GMLR project cost rises by Rs 2.47 billion due to tunnel realignment
ROADS & HIGHWAYS

GMLR project cost rises by Rs 2.47 billion due to tunnel realignment

The Brihanmumbai Municipal Corporation (BMC) plans to realign the 4.7 km twin tunnels of the Goregaon-Mulund Link Road (GMLR) by 600 meters, resulting in a Rs 2.47 billion increase in the project?s cost. The total estimated cost for the tunnel project, initially set at Rs 63.01 billion, has faced criticism from opposition parties.

The GMLR project, a key infrastructure initiative, includes twin tunnels that will traverse the Sanjay Gandhi National Park?s diverse landscape of hills, forests, and farmlands. The realignment is prompted by objections from local tribal communities in Habale pada and Nagarmudi pada, who raised concerns about the impact of the tunnel construction on their livelihoods.

To address these concerns, the BMC has decided to shift the tunnel launch point 600 meters away from the original location in Habale pada. The proposed realignment will be reviewed by experts from the Indian Institutes of Technology (IIT) to ensure its feasibility.

A BMC official stated, ?We will begin construction by using a tunnel boring machine (TBM) and have obtained permission from Film City for the revised tunnel location. The realignment, necessitated by local objections, will increase the project cost by Rs 2.47 billion. The original tunnel cost was Rs 63.01 billion, with the total GMLR project estimated at Rs 85 billion.?

The cost escalation has drawn criticism from opposition leaders, including Ravi Raja, former Congress corporator, who has questioned the justification for the additional Rs 2.5 billion expense. Raja also expressed concerns about the contractor, Singla Pvt Ltd, and called for stringent external oversight by agencies like IIT.

The TBM will be assembled near the site, with tunnel construction expected to start in April 2025. The GMLR, connecting Goregaon in the western suburbs with Mulund in the eastern suburbs, will be approximately 12.2 km long, with the tunnels forming a 4.7 km portion of the third phase. The project is scheduled for completion by October 2028.

(The Indian Express)

The Brihanmumbai Municipal Corporation (BMC) plans to realign the 4.7 km twin tunnels of the Goregaon-Mulund Link Road (GMLR) by 600 meters, resulting in a Rs 2.47 billion increase in the project?s cost. The total estimated cost for the tunnel project, initially set at Rs 63.01 billion, has faced criticism from opposition parties. The GMLR project, a key infrastructure initiative, includes twin tunnels that will traverse the Sanjay Gandhi National Park?s diverse landscape of hills, forests, and farmlands. The realignment is prompted by objections from local tribal communities in Habale pada and Nagarmudi pada, who raised concerns about the impact of the tunnel construction on their livelihoods. To address these concerns, the BMC has decided to shift the tunnel launch point 600 meters away from the original location in Habale pada. The proposed realignment will be reviewed by experts from the Indian Institutes of Technology (IIT) to ensure its feasibility. A BMC official stated, ?We will begin construction by using a tunnel boring machine (TBM) and have obtained permission from Film City for the revised tunnel location. The realignment, necessitated by local objections, will increase the project cost by Rs 2.47 billion. The original tunnel cost was Rs 63.01 billion, with the total GMLR project estimated at Rs 85 billion.? The cost escalation has drawn criticism from opposition leaders, including Ravi Raja, former Congress corporator, who has questioned the justification for the additional Rs 2.5 billion expense. Raja also expressed concerns about the contractor, Singla Pvt Ltd, and called for stringent external oversight by agencies like IIT. The TBM will be assembled near the site, with tunnel construction expected to start in April 2025. The GMLR, connecting Goregaon in the western suburbs with Mulund in the eastern suburbs, will be approximately 12.2 km long, with the tunnels forming a 4.7 km portion of the third phase. The project is scheduled for completion by October 2028. (The Indian Express)

Next Story
Resources

Madhya Pradesh Champions Inclusive Tourism at Heritage Sites

On the occasion of World Heritage Day, Madhya Pradesh is taking a significant step toward inclusive tourism by making its historical sites accessible to all — especially persons with disabilities. The state is rolling out its ‘Accessibility Infrastructure and Development’ project at Maheshwar, Mandu, Dhar, and Orchha, aiming to create a more welcoming experience at these iconic cultural destinations.The initiative, under the leadership of Chief Minister Dr Mohan Yadav and Tourism Minister Shri Dharmendra Bhav Singh Lodhi, includes infrastructure upgrades such as ramps, Braille signage, w..

Next Story
Resources

Runwal Realty Onboards Sonam Kapoor as Brand Ambassador

Real estate major Runwal has unveiled a refreshed identity as Runwal Realty, signalling a renewed commitment to crafting spaces that stand the test of time. With this refresh, the brand unveils its new philosophy: “Building for Generations to Come” and welcomes Bollywood star and global fashion icon Sonam Kapoor as its brand ambassador. This evolved identity reflects Runwal Realty’s commitment to creating not just homes, but heirlooms—crafted through visionary design, meticulous planning, global design expertise and an unwavering focus on quality. With the customer at its core, each de..

Next Story
Infrastructure Urban

Emerging Trends in Infrastructure and Transport 2025: KPMG

KPMG’s latest report, The Great Reset: Emerging Trends in Infrastructure and Transport 2025 edition, sheds light on the profound changes transforming the global infrastructure landscape. As industries adapt to the challenges posed by climate change, economic pressures, and technological advancements, the report identifies key trends and provides actionable insights for leaders in infrastructure and transport sectors. “In today’s interconnected world, the lack of standardized supply chain practices is not just an operational challenge—it’s an environmental and economic one. We’..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?