We have 20 roads projects and three non-roads projects that are operational
ROADS & HIGHWAYS

We have 20 roads projects and three non-roads projects that are operational

Mukund G Sapre Executive Director, IL&FS Transportation Networks Ltd (ITNL)

The year 2015 has been productive and relatively successful for ITNL on the project execution front. And Sapre is set to actively support the company in fulfilling its set targets. He shares more on the landmark projects that are adding to the company´s growth.

Key achievements: During the year, our road portfolio touched 14,680 lane km spread over 31 projects with an operational portfolio of 9,439 lane km of highway from 20 road projects and foraying into other surface transportation sub-sectors like metro rail, city bus services and border check-posts. Many projects under construction, such as the 539-lane-km Sikar-Bikaner Expressway in Rajasthan, were completed. We have also been successful in achieving the tunnel breakthrough of the 9-km Chenani-Nashri Tunnelway in Jammu & Kashmir and have completed the 533-lane-km Moradabad Bareilly Expressway in Uttar Pradesh. Additionally, we have made 17 check-posts and two central control facilities in Madhya Pradesh awarded by MPRDCL operational. Another three projects - the Baleshwar-Kharagpur road project, Jorabat-Shillong road project and Thiruvananthapuram City Road Improvement Project - are nearing completion and we are awaiting declaration of COD from the client.

Status on the Rapid Metrorail Gurgaon South Ltd: This approximately 7-km metro link from Delhi Metro´s Sikanderpur Station to Sector 56 in Gurgaon was awarded by HUDA for a concession period of 98 years. To date, we have achieved a physical progress of 45 per cent and it is likely to be completed by December 2016.

Other contracts bagged in 2015: We have managed to emerge as a preferred bidder in a few projects. These include the Amravati-Chikli Road by NHAI on a DBFOT (toll) basis for a period of 19 years; the Fagne Mah-Guj Border Road by NHAI on a DBFOT (toll) basis for a period of 19 years; the Gujarat RoB from GRICL through a concession on BOT annuity basis for developing eight ROBs; and the Ranchi Ring Road (Section VII) by JARDCL on BOT annuity basis.

Raising Rs 750 crore via rights issue: The rights issue has been completed and money has been used to repay debt, thereby reducing debt levels. Given that the share price is at a substantial discount to its book value, the company thought that rather than making a fresh issue and forcing dilution of existing shareholders, it was prudent to mobilise capital through a rights issue, thereby enabling existing shareholders to maintain their holding.

Vision going forward: At present, we have 20 roads projects and three non-roads projects that are operational. We expect this to increase to 26 roads projects and four non-roads projects by the end of FY 2017.

Mukund G Sapre Executive Director, IL&FS Transportation Networks Ltd (ITNL) The year 2015 has been productive and relatively successful for ITNL on the project execution front. And Sapre is set to actively support the company in fulfilling its set targets. He shares more on the landmark projects that are adding to the company´s growth. Key achievements: During the year, our road portfolio touched 14,680 lane km spread over 31 projects with an operational portfolio of 9,439 lane km of highway from 20 road projects and foraying into other surface transportation sub-sectors like metro rail, city bus services and border check-posts. Many projects under construction, such as the 539-lane-km Sikar-Bikaner Expressway in Rajasthan, were completed. We have also been successful in achieving the tunnel breakthrough of the 9-km Chenani-Nashri Tunnelway in Jammu & Kashmir and have completed the 533-lane-km Moradabad Bareilly Expressway in Uttar Pradesh. Additionally, we have made 17 check-posts and two central control facilities in Madhya Pradesh awarded by MPRDCL operational. Another three projects - the Baleshwar-Kharagpur road project, Jorabat-Shillong road project and Thiruvananthapuram City Road Improvement Project - are nearing completion and we are awaiting declaration of COD from the client. Status on the Rapid Metrorail Gurgaon South Ltd: This approximately 7-km metro link from Delhi Metro´s Sikanderpur Station to Sector 56 in Gurgaon was awarded by HUDA for a concession period of 98 years. To date, we have achieved a physical progress of 45 per cent and it is likely to be completed by December 2016. Other contracts bagged in 2015: We have managed to emerge as a preferred bidder in a few projects. These include the Amravati-Chikli Road by NHAI on a DBFOT (toll) basis for a period of 19 years; the Fagne Mah-Guj Border Road by NHAI on a DBFOT (toll) basis for a period of 19 years; the Gujarat RoB from GRICL through a concession on BOT annuity basis for developing eight ROBs; and the Ranchi Ring Road (Section VII) by JARDCL on BOT annuity basis. Raising Rs 750 crore via rights issue: The rights issue has been completed and money has been used to repay debt, thereby reducing debt levels. Given that the share price is at a substantial discount to its book value, the company thought that rather than making a fresh issue and forcing dilution of existing shareholders, it was prudent to mobilise capital through a rights issue, thereby enabling existing shareholders to maintain their holding. Vision going forward: At present, we have 20 roads projects and three non-roads projects that are operational. We expect this to increase to 26 roads projects and four non-roads projects by the end of FY 2017.

Next Story
Building Material

JK Cement emerges successful bidder for Mahan coal mine in Madhya Pradesh

This marks the company’s second commercial coal block win, following its acquisition of the West of Shahdol (South) coal block. "The company is committed to becoming self-reliant for its existing cement plants and upcoming projects," JKC stated. The surplus coal from the mine will be sold commercially. The vesting order was handed over to JK Cement during a ceremony at Shastri Bhawan, New Delhi, a critical milestone for commencing mining operations within the stipulated timeline...

Next Story
Building Material

Prism Johnson's cement division goes live with Ramco ERP Suite

Prism Johnson has successfully gone live with the Ramco ERP Suite for its Cement Division. This milestone marks a significant step in Prism Johnson's digital transformation journey, leveraging Ramco Systems' advanced enterprise solutions and process control systems to streamline business processes, manufacturing operations and drive efficiency. The implementation includes cutting-edge modules for Maintenance, Sales, Distribution, Finance, Procurement, Manufacturing, Quality, and HR Management (HRM). These solutions enable Prism Johnson to achieve seamless integration across its business and wo..

Next Story
Infrastructure Urban

Indian shadow bank Shriram Finance gets record $1.28 billion loan

Shriram Finance Ltd. is reported to have borrowed $1.28 billion in a multi-currency social loan, marking the largest offshore facility ever undertaken by an Indian shadow lender. According to a press release issued by Shriram, the deal is divided across the dollar, euro, and dirham. Sources familiar with the transaction, who wished to remain anonymous, indicated that the tenors in the multi-tranche deal range from three to five years. This loan adds to the surge of offshore debt sales by Indian shadow lenders this year, a trend prompted by the Reserve Bank of India's tightening of rules in Nov..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000