Execution to remain strong while awards likely to remain subdued in 2019
ROADS & HIGHWAYS

Execution to remain strong while awards likely to remain subdued in 2019

According to rating firm ICRA outlook for the road sector, while the engineering, procurement and construction (EPC) project executions may witness a temporary slowdown during the general elections; the build-operate-transfer (BOT) and hybrid annuity model (HAM) projects executions are expected to continue unabated. Overall, a strong unexecuted pipeline and concerted effort on the right of way puts the NHAI on a strong footing and is set to witness sustained growth in execution in 2019.

The awards activity usually picks up substantially during the fourth quarter. Given the general elections in 2019, new award activity is likely to get affected in Q4 FY2019 and Q1 FY2020. Therefore, the awards will remain subdued owing to the general elections in 2019, according to the firm.

Credit profile of most industry players to be largely unaffected

Toll collections are expected to witness high single digit growth in 2019. However, high interest outgo due to leveraged balance sheets will continue to exert pressure on net profitability for the toll road projects. A significant pipeline of road projects to be awarded under the Bharatmala programme in the next three years is likely to boost the order book of medium-large size developers. Awarding projects after receiving all approvals is likely to reduce delays in execution and reduced idling of resources, thereby resulting in improved operating margins. Further, the toll-operate-transfer (TOT) awards are expected to crowd out the asset sale activity of private developers, resulting in lower stake sale transactions. Therefore, efforts to de-leverage the balance sheets through asset monetisation route are likely to get impacted.

NHAI’s borrowings to increase to fund the Bharatmala Pariyojana programme

Over the years, the NHAI’s expenditure increased primarily owing to the sharp increase in land acquisition cost. At the same time, budgetary support as a proportion of funding requirement for the NHAI steadily reduced, thereby increasing the dependence on internal and external budgetary resources (primarily debt). The total market borrowings for Bharatmala are estimated at Rs 209,279 crore till FY2022 (the total capital base including cess fund, toll collections and TOT proceeds is estimated at Rs 377,045 crore). At around Rs 60,000 crore per annum, the annual debt requirement is in line with that raised in the recent past. A major part of this is likely to be sourced from LIC and the EPFO.

Credit challenges persist

With banks facing a huge stressed asset problem, their ability to extend credit to the already stretched sectors like infrastructure will remain constrained. Lenders, in some cases, are insisting on higher as well as upfront equity infusion, particularly in the case of smaller players and developers with leveraged balance sheets. Many infrastructure players have raised funds through the corporate bond market for completed projects (replacing bank credit with bonds) – which is also one of the reasons for subdued growth of banking credit to the sector.

More than 90 per cent of the projects awarded under the HAM have achieved financial closure within the stipulated timeframe as per the concession agreement. Although the private sector banks have taken the lead in funding HAM projects, the FC-related challenges resurfaced in the recent past, given the stress in the banking system and with many PSU banks coming under prompt corrective action. Increasingly new developers are taking high exposure to HAM projects for whom achieving FC could be even more challenging in the current situation.

 

