BMC plans ambitious WEH Elevated Corridor with cable-stayed bridges
ROADS & HIGHWAYS

BMC plans ambitious WEH Elevated Corridor with cable-stayed bridges

In order to alleviate the chronic congestion on the Western Express Highway (WEH) and facilitate smooth vehicular movement from Mahim to Dahisar, the Brihanmumbai Municipal Corporation (BMC) is proposing the construction of an elevated corridor using cable-stayed bridges. This ambitious project, directed by Chief Minister Eknath Shinde, aims to enhance access control and improve traffic flow along the route.

The estimated cost of the WEH elevated corridor project is approximately Rs 55 billion. It involves the construction of elevated corridors spanning a distance of 15.3 kilometers, while the total length of the highway is approximately 25 kilometers. The elevated section will comprise three to four single-pier cable-stayed bridges, which will be connected to underpasses at various junctions.

To implement this project, the BMC will need to dismantle several existing flyovers to make room for the cable-stayed bridges. This will not only create additional lanes beneath the bridges but also free up space below them. The WEH elevated corridor is expected to take around four years to complete, with tendering commencing after the preparation of a detailed project report and government approval. The BMC anticipates finalising the DPR within the next five to six months.

The project aims to increase the number of lanes on both carriageways to 14 or 16, including lanes beneath the bridges. Underpasses will be constructed at key junctions like Kala Nagar, JVLR, and Aarey to ensure smooth movement of vehicles transitioning from arterial roads to the highway, minimising disruptions. The concept plan for the elevated corridor was developed by a consultant following a techno-economic feasibility study, which considered future traffic projections and incorporated pedestrian-friendly amenities. 

According to the study, the current highway consists of five lanes in each direction, with service roads accounting for approximately 50 per cent of the total length. However, the highway experiences significant traffic volume, ranging from 220,000 to 380,000 passenger car units per day, with peak volumes exceeding 10,000 PCU at multiple junctions, resulting in severe congestion.

The proposed concept design outlines a 15.3-kilometer elevated corridor between Mahim and Malad, divided into three to four sections featuring long single-pier cable-stayed bridges. Each flyover is expected to span two to three junctions. Presently, the express highway has six lanes on both carriageways of the bridges and four lanes on adjacent slip roads, making it a total of 10 lanes. The concept design suggests eight lanes on the bridges and either six or eight lanes on the road beneath and adjoining the bridges, bringing the total number of lanes to 14 or 16 on both carriageways. Traffic barriers will be installed to segregate traffic between these lengthy flyovers. To address cross-directional traffic issues, underpasses will be constructed at various junctions and bottlenecks. However, the concept design is subject to change based on the detailed project report.

Officials estimate that the implementation of the WEH elevated corridor project will take approximately four years, following a sequential construction methodology to minimise disruptions to traffic. The upgraded corridor is expected to include pedestrian facilities such as wider sidewalks and landscaped median spaces, providing a more pedestrian-friendly environment.

In order to alleviate the chronic congestion on the Western Express Highway (WEH) and facilitate smooth vehicular movement from Mahim to Dahisar, the Brihanmumbai Municipal Corporation (BMC) is proposing the construction of an elevated corridor using cable-stayed bridges. This ambitious project, directed by Chief Minister Eknath Shinde, aims to enhance access control and improve traffic flow along the route.The estimated cost of the WEH elevated corridor project is approximately Rs 55 billion. It involves the construction of elevated corridors spanning a distance of 15.3 kilometers, while the total length of the highway is approximately 25 kilometers. The elevated section will comprise three to four single-pier cable-stayed bridges, which will be connected to underpasses at various junctions.To implement this project, the BMC will need to dismantle several existing flyovers to make room for the cable-stayed bridges. This will not only create additional lanes beneath the bridges but also free up space below them. The WEH elevated corridor is expected to take around four years to complete, with tendering commencing after the preparation of a detailed project report and government approval. The BMC anticipates finalising the DPR within the next five to six months.The project aims to increase the number of lanes on both carriageways to 14 or 16, including lanes beneath the bridges. Underpasses will be constructed at key junctions like Kala Nagar, JVLR, and Aarey to ensure smooth movement of vehicles transitioning from arterial roads to the highway, minimising disruptions. The concept plan for the elevated corridor was developed by a consultant following a techno-economic feasibility study, which considered future traffic projections and incorporated pedestrian-friendly amenities. According to the study, the current highway consists of five lanes in each direction, with service roads accounting for approximately 50 per cent of the total length. However, the highway experiences significant traffic volume, ranging from 220,000 to 380,000 passenger car units per day, with peak volumes exceeding 10,000 PCU at multiple junctions, resulting in severe congestion.The proposed concept design outlines a 15.3-kilometer elevated corridor between Mahim and Malad, divided into three to four sections featuring long single-pier cable-stayed bridges. Each flyover is expected to span two to three junctions. Presently, the express highway has six lanes on both carriageways of the bridges and four lanes on adjacent slip roads, making it a total of 10 lanes. The concept design suggests eight lanes on the bridges and either six or eight lanes on the road beneath and adjoining the bridges, bringing the total number of lanes to 14 or 16 on both carriageways. Traffic barriers will be installed to segregate traffic between these lengthy flyovers. To address cross-directional traffic issues, underpasses will be constructed at various junctions and bottlenecks. However, the concept design is subject to change based on the detailed project report.Officials estimate that the implementation of the WEH elevated corridor project will take approximately four years, following a sequential construction methodology to minimise disruptions to traffic. The upgraded corridor is expected to include pedestrian facilities such as wider sidewalks and landscaped median spaces, providing a more pedestrian-friendly environment.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code