Gorakhpur Link Expressway to be operational soon
ROADS & HIGHWAYS

Gorakhpur Link Expressway to be operational soon

The 92-kilometre-long Gorakhpur Link Expressway, which connects the city to the Purvanchal Expressway, will be opened to the public soon. Chief Minister Yogi Adityanath set a December deadline for the completion of the Gorakhpur Link Expressway in February. The project, which began in February 2020, will cost Rs 5,877 crore, including land costs.

More than 62% of the construction work has been completed thus far. Once completed, the motorway will ensure smooth vehicular traffic movement from Gorakhpur to Lucknow, Agra, and Delhi.

While clearing and grubbing work has been completed, civil work on the main carriageway is currently underway, including granular sub-base (GSB), wet mix macadam (WMM), and dense bituminous macadam (DBM).

The four-lane (expandable to six lanes) expressway begins at Jaitpur on NH-27 in Gorakhpur district and links with the Purvanchal Expressway near Salarpur in Azamgarh district. The access-controlled expressway spans across four districts — Gorakhpur, Sant Kabir Nagar, Ambedkar Nagar, and Azamgarh.

The nodal agency, Uttar Pradesh Expressway Development Authority (UPEIDA), is carrying out this project in the engineering, procurement, and construction (EPC) mode. For implementation, the project has been divided into two packages. While one company is working on the project's 47-kilometer-long package-1, another is working on package-2, which is 43.03 kilometres long. Two toll plazas, three ramp plazas, seven flyovers, 16 vehicular underpasses, 50 light vehicular underpasses, 35 pedestrian underpasses, seven major bridges, 27 minor bridges, and 389 culverts are also being built as part of the motorway. A separate link road will connect the Gorakhpur Link Expressway to Varanasi, according to a UPEIDA spokesperson.

The motorway is expected to serve as an industrial corridor, connecting various manufacturing units. Keeping this in mind, the latest budget includes a Rs 200 crore allocation for the Industrial Corridor along the Gorakhpur-link Expressway.

Also Read
Rs 120 bn project development in Gorakhpur in 1 st year CM’s 2 nd-stint 
Dalmia Cement to sell stake in firm Sarvapriya Healthcare

The 92-kilometre-long Gorakhpur Link Expressway, which connects the city to the Purvanchal Expressway, will be opened to the public soon. Chief Minister Yogi Adityanath set a December deadline for the completion of the Gorakhpur Link Expressway in February. The project, which began in February 2020, will cost Rs 5,877 crore, including land costs. More than 62% of the construction work has been completed thus far. Once completed, the motorway will ensure smooth vehicular traffic movement from Gorakhpur to Lucknow, Agra, and Delhi. While clearing and grubbing work has been completed, civil work on the main carriageway is currently underway, including granular sub-base (GSB), wet mix macadam (WMM), and dense bituminous macadam (DBM). The four-lane (expandable to six lanes) expressway begins at Jaitpur on NH-27 in Gorakhpur district and links with the Purvanchal Expressway near Salarpur in Azamgarh district. The access-controlled expressway spans across four districts — Gorakhpur, Sant Kabir Nagar, Ambedkar Nagar, and Azamgarh. The nodal agency, Uttar Pradesh Expressway Development Authority (UPEIDA), is carrying out this project in the engineering, procurement, and construction (EPC) mode. For implementation, the project has been divided into two packages. While one company is working on the project's 47-kilometer-long package-1, another is working on package-2, which is 43.03 kilometres long. Two toll plazas, three ramp plazas, seven flyovers, 16 vehicular underpasses, 50 light vehicular underpasses, 35 pedestrian underpasses, seven major bridges, 27 minor bridges, and 389 culverts are also being built as part of the motorway. A separate link road will connect the Gorakhpur Link Expressway to Varanasi, according to a UPEIDA spokesperson. The motorway is expected to serve as an industrial corridor, connecting various manufacturing units. Keeping this in mind, the latest budget includes a Rs 200 crore allocation for the Industrial Corridor along the Gorakhpur-link Expressway. Also Read Rs 120 bn project development in Gorakhpur in 1 st year CM’s 2 nd-stint  Dalmia Cement to sell stake in firm Sarvapriya Healthcare

Next Story
Infrastructure Urban

IICA & CMAI Ink MoU to Boost India's Carbon Markets & Decarbonisation

In a major step toward strengthening India’s carbon markets and advancing decarbonisation efforts, the Indian Institute of Corporate Affairs (IICA) and the Carbon Market Association of India (CMAI) formalized their collaboration through a Memorandum of Understanding (MoU) in New Delhi. The agreement was announced during the IICA-CMAI Masterclass on Global & Indian Carbon Markets, held as part of India Climate Week. The event was attended by key government officials, including the Union Minister for Road, Transport & Highways, who emphasized the importance of biofuels and green hydrogen in sh..

Next Story
Infrastructure Urban

Kavach Installation on Mumbai-Delhi-Kolkata Route Extended to Dec ’25

The Railway Board has extended the deadline for the installation of the Automatic Train Protection (ATP) system, Kavach, on the Delhi-Mumbai and Delhi-Kolkata routes from March to December 2025. According to the revised railway budget estimates for 2025-26, track-side equipment for Kavach Version 4.0 will be installed across the 3,000 km stretch by the end of 2025, with work progressing on the remaining sections. Indian Railways adopted Kavach as the national ATP system in 2020, with the latest specification for Version 4.0 approved in July 2024. The project includes the installation of Kava..

Next Story
Infrastructure Transport

CRS Inspects Newly Doubled Nawada-Tilaiya Rail Section in ECR

The Commissioner of Railway Safety (CRS), Eastern Circle, Kolkata, Suvomoy Mitra conducted an inspection of the newly doubled Nawada-Tilaiya section under the Kiul-Gaya doubling project in Danapur Division. The inspection included a thorough assessment of the newly constructed double line and bridges in the section. As part of the evaluation, a speed trial was successfully carried out at 120 km/h using a special train between Nawada and Tilaiya. The inspection was attended by the Divisional Railway Manager (DRM) of Danapur Division, Jayant Kumar Choudhary, along with senior officials from the..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?