Mumbai coastal road project 36% completed: BMC
ROADS & HIGHWAYS

Mumbai coastal road project 36% completed: BMC

The Brihanmumbai Municipal Corporation (BMC) has completed 36% of the total work of the Mumbai coastal road project, against the 40% target set for completion by mid of 2021.

The civic body aims to finish all the work by December 2023, according to the authorities. The earlier target of project completion was July 2023, which was affected by the Covid-19 pandemic restrictions.

Chief engineer for the coastal road project, Vijay Nighot, said that the completed work includes about 470 metre or 25% of tunneling work of one tunnel and reclamation of 105 hectares of the total 111 hectares.

He further added that the piling work, casting of piers and girders, construction of the ramp work at Marine Drive, and tunneling work are in progress at present.

In December last year, BMC announced that its original aim of finishing the coastal road project by October 2022 had been extended to July 2023.

Nighot had then said that we have wasted eight months due to the court case, that had stayed the project construction in 2019, and additional six months due to the lockdown.

The coastal road will join Nariman Point to Bandra Worli Sea Link, which is 10.58 km long. Twin tunnels of a length of 2.07 km will join Girgaum Chowpatty and Malabar Hill. All underground tunnels will have three lanes of depth 70 m. The coastal road project will cost Rs 8,429 crore.

55% of the work should be accomplished by this December, and 85% of the work should be done by 2022 as per the civic body plan.

Image Source


Also read: Mumbai’s coastal road project: BMC completes 330 m of tunnelling work

Also read: India’s biggest TBM begins tunnelling for Mumbai coastal road

The Brihanmumbai Municipal Corporation (BMC) has completed 36% of the total work of the Mumbai coastal road project, against the 40% target set for completion by mid of 2021. The civic body aims to finish all the work by December 2023, according to the authorities. The earlier target of project completion was July 2023, which was affected by the Covid-19 pandemic restrictions. Chief engineer for the coastal road project, Vijay Nighot, said that the completed work includes about 470 metre or 25% of tunneling work of one tunnel and reclamation of 105 hectares of the total 111 hectares. He further added that the piling work, casting of piers and girders, construction of the ramp work at Marine Drive, and tunneling work are in progress at present. In December last year, BMC announced that its original aim of finishing the coastal road project by October 2022 had been extended to July 2023. Nighot had then said that we have wasted eight months due to the court case, that had stayed the project construction in 2019, and additional six months due to the lockdown. The coastal road will join Nariman Point to Bandra Worli Sea Link, which is 10.58 km long. Twin tunnels of a length of 2.07 km will join Girgaum Chowpatty and Malabar Hill. All underground tunnels will have three lanes of depth 70 m. The coastal road project will cost Rs 8,429 crore. 55% of the work should be accomplished by this December, and 85% of the work should be done by 2022 as per the civic body plan. Image Source Also read: Mumbai’s coastal road project: BMC completes 330 m of tunnelling work Also read: India’s biggest TBM begins tunnelling for Mumbai coastal road

Next Story
Infrastructure Energy

Adani Green Adds 212.5 MW Solar in Gujarat

Adani Green Energy Ltd. has commissioned a 212.5 MW solar power project at Khavda, Gujarat, through its subsidiary Adani Renewable Energy Fifty Seven Ltd. This addition brings Adani Green's total operational renewable capacity to 13,700 MW, as per a stock exchange filing. Last month, Adani Green became India's first renewable energy company to cross 12,000 MW of operational capacity. The company is also developing the world's largest 30,000 MW renewable energy plant in Khavda, spanning 538 sq km—about five times the size of Paris and nearly as large as Mumbai. Upon completion, it will be th..

Next Story
Infrastructure Energy

ONGC NTPC Green Acquires Ayana for Rs 62.5 Billion

ONGC NTPC Green Pvt Ltd (ONGPL) has completed the Rs 62.5 billion acquisition of Ayana Renewable Power, securing a 100% equity stake. The 50:50 joint venture between NTPC Green Energy Ltd (NGEL) and ONGC Green Ltd finalized the deal. NGEL contributed Rs 31.2 billion toward the acquisition, aligning with its goal to achieve 60 GW of renewable capacity by 2032. Ayana, a key player in India's green energy sector, has a 4,112 MW portfolio, with 2,123 MW operational and 1,989 MW under construction. Its projects are backed by high-credit-rated buyers, including SECI, NTPC, GUVNL, and Indian Railw..

Next Story
Infrastructure Transport

Cabinet Approves Rs 37.1 Billion Patna-Sasaram Corridor

The Union Cabinet has approved the construction of a four-lane access-controlled Patna-Sasaram corridor in Bihar at an estimated cost of Rs 37.1 billion. The 120.1 km project, to be developed under the Hybrid Annuity Mode (HAM), aims to ease congestion and enhance connectivity. Currently, travel between Sasaram, Arrah, and Patna takes 3-4 hours due to heavy traffic on state highways. The new corridor will integrate greenfield and 10.6 km of brownfield upgrades, linking key cities such as Arrah, Grahini, Piro, Bikramganj, Mokar, and Sasaram. The project will connect NH-19, NH-319, NH-922, NH-..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?