Govt ramps up efforts to expedite Delhi-Mumbai expressway project
ROADS & HIGHWAYS

Govt ramps up efforts to expedite Delhi-Mumbai expressway project

Despite the ongoing Covid-19 pandemic, full efforts are being made to complete the Delhi-Mumbai Expressway project expeditiously, said Road Transport and Highways Minister Nitin Gadkari.

In the 1,350 km long Delhi-Mumbai Expressway project, 350 km has already been built, and construction work of 825 km is in progress, said Gadkari.

He further added that bids have been received or invited for the remaining 163 km length, and these remaining works are likely to be given in the current year.

The Delhi-Mumbai Expressway is estimated to be completed by January 2023.

Gadkari said that at present, the construction of seven expressways having a length of 2,507 km has been taken up, out of which 440 km construction has been completed.

He said that the ministry has announced detailed guidelines dated June 3, 2020, for providing relief due to the ongoing pandemic.

He further added that the ministry has announced guidelines for compulsory utilisation of waste plastic in periodic renewal coat of pavement on National Highways and also in wearing course of service roads within 50 km boundary of urban areas having five lakhs or more population.

He said at present, 149 fee plazas on state highways and 701 fee plazas on National Highways have been approved, with Electronic Toll Collection (ETC) infrastructure.

Through FASTag a total amount of Rs 52,386.58 crore has been collected till July 11, 2021.

Image Source


Also read: Pune-Nashik highway bypass is completed, Nitin Gadkari shares images

Also read: Delhi-Jaipur stretch set to become India's first e-highway

Despite the ongoing Covid-19 pandemic, full efforts are being made to complete the Delhi-Mumbai Expressway project expeditiously, said Road Transport and Highways Minister Nitin Gadkari. In the 1,350 km long Delhi-Mumbai Expressway project, 350 km has already been built, and construction work of 825 km is in progress, said Gadkari. He further added that bids have been received or invited for the remaining 163 km length, and these remaining works are likely to be given in the current year. The Delhi-Mumbai Expressway is estimated to be completed by January 2023. Gadkari said that at present, the construction of seven expressways having a length of 2,507 km has been taken up, out of which 440 km construction has been completed. He said that the ministry has announced detailed guidelines dated June 3, 2020, for providing relief due to the ongoing pandemic. He further added that the ministry has announced guidelines for compulsory utilisation of waste plastic in periodic renewal coat of pavement on National Highways and also in wearing course of service roads within 50 km boundary of urban areas having five lakhs or more population. He said at present, 149 fee plazas on state highways and 701 fee plazas on National Highways have been approved, with Electronic Toll Collection (ETC) infrastructure. Through FASTag a total amount of Rs 52,386.58 crore has been collected till July 11, 2021. Image Source Also read: Pune-Nashik highway bypass is completed, Nitin Gadkari shares images Also read: Delhi-Jaipur stretch set to become India's first e-highway

Next Story
Resources

Madhya Pradesh Champions Inclusive Tourism at Heritage Sites

On the occasion of World Heritage Day, Madhya Pradesh is taking a significant step toward inclusive tourism by making its historical sites accessible to all — especially persons with disabilities. The state is rolling out its ‘Accessibility Infrastructure and Development’ project at Maheshwar, Mandu, Dhar, and Orchha, aiming to create a more welcoming experience at these iconic cultural destinations.The initiative, under the leadership of Chief Minister Dr Mohan Yadav and Tourism Minister Shri Dharmendra Bhav Singh Lodhi, includes infrastructure upgrades such as ramps, Braille signage, w..

Next Story
Resources

Runwal Realty Onboards Sonam Kapoor as Brand Ambassador

Real estate major Runwal has unveiled a refreshed identity as Runwal Realty, signalling a renewed commitment to crafting spaces that stand the test of time. With this refresh, the brand unveils its new philosophy: “Building for Generations to Come” and welcomes Bollywood star and global fashion icon Sonam Kapoor as its brand ambassador. This evolved identity reflects Runwal Realty’s commitment to creating not just homes, but heirlooms—crafted through visionary design, meticulous planning, global design expertise and an unwavering focus on quality. With the customer at its core, each de..

Next Story
Infrastructure Urban

Emerging Trends in Infrastructure and Transport 2025: KPMG

KPMG’s latest report, The Great Reset: Emerging Trends in Infrastructure and Transport 2025 edition, sheds light on the profound changes transforming the global infrastructure landscape. As industries adapt to the challenges posed by climate change, economic pressures, and technological advancements, the report identifies key trends and provides actionable insights for leaders in infrastructure and transport sectors. “In today’s interconnected world, the lack of standardized supply chain practices is not just an operational challenge—it’s an environmental and economic one. We’..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?