribute to 55 per cent o..

Next Story
Infrastructure Energy

Power prices fall 31% amid renewable push

The average price of electricity traded on India’s power exchanges during October-November 2024 fell by 31 per cent year-on-year (YoY) to Rs.3.61 per unit in the Day-Ahead Market (DAM), down from Rs.5.23 per unit in the same period last year. Similarly, Real-Time Market (RTM) prices dropped by 29 per cent to Rs.3.59 per unit, compared to Rs.5.04 per unit a year ago, as per industry data. The price drop was driven by a surge in renewable energy generation, particularly hydro and wind power, supported by favourable monsoon conditions. Improved fuel availability and government-led ini..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000