Hindon Bridge expected to be completed by April 2026
ROADS & HIGHWAYS

Hindon Bridge expected to be completed by April 2026

The completion of the Hindon Bridge, a critical infrastructure project aimed at improving connectivity between Noida and Greater Noida, has been postponed to April 2026. The project involves constructing a road over two kilometers long, which will link the Noida Expressway to Greater Noida’s LG Chowk via the Hindon Bridge. However, the project has encountered major delays due to ongoing land acquisition challenges.

Spanning 290 meters over the Hindon River, the bridge has only reached 30% of its construction progress. Initially launched by the Chief Minister of Uttar Pradesh in January 2019, the project was intended to be completed within 18 months. However, due to land acquisition issues, especially on the side of the Noida Authority, construction was halted for an extended period.

The Uttar Pradesh State Bridge Corporation (UPSBCL), the body overseeing the bridge’s construction, has officially requested an 18-month extension to finalize the remaining work. The delay also affects the construction of approach roads on both sides of the bridge, which are being developed by the Noida and Greater Noida authorities. These approach roads, each around one kilometre long, are expected to be completed alongside the bridge. Work on the bridge was paused for two and a half years because of the land acquisition issues, but construction resumed in November 2023. The approach roads began earlier this year as part of the project’s revival.

Once completed, the Hindon Bridge is expected to cut travel time between Noida and Greater Noida, along with key locations such as the district collectorate, Surajpur, and Ghaziabad, by approximately 16 kilometres. This improvement is expected to relieve traffic congestion, particularly at Pari Chowk, which is currently a major bottleneck for commuters. The delay highlights the difficulties faced by large-scale infrastructure projects, especially when dealing with land management. Ultimately, the Hindon Bridge is anticipated to significantly enhance regional connectivity and help manage increasing traffic demands in the area.                                                                                                                         

The 14th RAHSTA Expo, part of the India Construction Festival, will be held on October 9 and 10, 2024, at the Jio Convention Centre in Mumbai. For more details, visit: https://rahstaexpo.com

The completion of the Hindon Bridge, a critical infrastructure project aimed at improving connectivity between Noida and Greater Noida, has been postponed to April 2026. The project involves constructing a road over two kilometers long, which will link the Noida Expressway to Greater Noida’s LG Chowk via the Hindon Bridge. However, the project has encountered major delays due to ongoing land acquisition challenges.Spanning 290 meters over the Hindon River, the bridge has only reached 30% of its construction progress. Initially launched by the Chief Minister of Uttar Pradesh in January 2019, the project was intended to be completed within 18 months. However, due to land acquisition issues, especially on the side of the Noida Authority, construction was halted for an extended period.The Uttar Pradesh State Bridge Corporation (UPSBCL), the body overseeing the bridge’s construction, has officially requested an 18-month extension to finalize the remaining work. The delay also affects the construction of approach roads on both sides of the bridge, which are being developed by the Noida and Greater Noida authorities. These approach roads, each around one kilometre long, are expected to be completed alongside the bridge. Work on the bridge was paused for two and a half years because of the land acquisition issues, but construction resumed in November 2023. The approach roads began earlier this year as part of the project’s revival.Once completed, the Hindon Bridge is expected to cut travel time between Noida and Greater Noida, along with key locations such as the district collectorate, Surajpur, and Ghaziabad, by approximately 16 kilometres. This improvement is expected to relieve traffic congestion, particularly at Pari Chowk, which is currently a major bottleneck for commuters. The delay highlights the difficulties faced by large-scale infrastructure projects, especially when dealing with land management. Ultimately, the Hindon Bridge is anticipated to significantly enhance regional connectivity and help manage increasing traffic demands in the area.                                                                                                                         

Next Story
Infrastructure Energy

UP NEDA invites bids for 320 MW solar projects on lease land

The Uttar Pradesh New and Renewable Energy Development Agency (UP NEDA) has announced an invitation for bids for the development of 320 megawatts (MW) of solar power projects on lease land. This initiative aims to bolster the state's renewable energy capacity and foster sustainable growth. The projects will be installed on land leased from the state government, with detailed requirements and eligibility criteria outlined in the bid documents.Interested parties are encouraged to review the terms and submit their proposals by the specified deadline. ..

Next Story
Infrastructure Urban

Government issues VGF guidelines for 1 GW offshore wind projects

The Indian government has released new guidelines for the implementation of a 1 gigawatt (GW) offshore wind energy initiative. These guidelines introduce a viability gap funding (VGF) mechanism designed to support the financial feasibility of large-scale offshore wind projects. The VGF scheme aims to attract private investment and encourage the development of offshore wind infrastructure, which is crucial for meeting India’s renewable energy targets. The guidelines outline the eligibility criteria, funding process, and project requirements to streamline the deployment of these projects. Key..

Next Story
Infrastructure Energy

HPL Electric & Power Wins Rs 1.44-billion Order; Shares Climb

Shares of HPL Electric & Power increased by up to 2.4 percent. This rise followed the company’s announcement of securing an order worth Rs 1.44 billion. According to an exchange filing, HPL Electric & Power disclosed that it had received Work Orders/Letter of Award amounting to Rs 1.43 billion from its regular leading customers. The order pertains to the supply of Smart Meters and Conventional Meters, which will be executed in accordance with the terms and conditions specified in the Letter of Award and work orders. HPL Electric & Power, a prominent manufacturer of electrical equipment, ..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000