Hindon Bridge expected to be completed by April 2026
ROADS & HIGHWAYS

Hindon Bridge expected to be completed by April 2026

The completion of the Hindon Bridge, a critical infrastructure project aimed at improving connectivity between Noida and Greater Noida, has been postponed to April 2026. The project involves constructing a road over two kilometers long, which will link the Noida Expressway to Greater Noida’s LG Chowk via the Hindon Bridge. However, the project has encountered major delays due to ongoing land acquisition challenges.

Spanning 290 meters over the Hindon River, the bridge has only reached 30% of its construction progress. Initially launched by the Chief Minister of Uttar Pradesh in January 2019, the project was intended to be completed within 18 months. However, due to land acquisition issues, especially on the side of the Noida Authority, construction was halted for an extended period.

The Uttar Pradesh State Bridge Corporation (UPSBCL), the body overseeing the bridge’s construction, has officially requested an 18-month extension to finalize the remaining work. The delay also affects the construction of approach roads on both sides of the bridge, which are being developed by the Noida and Greater Noida authorities. These approach roads, each around one kilometre long, are expected to be completed alongside the bridge. Work on the bridge was paused for two and a half years because of the land acquisition issues, but construction resumed in November 2023. The approach roads began earlier this year as part of the project’s revival.

Once completed, the Hindon Bridge is expected to cut travel time between Noida and Greater Noida, along with key locations such as the district collectorate, Surajpur, and Ghaziabad, by approximately 16 kilometres. This improvement is expected to relieve traffic congestion, particularly at Pari Chowk, which is currently a major bottleneck for commuters. The delay highlights the difficulties faced by large-scale infrastructure projects, especially when dealing with land management. Ultimately, the Hindon Bridge is anticipated to significantly enhance regional connectivity and help manage increasing traffic demands in the area.                                                                                                                         

The completion of the Hindon Bridge, a critical infrastructure project aimed at improving connectivity between Noida and Greater Noida, has been postponed to April 2026. The project involves constructing a road over two kilometers long, which will link the Noida Expressway to Greater Noida’s LG Chowk via the Hindon Bridge. However, the project has encountered major delays due to ongoing land acquisition challenges.Spanning 290 meters over the Hindon River, the bridge has only reached 30% of its construction progress. Initially launched by the Chief Minister of Uttar Pradesh in January 2019, the project was intended to be completed within 18 months. However, due to land acquisition issues, especially on the side of the Noida Authority, construction was halted for an extended period.The Uttar Pradesh State Bridge Corporation (UPSBCL), the body overseeing the bridge’s construction, has officially requested an 18-month extension to finalize the remaining work. The delay also affects the construction of approach roads on both sides of the bridge, which are being developed by the Noida and Greater Noida authorities. These approach roads, each around one kilometre long, are expected to be completed alongside the bridge. Work on the bridge was paused for two and a half years because of the land acquisition issues, but construction resumed in November 2023. The approach roads began earlier this year as part of the project’s revival.Once completed, the Hindon Bridge is expected to cut travel time between Noida and Greater Noida, along with key locations such as the district collectorate, Surajpur, and Ghaziabad, by approximately 16 kilometres. This improvement is expected to relieve traffic congestion, particularly at Pari Chowk, which is currently a major bottleneck for commuters. The delay highlights the difficulties faced by large-scale infrastructure projects, especially when dealing with land management. Ultimately, the Hindon Bridge is anticipated to significantly enhance regional connectivity and help manage increasing traffic demands in the area.                                                                                                                         

Next Story
Infrastructure Urban

Trump-Backed $100 Billion Stargate to Use Solar Power for AI Infra

A $100 billion joint venture, endorsed by former President Donald Trump, is set to advance artificial intelligence in the U.S. and will rely partly on renewable energy sources such as solar power and batteries, favored by his climate-focused predecessor.The Stargate venture, announced on January 23, 2025, involves SoftBank Group Corp., OpenAI, and Oracle Corp. These companies will invest $100 billion to establish infrastructure in the U.S., including data centres for OpenAI. Although executives highlighted a potential $500 billion expansion, they did not specify energy sources for the project...

Next Story
Building Material

JK Cement Acquires Majority Stake in Saifco Cement to Expand in J&K

JK Cement has made a significant move in its growth strategy by acquiring a 60% equity stake in Saifco Cement, a cement manufacturer based in Srinagar, Jammu and Kashmir. The acquisition, valued at approximately Rs 1.74 billion, was approved during a board meeting on January 25, 2025.Located in Khunmoh, Srinagar, Saifco's integrated manufacturing unit, which includes both clinker and grinding capacities, aligns with JK Cement's expansion plans. Saifco has an annual turnover of around Rs 860 million, and this acquisition not only strengthens JK Cement's presence in the region but also offers a ..

Next Story
Infrastructure Transport

Etihad Unveils Train Connecting Dubai and Abu Dhabi in 30 Minutes

Etihad Rail has announced the launch of a new high-speed passenger train service between Dubai and Abu Dhabi, set to reduce travel time to just 30 minutes. The trains will travel at speeds of up to 350 km/h, significantly improving connectivity between the two emirates.The announcement was made during an official ceremony at Al Faya Depot, with officials from the Dubai Media Office (DMO) and Abu Dhabi Media Office (ADMO) sharing the news on social media platform X.The high-speed rail route will pass through major destinations and tourist attractions, providing a fast, efficient travel experien..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000