NHAI fast-tracks Mumbai-Goa highway ahead of Ganesh festival
ROADS & HIGHWAYS

NHAI fast-tracks Mumbai-Goa highway ahead of Ganesh festival

The National Highways Authority of India (NHAI) is accelerating the construction of a 42-kilometre section of the Mumbai-Goa highway, from Panvel to Kasu in Raigad district, to facilitate the return of migrants to their hometowns for Ganeshotsav celebrations in the Konkan region. This stretch is being transformed from a bituminous road into a cemented one.

The Mumbai-Goa highway project, covering a total of 555 kilometres, extends across Maharashtra to Patradevi in Sindhudurg district. NHAI is responsible for an 84-kilometre segment from Panvel to Indapur in Raigad district, divided into two packages. Package 1 involves the 42-kilometre stretch from Panvel to Kasu, while Package 2 includes the remaining 42 kilometres from Kasu to Indapur.

JM Mhatre Infra secured the work order for Package 1, valued at Rs 1.51 billion, while Kalyan Toll Infra secured Package 2's work order in November 2022.

Initial challenges and delays plagued the project, as Supreme Tollways was initially awarded the entire 84-kilometre construction task in 2011, with a completion target set for 2014. However, issues such as land acquisition and utility shifting led to delays, and the contractor faced financial difficulties.

In 2021, NHAI terminated the contractor's services due to deadline non-compliance. Despite legal challenges, NHAI appointed two new contractors in 2022.

Currently, 32 kilometres of the Panvel-to-Kasu stretch have been completed, with ongoing work to cement the road due to heavy rainfall in the region. NHAI aims to complete the remaining work in time for the Ganesh festival. Package 2 construction will continue until December 2024 and includes underpasses, bridges, and road cementing from Kasu to Indapur.

While NHAI oversees 84 kilometres of the Mumbai-Goa highway in Maharashtra, the state Public Works Department (PWD) is responsible for the remaining 376 kilometres. PWD has finished 266 kilometres of the stretch and aims to complete the remaining 88 kilometres by December this year. The project is divided into ten packages for efficient execution, spanning from Mangaon in Raigad district to Patradevi in Sindhudurg district.

If you want to learn more about Indian Roads, make sure you sign-up for the India Roads Conference at the India Construction Festival on October 12th in New Delhi

Click HERE and reserve your seats! Or call Deepali on 82919 95574....

The National Highways Authority of India (NHAI) is accelerating the construction of a 42-kilometre section of the Mumbai-Goa highway, from Panvel to Kasu in Raigad district, to facilitate the return of migrants to their hometowns for Ganeshotsav celebrations in the Konkan region. This stretch is being transformed from a bituminous road into a cemented one.The Mumbai-Goa highway project, covering a total of 555 kilometres, extends across Maharashtra to Patradevi in Sindhudurg district. NHAI is responsible for an 84-kilometre segment from Panvel to Indapur in Raigad district, divided into two packages. Package 1 involves the 42-kilometre stretch from Panvel to Kasu, while Package 2 includes the remaining 42 kilometres from Kasu to Indapur.JM Mhatre Infra secured the work order for Package 1, valued at Rs 1.51 billion, while Kalyan Toll Infra secured Package 2's work order in November 2022.Initial challenges and delays plagued the project, as Supreme Tollways was initially awarded the entire 84-kilometre construction task in 2011, with a completion target set for 2014. However, issues such as land acquisition and utility shifting led to delays, and the contractor faced financial difficulties.In 2021, NHAI terminated the contractor's services due to deadline non-compliance. Despite legal challenges, NHAI appointed two new contractors in 2022.Currently, 32 kilometres of the Panvel-to-Kasu stretch have been completed, with ongoing work to cement the road due to heavy rainfall in the region. NHAI aims to complete the remaining work in time for the Ganesh festival. Package 2 construction will continue until December 2024 and includes underpasses, bridges, and road cementing from Kasu to Indapur.While NHAI oversees 84 kilometres of the Mumbai-Goa highway in Maharashtra, the state Public Works Department (PWD) is responsible for the remaining 376 kilometres. PWD has finished 266 kilometres of the stretch and aims to complete the remaining 88 kilometres by December this year. The project is divided into ten packages for efficient execution, spanning from Mangaon in Raigad district to Patradevi in Sindhudurg district. If you want to learn more about Indian Roads, make sure you sign-up for the India Roads Conference at the India Construction Festival on October 12th in New Delhi Click HERE and reserve your seats! Or call Deepali on 82919 95574....

Next Story
Infrastructure Urban

Macrotech acquires Bain Capital's stake in 3 entities for Rs 3 Bn

Realty firm Macrotech Developers has acquired Bain Capital's stake in three industrial and logistics park entities for Rs 3.07 billion as part of a strategy to enhance rental income. Macrotech Developers is one of the leading real estate firms in the country. It sells properties under Lodha brand. In a regulatory filing, the company informed that it has "executed Securities Purchase Agreements (SPAs) with India Opportunities Fund SSA Scheme 1 and DSS Opportunities Investment 1 (Bain Capital) for acquisition of their interest in the digital infrastructure platform entities (Bellissimo Digital I..

Next Story
Infrastructure Urban

Tata Steel reports Rs 7.59 Bn net profit in Jul-Sep

Tata Steel reported a net profit of Rs 7.58 billion for the September 2024 quarter, helped by lower expenses. It had posted a net loss of Rs 65.11 billion in the July-September period of the preceding 2023-24 fiscal, the company said in an exchange filing. In a separate statement, Tata Steel CEO and MD TV Narendran said the global operating environment remained complex, with key regions facing subdued growth. Macroeconomic conditions in China continued to weigh on commodity prices, including steel. In India, steel demand continued to improve, but domestic prices were under pressure due to chea..

Next Story
Infrastructure Urban

SC to verdict on Nov 7 on plea against NCLAT

The Supreme Court is scheduled to pronounce its verdict on a plea of State Bank of India (SBI) and other creditors challenging the National Company Law Appellate Tribunal (NCLAT) decision that upheld the resolution plan of grounded air carrier Jet Airways and approved the transfer of its ownership to Jalan Kalrock Consortium (JKC). A bench of Chief Justice D Y Chandrachud and Justices J B Pardiwala and Manoj Misra will pronounce the verdict which was reserved on October 16. The NCLAT had on March 12 upheld the resolution plan of the grounded air carrier and approved the transfer of its ownersh..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000