Landowner apathy delays NHAI projects in Punjab
ROADS & HIGHWAYS

Landowner apathy delays NHAI projects in Punjab

The indifference of landowners, including successors and purchasers, towards updating revenue records has emerged as a significant obstacle in land acquisition for National Highway Authority of India (NHAI) projects across Punjab. This issue has particularly affected the progress of the Jammu Katra Highway project in Saraud, where the consent of 52 co-owners, including NRIs, is required for one acquisition case.

Despite efforts by a 10-member committee, formed with the input of Bharatiya Kisan Union (Ugrian) representatives, to resolve the issue, progress has been slow. Stakeholders attribute this delay to a shortage of experienced revenue officials in the district and a lack of coordination between residents and revenue staff.

In several cases, compensation issued by the NHAI has not been transferred to the actual possessors due to discrepancies in the revenue records, which list multiple co-owners. For instance, in one case, landowners Bhagwant Singh and Raj Singh have been unable to receive compensation because the records show 52 co-owners, some of whom are NRIs and industrialists. The situation remains unresolved as none of these individuals have appeared to address the issue.

Other complications include cases where the claimant is not in possession of the land, and disputes over ownership are preventing the division and transfer of compensation. The situation is further complicated by records listing deceased persons as co-owners.

Harvir Singh Dhindsa, President, Punjab Revenue Patwar Union, acknowledged the challenges but noted that efforts had been made to update records in Saraud village. He urged farm leaders to persuade the concerned farmers to provide written consent to expedite the process.

The Revenue Department has also highlighted the lack of coordination among farmers and revenue officials as a longstanding issue, with several patwaris from Saraud village facing vigilance cases over the years. (The Tribune)

The indifference of landowners, including successors and purchasers, towards updating revenue records has emerged as a significant obstacle in land acquisition for National Highway Authority of India (NHAI) projects across Punjab. This issue has particularly affected the progress of the Jammu Katra Highway project in Saraud, where the consent of 52 co-owners, including NRIs, is required for one acquisition case. Despite efforts by a 10-member committee, formed with the input of Bharatiya Kisan Union (Ugrian) representatives, to resolve the issue, progress has been slow. Stakeholders attribute this delay to a shortage of experienced revenue officials in the district and a lack of coordination between residents and revenue staff. In several cases, compensation issued by the NHAI has not been transferred to the actual possessors due to discrepancies in the revenue records, which list multiple co-owners. For instance, in one case, landowners Bhagwant Singh and Raj Singh have been unable to receive compensation because the records show 52 co-owners, some of whom are NRIs and industrialists. The situation remains unresolved as none of these individuals have appeared to address the issue. Other complications include cases where the claimant is not in possession of the land, and disputes over ownership are preventing the division and transfer of compensation. The situation is further complicated by records listing deceased persons as co-owners. Harvir Singh Dhindsa, President, Punjab Revenue Patwar Union, acknowledged the challenges but noted that efforts had been made to update records in Saraud village. He urged farm leaders to persuade the concerned farmers to provide written consent to expedite the process. The Revenue Department has also highlighted the lack of coordination among farmers and revenue officials as a longstanding issue, with several patwaris from Saraud village facing vigilance cases over the years. (The Tribune)

Next Story
Real Estate

Ajmera Realty Acquires Land Parcel in Ghatkopar East

Ajmera Realty & Infra India (ARIIL) has acquired a 1,341.1 sq. mt. premium land parcel in Ghatkopar East, Mumbai. This acquisition, secured through a competitive bidding process with KJ Somaiya Trust at a cost of Rs 0.51 billion. With the earnest money paid and an MoU in place, the project is expected to yield a carpet area of ~44,000 sq. ft., with an estimated GDV of Rs 1.75 billion, said the BSE filing.Situated in Ghatkopar East, a well-established locality with a rising demand for spacious, high-end living, the company sees significant potential to launch an ultra-luxury project in this..

Next Story
Real Estate

Lemon Tree Hotels Launches 8th Property in Gujarat

Lemon Tree Hotels announces the opening of Keys Lite by Lemon Tree Hotels, Vadodara, Gujarat. This is the eighth property of the group in the state, as per the BSE filing.The efficient and affordable hotel features 63 well-appointed rooms and will open in two phases. Of these 57 rooms, a multi-cuisine coffee shop – Keys Café, along with expansive banquet spaces and conference facilities will be launched in the first phase. The remaining six rooms will be operational soon after in the second phase.Vadodara is known for its glorious past, echoed in its magnificent palaces and rich culture. Be..

Next Story
Infrastructure Transport

Nagpur-Goa Shaktipeeth Expressway Set to Revolutionise Travel

The Nagpur-Goa Shaktipeeth Expressway, a major 802-kilometer six-lane route, is set to revolutionize travel between Nagpur and Goa. Developed by the Maharashtra State Road Development Corporation (MSRDC), this expressway will slash travel time from 18-20 hours to just 8-10 hours. By enhancing connectivity across 12 districts, it aims to boost tourism, regional development, and provide easier access to spiritual sites.Stretching from Pavnar in Wardha district to Patradevi on the Maharashtra-Goa border, the expressway will pass through several districts, including Wardha, Yavatmal, Hingoli, Nand..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000