According to rating firm ICRA outlook for the road sector, while the engineering, procurement and construction (EPC) project executions may witness a temporary slowdown during the general elections; the build-operate-transfer (BOT) and hybrid annuity model (HAM) projects executions are expected to continue unabated. Overall, a strong unexecuted pipeline and concerted effort on the right of way puts the NHAI on a strong footing and is set to witness sustained growth in execution in 2019. The awards activity usually picks up substantially during the fourth quarter. Given the general elections in 2019, new award activity is likely to get affected in Q4 FY2019 and Q1 FY2020. Therefore, the awards will remain subdued owing to the general elections in 2019, according to the firm. Credit profile of most industry players to be largely unaffected Toll collections are expected to witness high single digit growth in 2019. However, high interest outgo due to leveraged balance sheets will continue to exert pressure on net profitability for the toll road projects. A significant pipeline of road projects to be awarded under the Bharatmala programme in the next three years is likely to boost the order book of medium-large size developers. Awarding projects after receiving all approvals is likely to reduce delays in execution and reduced idling of resources, thereby resulting in improved operating margins. Further, the toll-operate-transfer (TOT) awards are expected to crowd out the asset sale activity of private developers, resulting in lower stake sale transactions. Therefore, efforts to de-leverage the balance sheets through asset monetisation route are likely to get impacted. NHAI’s borrowings to increase to fund the Bharatmala Pariyojana programme Over the years, the NHAI’s expenditure increased primarily owing to the sharp increase in land acquisition cost. At the same time, budgetary support as a proportion of funding requirement for the NHAI steadily reduced, thereby increasing the dependence on internal and external budgetary resources (primarily debt). The total market borrowings for Bharatmala are estimated at Rs 209,279 crore till FY2022 (the total capital base including cess fund, toll collections and TOT proceeds is estimated at Rs 377,045 crore). At around Rs 60,000 crore per annum, the annual debt requirement is in line with that raised in the recent past. A major part of this is likely to be sourced from LIC and the EPFO. Credit challenges persist With banks facing a huge stressed asset problem, their ability to extend credit to the already stretched sectors like infrastructure will remain constrained. Lenders, in some cases, are insisting on higher as well as upfront equity infusion, particularly in the case of smaller players and developers with leveraged balance sheets. Many infrastructure players have raised funds through the corporate bond market for completed projects (replacing bank credit with bonds) – which is also one of the reasons for subdued growth of banking credit to the sector. More than 90 per cent of the projects awarded under the HAM have achieved financial closure within the stipulated timeframe as per the concession agreement. Although the private sector banks have taken the lead in funding HAM projects, the FC-related challenges resurfaced in the recent past, given the stress in the banking system and with many PSU banks coming under prompt corrective action. Increasingly new developers are taking high exposure to HAM projects for whom achieving FC could be even more challenging in the current situation.  

Next Story
Infrastructure Urban

CONCOR Launches Double-stack Service Between NCR and Varnama

State-run Container Corporation of India (CONCOR) has launched double-stack container train services between the National Capital Region (NCR) and Varnama near Baroda. This initiative aims to facilitate customers at Nhava Sheva near Mumbai, home to Jawaharlal Nehru Port (J N Port). On December 21, the first double-stack container train from Khatuwas and Dadri in NCR reached CONCOR’s Gati Shakti Multimodal Cargo Terminal (GCT) at Varnama, situated along the Western Dedicated Freight Corridor (WDFC). The train carried export cargo destined for J N Port, according to a statement from the state..

Next Story
Infrastructure Transport

Less than 10% of Rs 40 Billion State-aid for Shipbuilding Utilised

A government-sanctioned financial assistance program worth Rs 40 billion, intended to support local shipbuilders over a decade starting in April 2016, has seen minimal utilisation, with only Rs 3.85 billion—less than 10 per cent of the total fund—disbursed thus far. With 15 months remaining before the scheme concludes, its uptake has been limited. The financial aid applies to shipbuilding contracts signed between April 1, 2016, and March 31, 2026. According to a written response provided by Union Minister of Ports, Shipping, and Waterways Sarbananda Sonowal to the Rajya Sabha on December ..

Next Story
Infrastructure Transport

Civil Aviation Minister Opens New ATC Tower at Indore Airport

The Minister for Civil Aviation, Ram Mohan Naidu Kinjarapu, inaugurated the new Air Traffic Control (ATC) Tower-cum-technical block at Devi Ahilyabai Holkar International Airport in Indore, Madhya Pradesh. During the inauguration, the minister toured the facility, where ATC experts explained various technical aspects of tracking and coordinating flights from the newly constructed tower. In addition to the ATC tower, the airport has also introduced a zero-waste plant. The union minister confirmed that this initiative aligns with the government’s commitment to sustainability. Minister Ki..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000