BMC plans ambitious WEH Elevated Corridor with cable-stayed bridges
ROADS & HIGHWAYS

BMC plans ambitious WEH Elevated Corridor with cable-stayed bridges

In order to alleviate the chronic congestion on the Western Express Highway (WEH) and facilitate smooth vehicular movement from Mahim to Dahisar, the Brihanmumbai Municipal Corporation (BMC) is proposing the construction of an elevated corridor using cable-stayed bridges. This ambitious project, directed by Chief Minister Eknath Shinde, aims to enhance access control and improve traffic flow along the route.

The estimated cost of the WEH elevated corridor project is approximately Rs 55 billion. It involves the construction of elevated corridors spanning a distance of 15.3 kilometers, while the total length of the highway is approximately 25 kilometers. The elevated section will comprise three to four single-pier cable-stayed bridges, which will be connected to underpasses at various junctions.

To implement this project, the BMC will need to dismantle several existing flyovers to make room for the cable-stayed bridges. This will not only create additional lanes beneath the bridges but also free up space below them. The WEH elevated corridor is expected to take around four years to complete, with tendering commencing after the preparation of a detailed project report and government approval. The BMC anticipates finalising the DPR within the next five to six months.

The project aims to increase the number of lanes on both carriageways to 14 or 16, including lanes beneath the bridges. Underpasses will be constructed at key junctions like Kala Nagar, JVLR, and Aarey to ensure smooth movement of vehicles transitioning from arterial roads to the highway, minimising disruptions. The concept plan for the elevated corridor was developed by a consultant following a techno-economic feasibility study, which considered future traffic projections and incorporated pedestrian-friendly amenities. 

According to the study, the current highway consists of five lanes in each direction, with service roads accounting for approximately 50 per cent of the total length. However, the highway experiences significant traffic volume, ranging from 220,000 to 380,000 passenger car units per day, with peak volumes exceeding 10,000 PCU at multiple junctions, resulting in severe congestion.

The proposed concept design outlines a 15.3-kilometer elevated corridor between Mahim and Malad, divided into three to four sections featuring long single-pier cable-stayed bridges. Each flyover is expected to span two to three junctions. Presently, the express highway has six lanes on both carriageways of the bridges and four lanes on adjacent slip roads, making it a total of 10 lanes. The concept design suggests eight lanes on the bridges and either six or eight lanes on the road beneath and adjoining the bridges, bringing the total number of lanes to 14 or 16 on both carriageways. Traffic barriers will be installed to segregate traffic between these lengthy flyovers. To address cross-directional traffic issues, underpasses will be constructed at various junctions and bottlenecks. However, the concept design is subject to change based on the detailed project report.

Officials estimate that the implementation of the WEH elevated corridor project will take approximately four years, following a sequential construction methodology to minimise disruptions to traffic. The upgraded corridor is expected to include pedestrian facilities such as wider sidewalks and landscaped median spaces, providing a more pedestrian-friendly environment.

In order to alleviate the chronic congestion on the Western Express Highway (WEH) and facilitate smooth vehicular movement from Mahim to Dahisar, the Brihanmumbai Municipal Corporation (BMC) is proposing the construction of an elevated corridor using cable-stayed bridges. This ambitious project, directed by Chief Minister Eknath Shinde, aims to enhance access control and improve traffic flow along the route.The estimated cost of the WEH elevated corridor project is approximately Rs 55 billion. It involves the construction of elevated corridors spanning a distance of 15.3 kilometers, while the total length of the highway is approximately 25 kilometers. The elevated section will comprise three to four single-pier cable-stayed bridges, which will be connected to underpasses at various junctions.To implement this project, the BMC will need to dismantle several existing flyovers to make room for the cable-stayed bridges. This will not only create additional lanes beneath the bridges but also free up space below them. The WEH elevated corridor is expected to take around four years to complete, with tendering commencing after the preparation of a detailed project report and government approval. The BMC anticipates finalising the DPR within the next five to six months.The project aims to increase the number of lanes on both carriageways to 14 or 16, including lanes beneath the bridges. Underpasses will be constructed at key junctions like Kala Nagar, JVLR, and Aarey to ensure smooth movement of vehicles transitioning from arterial roads to the highway, minimising disruptions. The concept plan for the elevated corridor was developed by a consultant following a techno-economic feasibility study, which considered future traffic projections and incorporated pedestrian-friendly amenities. According to the study, the current highway consists of five lanes in each direction, with service roads accounting for approximately 50 per cent of the total length. However, the highway experiences significant traffic volume, ranging from 220,000 to 380,000 passenger car units per day, with peak volumes exceeding 10,000 PCU at multiple junctions, resulting in severe congestion.The proposed concept design outlines a 15.3-kilometer elevated corridor between Mahim and Malad, divided into three to four sections featuring long single-pier cable-stayed bridges. Each flyover is expected to span two to three junctions. Presently, the express highway has six lanes on both carriageways of the bridges and four lanes on adjacent slip roads, making it a total of 10 lanes. The concept design suggests eight lanes on the bridges and either six or eight lanes on the road beneath and adjoining the bridges, bringing the total number of lanes to 14 or 16 on both carriageways. Traffic barriers will be installed to segregate traffic between these lengthy flyovers. To address cross-directional traffic issues, underpasses will be constructed at various junctions and bottlenecks. However, the concept design is subject to change based on the detailed project report.Officials estimate that the implementation of the WEH elevated corridor project will take approximately four years, following a sequential construction methodology to minimise disruptions to traffic. The upgraded corridor is expected to include pedestrian facilities such as wider sidewalks and landscaped median spaces, providing a more pedestrian-friendly environment.

Next Story
Infrastructure Urban

Greenply Launches Ecotec Prime Plywood

Greenply Industries has launched Ecotec Prime, strengthening its economy plywood portfolio with a product designed to offer both fire and water protection. The plywood combines IS 5509 certified fire-retardant technology with Boiling Waterproof grade performance.The company said the launch addresses a gap in the affordable plywood segment, where safety-led features have largely been limited to premium categories. Backed by a 20-year warranty, Ecotec Prime is positioned for homes, offices, commercial spaces, hospitals, hotels, malls and government projects.Greenply said the product aims to make..

Next Story
Infrastructure Energy

BorgWarner Wins Two Asian Powertrain Orders

BorgWarner has secured two new conquest programme awards in Asia, strengthening its propulsion and drivetrain business. The awards include a latest-generation wet dual clutch for a Chinese OEM’s SUV platform and a torsional assist variable cam timing system for a Japanese OEM’s next-generation hybrid engine.The wet dual clutch combines high-performance wet friction materials with an optimised groove design to reduce drag torque, improving transmission efficiency and fuel economy. It also offers smoother launch and shift performance at lower actuation pressure, while an integrated wave spri..

Next Story
Real Estate

42MM Designs Climate-Responsive Summer Home

42MM Architecture has introduced Spaces That Breathe: Designing Homes Around Summer Rhythms, a residence designed around the realities of Indian summers. The home responds to heat through built form, orientation, shading and material use rather than relying primarily on applied systems.The design is arranged as layered volumes, with projecting upper floors, recessed glazing, shaded edges, vertical fins and screened facades helping reduce heat gain while supporting controlled ventilation. A central landscaped court brings light and air into the house, while living areas are oriented towards thi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement