Bengaluru Civic Body Faces Criticism for Tunnel Road Report Errors
ROADS & HIGHWAYS

Bengaluru Civic Body Faces Criticism for Tunnel Road Report Errors

A detailed project report (DPR) for an ambitious tunnel road project in Bengaluru, Karnataka, has raised concerns after it was found to contain several inaccuracies, including environmental discrepancies and references to cities in Maharashtra. The DPR, prepared by New Delhi-based Rodic Consultants and submitted to the Bruhat Bengaluru Mahanagara Palike (BBMP) in November 2024, outlined plans for an 18 km tunnel road connecting Hebbal and Silk Board, at a cost of Rs 90.5 million.

The report, completed in just three months, has been criticised for including traffic volume data from two cities in Maharashtra while discussing traffic patterns in Bengaluru. A specific section of the report, which analyses traffic volumes at Malur Road, Guttahalli Main Road, and NR Road, mentions traffic characteristics between Malegaon and Nashik, prompting concerns of a "copy-paste" job.

The report stated that nine cordon points had been identified to understand the traffic characteristics in the study area, followed by a detailed account of traffic flow and counts at various junctions. However, the inclusion of traffic data from cities far from Bengaluru has led to questions about the validity of the entire report.

The tunnel project, which is estimated to cost Rs 126.90 billion, aims to alleviate traffic congestion between the two key junctions, Hebbal and Silk Board. The proposed tunnel is designed to reduce travel time from 90 minutes to just 20 minutes, with three intermediate ramps at Mekhri Circle, Racecourse, and Lalbagh, improving connectivity along the North-South Corridor.

Karnataka’s Deputy Chief Minister DK Shivakumar, who has been advocating for the project as part of his “Brand Bengaluru” initiative, believes the tunnel will significantly reduce traffic congestion, particularly at the busy Hebbal and Silk Board junctions.

In addition to the DPR, the BBMP had also commissioned a feasibility study for the same corridor from Altinok Consulting at a cost of Rs 40.7 million.

The report’s quick turnaround, completed in just three months, raised concerns among observers, as DPRs typically take nine months to a year to prepare. For comparison, the DPR for Bengaluru Metro’s 37-km Hebbal-Sarjapur corridor, prepared by RINA Consulting at a cost of Rs 10.5 million, took a full year to complete. This stark difference in both cost and timelines has further fuelled scrutiny regarding the planning process of the tunnel project.

Redefine the future of urban mobility! Join us at the Metro Rail Conference 2025 to explore groundbreaking ideas and insights. 👉 Register today!

A detailed project report (DPR) for an ambitious tunnel road project in Bengaluru, Karnataka, has raised concerns after it was found to contain several inaccuracies, including environmental discrepancies and references to cities in Maharashtra. The DPR, prepared by New Delhi-based Rodic Consultants and submitted to the Bruhat Bengaluru Mahanagara Palike (BBMP) in November 2024, outlined plans for an 18 km tunnel road connecting Hebbal and Silk Board, at a cost of Rs 90.5 million. The report, completed in just three months, has been criticised for including traffic volume data from two cities in Maharashtra while discussing traffic patterns in Bengaluru. A specific section of the report, which analyses traffic volumes at Malur Road, Guttahalli Main Road, and NR Road, mentions traffic characteristics between Malegaon and Nashik, prompting concerns of a copy-paste job. The report stated that nine cordon points had been identified to understand the traffic characteristics in the study area, followed by a detailed account of traffic flow and counts at various junctions. However, the inclusion of traffic data from cities far from Bengaluru has led to questions about the validity of the entire report. The tunnel project, which is estimated to cost Rs 126.90 billion, aims to alleviate traffic congestion between the two key junctions, Hebbal and Silk Board. The proposed tunnel is designed to reduce travel time from 90 minutes to just 20 minutes, with three intermediate ramps at Mekhri Circle, Racecourse, and Lalbagh, improving connectivity along the North-South Corridor. Karnataka’s Deputy Chief Minister DK Shivakumar, who has been advocating for the project as part of his “Brand Bengaluru” initiative, believes the tunnel will significantly reduce traffic congestion, particularly at the busy Hebbal and Silk Board junctions. In addition to the DPR, the BBMP had also commissioned a feasibility study for the same corridor from Altinok Consulting at a cost of Rs 40.7 million. The report’s quick turnaround, completed in just three months, raised concerns among observers, as DPRs typically take nine months to a year to prepare. For comparison, the DPR for Bengaluru Metro’s 37-km Hebbal-Sarjapur corridor, prepared by RINA Consulting at a cost of Rs 10.5 million, took a full year to complete. This stark difference in both cost and timelines has further fuelled scrutiny regarding the planning process of the tunnel project.

Next Story
Infrastructure Transport

Telangana Eyes Rail Boost for $1 Trillion Goal

Telangana Chief Minister A Revanth Reddy emphasized the state's commitment to contributing $1 trillion to India's $5 trillion economic vision, contingent on robust railway infrastructure development. Speaking virtually at the inauguration of the modernized Cherlapally terminal, the CM called for central government support for key rail projects, including the second phase of Hyderabad Metro and the early execution of the Vikarabad-Krishna rail line via Kodangal. Highlighting Telangana's land-locked nature, Reddy proposed a dedicated rail line between Secunderabad and Machilipatnam port in Andhr..

Next Story
Infrastructure Transport

Thane Reviews Road Projects Amid Key Challenges

The city of Thane has recently undertaken a comprehensive review of its ongoing road infrastructure projects, focusing on overcoming key challenges that have hindered their timely completion. The review meeting, led by senior municipal officials, was aimed at assessing the current progress of multiple roadworks and addressing obstacles such as land acquisition issues, delayed approvals, and lack of coordination between departments. Among the most pressing concerns raised during the review were the frequent disruptions caused by local traffic, difficulties in obtaining necessary permissions for..

Next Story
Infrastructure Urban

MP Expands Vikram Udyogpuri for Investments

The Madhya Pradesh Industrial Development Corporation (MPIDC) has acquired over 400 hectares of private land to develop Phase 2 of the Vikram Udyogpuri industrial area. This expansion aims to attract significant industrial investments and address the rising demand for space in the region. Vikram Udyogpuri currently spans 458 hectares and is nearing full capacity. The MPIDC has initiated the process of land acquisition and is preparing a detailed project report for the second phase. This strategic project will be a highlight at the upcoming Investors' Summit 2025 in Bhopal this February. "We ..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000