+
BMC plans ambitious WEH Elevated Corridor with cable-stayed bridges
ROADS & HIGHWAYS

BMC plans ambitious WEH Elevated Corridor with cable-stayed bridges

In order to alleviate the chronic congestion on the Western Express Highway (WEH) and facilitate smooth vehicular movement from Mahim to Dahisar, the Brihanmumbai Municipal Corporation (BMC) is proposing the construction of an elevated corridor using cable-stayed bridges. This ambitious project, directed by Chief Minister Eknath Shinde, aims to enhance access control and improve traffic flow along the route.

The estimated cost of the WEH elevated corridor project is approximately Rs 55 billion. It involves the construction of elevated corridors spanning a distance of 15.3 kilometers, while the total length of the highway is approximately 25 kilometers. The elevated section will comprise three to four single-pier cable-stayed bridges, which will be connected to underpasses at various junctions.

To implement this project, the BMC will need to dismantle several existing flyovers to make room for the cable-stayed bridges. This will not only create additional lanes beneath the bridges but also free up space below them. The WEH elevated corridor is expected to take around four years to complete, with tendering commencing after the preparation of a detailed project report and government approval. The BMC anticipates finalising the DPR within the next five to six months.

The project aims to increase the number of lanes on both carriageways to 14 or 16, including lanes beneath the bridges. Underpasses will be constructed at key junctions like Kala Nagar, JVLR, and Aarey to ensure smooth movement of vehicles transitioning from arterial roads to the highway, minimising disruptions. The concept plan for the elevated corridor was developed by a consultant following a techno-economic feasibility study, which considered future traffic projections and incorporated pedestrian-friendly amenities. 

According to the study, the current highway consists of five lanes in each direction, with service roads accounting for approximately 50 per cent of the total length. However, the highway experiences significant traffic volume, ranging from 220,000 to 380,000 passenger car units per day, with peak volumes exceeding 10,000 PCU at multiple junctions, resulting in severe congestion.

The proposed concept design outlines a 15.3-kilometer elevated corridor between Mahim and Malad, divided into three to four sections featuring long single-pier cable-stayed bridges. Each flyover is expected to span two to three junctions. Presently, the express highway has six lanes on both carriageways of the bridges and four lanes on adjacent slip roads, making it a total of 10 lanes. The concept design suggests eight lanes on the bridges and either six or eight lanes on the road beneath and adjoining the bridges, bringing the total number of lanes to 14 or 16 on both carriageways. Traffic barriers will be installed to segregate traffic between these lengthy flyovers. To address cross-directional traffic issues, underpasses will be constructed at various junctions and bottlenecks. However, the concept design is subject to change based on the detailed project report.

Officials estimate that the implementation of the WEH elevated corridor project will take approximately four years, following a sequential construction methodology to minimise disruptions to traffic. The upgraded corridor is expected to include pedestrian facilities such as wider sidewalks and landscaped median spaces, providing a more pedestrian-friendly environment.

In order to alleviate the chronic congestion on the Western Express Highway (WEH) and facilitate smooth vehicular movement from Mahim to Dahisar, the Brihanmumbai Municipal Corporation (BMC) is proposing the construction of an elevated corridor using cable-stayed bridges. This ambitious project, directed by Chief Minister Eknath Shinde, aims to enhance access control and improve traffic flow along the route.The estimated cost of the WEH elevated corridor project is approximately Rs 55 billion. It involves the construction of elevated corridors spanning a distance of 15.3 kilometers, while the total length of the highway is approximately 25 kilometers. The elevated section will comprise three to four single-pier cable-stayed bridges, which will be connected to underpasses at various junctions.To implement this project, the BMC will need to dismantle several existing flyovers to make room for the cable-stayed bridges. This will not only create additional lanes beneath the bridges but also free up space below them. The WEH elevated corridor is expected to take around four years to complete, with tendering commencing after the preparation of a detailed project report and government approval. The BMC anticipates finalising the DPR within the next five to six months.The project aims to increase the number of lanes on both carriageways to 14 or 16, including lanes beneath the bridges. Underpasses will be constructed at key junctions like Kala Nagar, JVLR, and Aarey to ensure smooth movement of vehicles transitioning from arterial roads to the highway, minimising disruptions. The concept plan for the elevated corridor was developed by a consultant following a techno-economic feasibility study, which considered future traffic projections and incorporated pedestrian-friendly amenities. According to the study, the current highway consists of five lanes in each direction, with service roads accounting for approximately 50 per cent of the total length. However, the highway experiences significant traffic volume, ranging from 220,000 to 380,000 passenger car units per day, with peak volumes exceeding 10,000 PCU at multiple junctions, resulting in severe congestion.The proposed concept design outlines a 15.3-kilometer elevated corridor between Mahim and Malad, divided into three to four sections featuring long single-pier cable-stayed bridges. Each flyover is expected to span two to three junctions. Presently, the express highway has six lanes on both carriageways of the bridges and four lanes on adjacent slip roads, making it a total of 10 lanes. The concept design suggests eight lanes on the bridges and either six or eight lanes on the road beneath and adjoining the bridges, bringing the total number of lanes to 14 or 16 on both carriageways. Traffic barriers will be installed to segregate traffic between these lengthy flyovers. To address cross-directional traffic issues, underpasses will be constructed at various junctions and bottlenecks. However, the concept design is subject to change based on the detailed project report.Officials estimate that the implementation of the WEH elevated corridor project will take approximately four years, following a sequential construction methodology to minimise disruptions to traffic. The upgraded corridor is expected to include pedestrian facilities such as wider sidewalks and landscaped median spaces, providing a more pedestrian-friendly environment.

Next Story
Infrastructure Urban

Digital First: Bridging the Skilled Talent Gap in India’s Construction Sector

India stands at a defining juncture in its economic journey as it accelerates toward becoming a US$7 trillion economy by 2030. India’s construction sector, encompassing infrastructure and real estate development will play a pivotal role in its economic transformation. Expansion in developments such as the national highways, smart cities, airports, metro networks, logistics hubs, housing, etc. underscores the physical expression of India’s development ambition. The construction sector is already the second-largest contributor to India’s GDP, accounting for nearly 18 per cent of total..

Next Story
Infrastructure Transport

Titagarh Rail to Raise Rs 2 billion via Preferential Allotment to Promoters

Titagarh Rail Systems has announced a proposal to raise approximately Rs 2 billion through a preferential issue of 21,16,402 convertible warrants to members of its Promoter Group. The board of directors approved the move at its meeting held on July 9, 2025, subject to shareholder and regulatory approvals. The warrants, priced at Rs 945 each, will be allotted to Mrs Rashmi Chowdhary and Mr Prithish Chowdhary in line with Chapter V of SEBI’s ICDR Regulations. Each warrant is convertible into one equity share of ₹2 face value within 18 months from the date of allotment.   ..

Next Story
Real Estate

Hindware Strengthens Eastern Footprint with New Brand Store in Kolkata

Bathware major Hindware has expanded its retail footprint in West Bengal with the launch of a new state-of-the-art brand store in Ichapore, Kolkata. This marks the company’s fourth brand store in the city and 30th in the state, underlining its strategic focus on the eastern market. The newly launched store, operated by Tirupati Sales Corporation, showcases the entire spectrum of Hindware’s bathware offerings, including sanitaryware, faucets, showers, basins, and products from its premium lines — Queo and the Hindware Italian Collection. It is aimed at providing an immersive experien..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?