CAG Audit exposes discrepancies in BBP-1 implementation
ROADS & HIGHWAYS

CAG Audit exposes discrepancies in BBP-1 implementation

The audit report by the Comptroller and Auditor General of India (CAG) regarding the 'Implementation of Phase-I of Bharatmala Pariyojana (BPP-1)' has brought to light significant revelations. The report highlights that the National Highway Authority of India (NHAI) Board sanctioned the Dwarka Expressway at a civil cost of Rs 72.87 billion, equating to Rs 2.50 billion per kilometre. This stands in stark contrast to the per kilometre civil cost of Rs 182 million that had been approved by the Cabinet Committee on Economic Affairs (CCEA).

In addition, the report uncovers that the Delhi-Vadodara Expressway, with an estimated civil cost of approximately Rs 328.39 billion, was endorsed by the NHAI Board even though it had not been included in the list of BPP-I projects approved by the CCEA.

The report sheds light on the fact that NHAI was responsible for the development of 70,950 km out of the designated 76,999 km of national highways for BPP-I. The NHAI was granted the authority to determine the construction approach for its projects. However, the audit discerned that NHAI was making decisions about construction methods without proper documented justifications.

According to the CAG report, "The audit also noticed that the evaluation and approval framework initially proposed to the CCEA failed to establish clear definitions for the terms 'project' and 'package'. As a result, the determination of whether construction packages within a single project should be regarded as individual projects or combined as one comprehensive project lacked clarity."

The CAG report further expounds that the appraisal and endorsement framework stipulated by the CCEA for BPP-I was not being adhered to by the entities responsible for project execution.

"The analysis encompassed a sample of 50 NHAI projects, and among these, eight projects had not undergone appraisal by the Project Appraisal and Technical Scrutiny Committee. This omission occurred due to the projects either being evaluated under the previous NHDP program or classified as balance works or one-time improvement initiatives," the report elucidated.

The audit report by the Comptroller and Auditor General of India (CAG) regarding the 'Implementation of Phase-I of Bharatmala Pariyojana (BPP-1)' has brought to light significant revelations. The report highlights that the National Highway Authority of India (NHAI) Board sanctioned the Dwarka Expressway at a civil cost of Rs 72.87 billion, equating to Rs 2.50 billion per kilometre. This stands in stark contrast to the per kilometre civil cost of Rs 182 million that had been approved by the Cabinet Committee on Economic Affairs (CCEA).In addition, the report uncovers that the Delhi-Vadodara Expressway, with an estimated civil cost of approximately Rs 328.39 billion, was endorsed by the NHAI Board even though it had not been included in the list of BPP-I projects approved by the CCEA.The report sheds light on the fact that NHAI was responsible for the development of 70,950 km out of the designated 76,999 km of national highways for BPP-I. The NHAI was granted the authority to determine the construction approach for its projects. However, the audit discerned that NHAI was making decisions about construction methods without proper documented justifications.According to the CAG report, The audit also noticed that the evaluation and approval framework initially proposed to the CCEA failed to establish clear definitions for the terms 'project' and 'package'. As a result, the determination of whether construction packages within a single project should be regarded as individual projects or combined as one comprehensive project lacked clarity.The CAG report further expounds that the appraisal and endorsement framework stipulated by the CCEA for BPP-I was not being adhered to by the entities responsible for project execution.The analysis encompassed a sample of 50 NHAI projects, and among these, eight projects had not undergone appraisal by the Project Appraisal and Technical Scrutiny Committee. This omission occurred due to the projects either being evaluated under the previous NHDP program or classified as balance works or one-time improvement initiatives, the report elucidated.

Next Story
Infrastructure Urban

Shoals' Q3 2024 revenue falls 23.9% due to project delays, supply chain

Shoals Technologies Group, a U.S.-headquartered manufacturer of electrical balance of systems (EBOS) for solar, energy storage, and e-mobility, reported a 23.9% year-over-year (YoY) decline in revenue, which dropped to $102.2 million in the third quarter (Q3) of 2024. This decline was mainly attributed to project delays and supply chain disruptions. The company posted a net loss of $300,000, a significant improvement compared to the $9.8 million net loss in Q3 2023. Adjusted net income was reported at $13.9 million, reflecting a 58.2% YoY decrease. Adjusted EBITDA stood at $24.5 million, a 4..

Next Story
Infrastructure Energy

FTC Solar sees 67% YoY decline in Q3 revenue from lower volumes

FTC Solar, a U.S.-based provider of solar tracker systems, reported a revenue of $10.14 million in the third quarter (Q3) of 2024, surpassing analyst expectations by $240,680. However, this figure marked a 66.8% year-over-year (YoY) decline compared to the same quarter in 2023, primarily attributed to reduced product volumes. The decline in solar tracker revenue was mainly due to an 82% decrease in the amount of MW produced, which was negatively impacted by delays in customer projects. This was partially offset by an increase in the average selling price (ASP), which led to better pricing an..

Next Story
Infrastructure Urban

Dilip Buildcon wins bid for BharatNet Phase III broadband project

Dilip Buildcon announced on Tuesday, November 12, that its STL-DBL consortium had submitted the lowest bid for BSNL's BharatNet Phase III broadband connectivity project. The USOF-funded project, which aims to provide middle and last-mile connectivity in Jammu Kashmir and Ladakh, is valued at Rs.1,625.36 Crore. Dilip Buildcon holds a 70.23% stake in the implementation of the project. The project is expected to be completed in three years, and the corporation will secure a 10-year maintenance contract. In recent days, BSNL has awarded several contracts for the BharatNet project. On Monday, No..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000