BMC is yet to recover Rs 0.65 billion fine pending for road contractor
ROADS & HIGHWAYS

BMC is yet to recover Rs 0.65 billion fine pending for road contractor

As the company dragged it into arbitration in February, former Colaba corporator Makarand Narwekar from the BJP claimed that BMC is still owed Rs 64.6 billion, which it terminated four months after it handed down a penalty of Rs 16.00 billion to be paid within 30 days for cement concrete (CC) road works in Mumbai for the second time.

This is the first instance in which a contractor has brought the civic body into arbitration following the termination of a contract in recent memory. In the arbitration matter, Narwekar insisted that BMC choose a special counsel. Narwekar stated that, according to the BMC order, the penalty needed to be paid within 30 days. He demanded that the BMC initiate a civil suit against the contractor for the payment of the penalty. He questioned why the BMC was delaying action and allowing the contractor to exploit the civic body. Narwekar emphasised the necessity for the civic body to take firm action against contractors, considering taxpayer funds were involved. He also mentioned that by the onset of the monsoon in June, 50% of the scheduled 397 km of cement concrete (CC) road works in the city were supposed to be completed, but only 25% of that target had been achieved. Narwekar pointed out that CM Eknath Shinde himself had instructed BMC to concrete all roads. He requested municipal commissioner Bhushan Gagrani release a status report on CC roads by June 1. Narwekar stated that out of the 2050-km network of roads in Mumbai, just over 1,200 km had been concretized. In November 2023, BMC terminated RSIIL's contract for the first time for failing to initiate work. Two months later, it awarded CC contracts for 397 km of roads in the eastern and western suburbs worth Rs 60.80 billion. Officials acknowledged that only 25% of this work had been completed. They explained that when RSIIL was awarded its contract in January 2023, 50 stretches were supposed to be ready before the last monsoon. Subsequently, 400 stretches were to be taken up from October 2023 to May 2024, and the last 450 stretches were scheduled for October 2024 to May 2025. Narwekar stated that the achievement of these deadlines could only be ascertained through a status report.

As the company dragged it into arbitration in February, former Colaba corporator Makarand Narwekar from the BJP claimed that BMC is still owed Rs 64.6 billion, which it terminated four months after it handed down a penalty of Rs 16.00 billion to be paid within 30 days for cement concrete (CC) road works in Mumbai for the second time. This is the first instance in which a contractor has brought the civic body into arbitration following the termination of a contract in recent memory. In the arbitration matter, Narwekar insisted that BMC choose a special counsel. Narwekar stated that, according to the BMC order, the penalty needed to be paid within 30 days. He demanded that the BMC initiate a civil suit against the contractor for the payment of the penalty. He questioned why the BMC was delaying action and allowing the contractor to exploit the civic body. Narwekar emphasised the necessity for the civic body to take firm action against contractors, considering taxpayer funds were involved. He also mentioned that by the onset of the monsoon in June, 50% of the scheduled 397 km of cement concrete (CC) road works in the city were supposed to be completed, but only 25% of that target had been achieved. Narwekar pointed out that CM Eknath Shinde himself had instructed BMC to concrete all roads. He requested municipal commissioner Bhushan Gagrani release a status report on CC roads by June 1. Narwekar stated that out of the 2050-km network of roads in Mumbai, just over 1,200 km had been concretized. In November 2023, BMC terminated RSIIL's contract for the first time for failing to initiate work. Two months later, it awarded CC contracts for 397 km of roads in the eastern and western suburbs worth Rs 60.80 billion. Officials acknowledged that only 25% of this work had been completed. They explained that when RSIIL was awarded its contract in January 2023, 50 stretches were supposed to be ready before the last monsoon. Subsequently, 400 stretches were to be taken up from October 2023 to May 2024, and the last 450 stretches were scheduled for October 2024 to May 2025. Narwekar stated that the achievement of these deadlines could only be ascertained through a status report.

Next Story
Real Estate

MARC Auditorium

Spanning 80 acre on the outskirts of Bengaluru, the Manipal Academy of Higher Education (MAHE) recently inaugurated the Dr Ramdas M Pai Convention Hall and Food Court (MARC), a 123,000-sq-ft facility comprising a 1,200-seater auditorium above and a two-level food court below.Elaborating on the design framework, Akshay Heranjal, Co-Founder and Principal Architect, The Purple Ink Studio, remarks, “The design programme included two distinct facilities: a food court spanning two (lower) levels and a 1,200-seater auditorium positioned above. A rectangular soft enclosure of a p..

Next Story
Infrastructure Transport

Ceigall 2.0 has begun and the journey ahead looks promising

"We are a nearly 23-year-old company and if I had to define Ceigall, it’s simple – what comes on the road, we build it,” said Ramneek Sehgal, Managing Director of Ceigall India, which is known for its ability to deliver complex projects on time, such as the successful completion of the Katra Expressway. “Ceigall is making its mark in India's construction landscape. From highways, expressways and elevated roads to railways, metro railways, runways and tunnels – you name it, we do it. Beyond roads, we’re also into utilities and solar energy projects. We've already installed thre..

Next Story
Infrastructure Urban

Hyderabad Ranked Fastest Growing City for Infra Development

Hyderabad has emerged as the fastest-growing city in India among the top six, excelling in key areas such as governance, socio-economic profile, physical infrastructure, and real estate. According to the latest India Prime City Index report by Knight Frank India, the city has experienced remarkable growth, driven by extensive infrastructure projects, a surge in real estate demand, and a rising population of ultra-high-net-worth individuals (UHNWIs) and high-net-worth individuals (HNWIs). Proactive policy initiatives have also played a role in enhancing the city’s socio-economic landscape. F..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000