PWD to assess the smart road projects in Thiruvananthapuram
ROADS & HIGHWAYS

PWD to assess the smart road projects in Thiruvananthapuram

The board of the Smart City Thiruvananthapuram Ltd (STCL) has tasked the Public Works Department (PWD) secretary with examining the current progress of smart road projects in the city.

STCL had previously sought the state government's agreement to not extend the contract of the private business that had been awarded the work on the smart Road project within the city's corporate borders. The deadline for finishing the work on the company roads was May 31. A note was apparently sent to the secretary of the local self-government department, noting the firm's failure to meet the deadline.

It has been determined to remove 23 corporation roads from the contractor's scope of work. A new tender will be issued for the construction of 23 corporation roads.

Concerning the 17 roads where work has already begun, the PWD secretary will decide whether to continue with the current contractor or explore alternative choices.

A show-cause notice had previously been issued to the contractor. The city corporation had already informed SCTL that it did not wish to continue working with the private enterprise on the project's implementation.

Mayor Arya Rajendran, senior corporation officials, and works committee chairman D.R. Anil met with the contractor and even pledged to send staff to finish the job.

See also:
PWD sanctions smart road project
First phase of Althara-Attakulangara smart road project work starts


The board of the Smart City Thiruvananthapuram Ltd (STCL) has tasked the Public Works Department (PWD) secretary with examining the current progress of smart road projects in the city. STCL had previously sought the state government's agreement to not extend the contract of the private business that had been awarded the work on the smart Road project within the city's corporate borders. The deadline for finishing the work on the company roads was May 31. A note was apparently sent to the secretary of the local self-government department, noting the firm's failure to meet the deadline. It has been determined to remove 23 corporation roads from the contractor's scope of work. A new tender will be issued for the construction of 23 corporation roads. Concerning the 17 roads where work has already begun, the PWD secretary will decide whether to continue with the current contractor or explore alternative choices. A show-cause notice had previously been issued to the contractor. The city corporation had already informed SCTL that it did not wish to continue working with the private enterprise on the project's implementation. Mayor Arya Rajendran, senior corporation officials, and works committee chairman D.R. Anil met with the contractor and even pledged to send staff to finish the job. See also: PWD sanctions smart road projectFirst phase of Althara-Attakulangara smart road project work starts

Next Story
Infrastructure Energy

Coal Supply Chain Strengthened Nationwide

The Ministry of Coal has adopted multiple measures to improve the coal supply chain, ensuring efficient and cost-effective transportation. In February 2024, it launched the Coal Logistic Plan and Policy to enhance supply chain efficiency, lower costs, and promote sustainability. A key initiative is the development of First Mile Connectivity (FMC) projects, which aim to streamline coal evacuation from mines using mechanised loading infrastructure such as conveyor belts and crushers. So far, 39 FMC projects have been completed, adding a total capacity of 386 million tonnes. Rail infras..

Next Story
Infrastructure Energy

Raghavpur Project in MP gets environmental clearance

Afcons Infrastructure has received environmental clearance for the Raghavpur Multipurpose Project in Madhya Pradesh’s Dindori district, awarded by the Narmada Valley Development Authority. The project includes the construction of a dam and a 25 MW powerhouse on the Narmada River, along with a pressurised piped irrigation system to serve 17,587 hectares of farmland.The clearance was granted by the Madhya Pradesh State Environment Impact Assessment Authority (SEIAA), marking a key milestone. The project aims to boost both clean energy and agricultural output by integrating hydropower generatio..

Next Story
Equipment

Zoomlion begins Phase II of German factory project

Zoomlion Heavy Industry Science & Technology has initiated Phase II of its German factory project in Waldlaubersheim, investing over €50 million to expand the Wilbert TowerCranes GmbH facility. Spanning 60,000 square metres, the upgraded unit will produce tower cranes, truck cranes, and concrete machinery, aiming to deliver over 1,000 units annually and generate around USD 300 million in output once fully operational.The move aligns with Zoomlion’s vision to establish a central hub in Europe and strengthen its global supply chain, R&D, and service network. The new facility ..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?