Contractual dispute settlement scheme launched
ROADS & HIGHWAYS

Contractual dispute settlement scheme launched

The land acquisition process for the long-awaited Kundannoor-Angamaly NH Bypass is yet to begin as we are waiting for the concurrence of the Union Ministry of Road Transport and Highways (MoRTH). In January, the National Highways Authority of India (NHAI) approved the alignment of the 44-km stretch, with expectations that the project would be commissioned by early 2027. However, due to procedural complexities, motorists and landowners whose land would be acquired for the project were doubtful about meeting the deadline.

The Kundannoor-Angamaly NH Bypass is a crucial corridor that was proposed in 2016 to ease congestion on the Edappally-Aroor NH 66 Bypass, which is heavily used by approximately one lakh passenger car units daily. It also aims to alleviate traffic congestion on the Edappally-Angamaly NH 544 stretch. The lack of alternative corridors exacerbates traffic snarls, particularly at the poorly planned Edappally Junction, where the two corridors intersect.

MoRTH's concurrence is necessary to finalize and publish the 3(A) notification issued under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation, and Resettlement (LARR) Act, 2013. A draft notification had been prepared earlier in the year, but the delay was due to a policy decision the State government had to make regarding exempting the project and the Kollam-Shengottai highway development project from State GST. The State had initially stated its inability to contribute 25% of the project's land acquisition cost.

Once the 3(A) notification is published, a public hearing will be conducted under Section 3(C) of the Act as part of the land acquisition process.

This will be followed by the survey and demarcation of individual plots of land required for the highway project. While these steps could be completed within a couple of months, the consolidation of survey results and their publication, as per Section 3(D) of the Act, would take around six months. This is mainly because approximately 287 hectares of land, including paddy fields, scattered across the 44-km distance, need to be acquired.

Also read:
BMC Awards NCC-J Kumar JV Contract for GMLR Twin Tunnels
NHIDCL collaborates with NIT Jamshedpur for Innovative Highway Solution


The land acquisition process for the long-awaited Kundannoor-Angamaly NH Bypass is yet to begin as we are waiting for the concurrence of the Union Ministry of Road Transport and Highways (MoRTH). In January, the National Highways Authority of India (NHAI) approved the alignment of the 44-km stretch, with expectations that the project would be commissioned by early 2027. However, due to procedural complexities, motorists and landowners whose land would be acquired for the project were doubtful about meeting the deadline. The Kundannoor-Angamaly NH Bypass is a crucial corridor that was proposed in 2016 to ease congestion on the Edappally-Aroor NH 66 Bypass, which is heavily used by approximately one lakh passenger car units daily. It also aims to alleviate traffic congestion on the Edappally-Angamaly NH 544 stretch. The lack of alternative corridors exacerbates traffic snarls, particularly at the poorly planned Edappally Junction, where the two corridors intersect. MoRTH's concurrence is necessary to finalize and publish the 3(A) notification issued under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation, and Resettlement (LARR) Act, 2013. A draft notification had been prepared earlier in the year, but the delay was due to a policy decision the State government had to make regarding exempting the project and the Kollam-Shengottai highway development project from State GST. The State had initially stated its inability to contribute 25% of the project's land acquisition cost. Once the 3(A) notification is published, a public hearing will be conducted under Section 3(C) of the Act as part of the land acquisition process. This will be followed by the survey and demarcation of individual plots of land required for the highway project. While these steps could be completed within a couple of months, the consolidation of survey results and their publication, as per Section 3(D) of the Act, would take around six months. This is mainly because approximately 287 hectares of land, including paddy fields, scattered across the 44-km distance, need to be acquired. Also read: BMC Awards NCC-J Kumar JV Contract for GMLR Twin TunnelsNHIDCL collaborates with NIT Jamshedpur for Innovative Highway Solution

Next Story
Infrastructure Urban

Arya Omnitalk Powers India’s Toll Revolution with AI-Driven Solutions

Arya Omnitalk, a leader in intelligent transportation systems, is revolutionising toll collection across India’s national highways with its advanced AI-powered Toll Management Solutions. Designed for rugged remote toll locations, the company’s cutting-edge technology ensures seamless, reliable, and secure tolling—especially during high-capacity operations exceeding 200%. By integrating real-time analytics, cyber protection, and FASTag-based cashless tolling, Arya Omnitalk’s systems are significantly reducing congestion, improving transparency, and enhancing revenue assurance. Its full..

Next Story
Infrastructure Urban

Over 800 Join Anant Raj Runathon to Mark Earth Day

Over 800 participants came together at Anant Raj Estate, Sector 63A, Gurugram, for the Anant Raj Runathon 2025—a vibrant celebration of Earth Day through fitness, community bonding, and sustainability. Curated by renowned running coach Ravinder, the event featured four categories: 10-mile and 5-mile timed runs, a 5-mile walkathon, and a 1-mile kids’ run. Runners of all ages took to the green, scenic roads of the area—some chasing personal bests, others running for a cause. The Runathon was designed to promote healthy living while raising awareness about sustainable practices. Participa..

Next Story
Infrastructure Urban

PETRONAS Lubricants, Quaker Houghton Ink Strategic Deal

In a significant step towards strengthening industrial operations in India and Malaysia, PETRONAS Lubricants India Pvt. Ltd (PLIPL) and Quaker Houghton have announced a strategic partnership aimed at delivering high-performance industrial fluid solutions to key manufacturing sectors, including steel production. The collaboration combines the strengths of both companies—leveraging PETRONAS Lubricants India’s maintenance lubricant technologies and Quaker Houghton’s deep expertise in metalworking fluids. Starting from the second quarter of 2025, Quaker Houghton will begin offering PETRONAS..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?