In FY2019-20, we are working towards a 35 per cent growth in turnover
ROADS & HIGHWAYS

In FY2019-20, we are working towards a 35 per cent growth in turnover

Rail Vikas Nigam (RVNL), a CPSE under the Ministry of Railways,was incorporated in 2003 to raise non-budgetary resources for implementation of rail capacity augmentation projects and their implementation on a fast-track basis. It is headed by Pradeep Gaur, Chairman & Managing Director, who is assisted by three functional directors and a CFO. RVNL has completed 8879.65 km of project length covering 360.01 km of new lines, 2932.35km of doubling, 1783.22 km of gauge conversion, 3762.07 km of railway electrification, 42 km of Metropolitan Transport Project (MTP), seven railway workshops, one cable-stayed bridge at Bardhhaman and four other specific works. Gaur shares more....

Name one major challenge faced in FY2018-19. How did the company tackle it?
The primary activity of RVNL is commissioning of rail infrastructure. Commissioning is directly related to release of funds by the Ministry of Railways. The problems faced owing to funds for commissioning of rail infrastructure were closely followed up with the Ministry of Railways/Ministry of Finance/IRFC and funds were arranged. In FY2018-19, the commissioning of new lines/gauge conversion/doubling (NL/GC/DL) increased by 61 per cent and railway electrification rose by 85 per cent.

Name one you consider the biggest contributor to the company’s growth in FY2018-19.
Our approach was based on the synergy of various verticals and employee satisfaction. All issues pertaining to project delivery, general progress of the company and employee satisfaction were closely looked into and timely action was taken to resolve them.

What is one single factor you avoided that could have otherwise impacted the company’s topline and bottomline?
RVNL is executing some projects on a cost-sharing basis between the Ministry of Railways and respective state governments. Owing to a precarious financial position, the administrations at state level were not able to provide their share of funds. Consequently, RVNL slowed down work on these projects to reduce the liability of the company. 

What are your plans for the company’s growth in FY2019-20? 
In FY 2019-20, we are working towards a 35 per cent growth in turnover and a 50 per cent increase in commissioning of projects (NL/GC/DL) and railway electrification. At present, around 15 days are taken by the Ministry to reimburse all project expenditure incurred by our company. A joint procedure order is currently under modification to bring this time period down to three days. RVNL has already commissioned the Obulavaripalli-Krishnapatnam (125 km) new line, which is built on the PPP model. Another PPP project, the Haridaspur-Paradeep (82 km) new line, is being targeted for commissioning in FY 2019-20. 

Rail Vikas Nigam
Net Sales EBITDA Reported PAT
FY19 (Rs Billion) 100.68 8.03 7.05
Growth over FY18 (%) 32.52 32.30 23.83

Rail Vikas Nigam (RVNL), a CPSE under the Ministry of Railways,was incorporated in 2003 to raise non-budgetary resources for implementation of rail capacity augmentation projects and their implementation on a fast-track basis. It is headed by Pradeep Gaur, Chairman & Managing Director, who is assisted by three functional directors and a CFO. RVNL has completed 8879.65 km of project length covering 360.01 km of new lines, 2932.35km of doubling, 1783.22 km of gauge conversion, 3762.07 km of railway electrification, 42 km of Metropolitan Transport Project (MTP), seven railway workshops, one cable-stayed bridge at Bardhhaman and four other specific works. Gaur shares more....Name one major challenge faced in FY2018-19. How did the company tackle it?The primary activity of RVNL is commissioning of rail infrastructure. Commissioning is directly related to release of funds by the Ministry of Railways. The problems faced owing to funds for commissioning of rail infrastructure were closely followed up with the Ministry of Railways/Ministry of Finance/IRFC and funds were arranged. In FY2018-19, the commissioning of new lines/gauge conversion/doubling (NL/GC/DL) increased by 61 per cent and railway electrification rose by 85 per cent.Name one you consider the biggest contributor to the company’s growth in FY2018-19.Our approach was based on the synergy of various verticals and employee satisfaction. All issues pertaining to project delivery, general progress of the company and employee satisfaction were closely looked into and timely action was taken to resolve them.What is one single factor you avoided that could have otherwise impacted the company’s topline and bottomline?RVNL is executing some projects on a cost-sharing basis between the Ministry of Railways and respective state governments. Owing to a precarious financial position, the administrations at state level were not able to provide their share of funds. Consequently, RVNL slowed down work on these projects to reduce the liability of the company. What are your plans for the company’s growth in FY2019-20? In FY 2019-20, we are working towards a 35 per cent growth in turnover and a 50 per cent increase in commissioning of projects (NL/GC/DL) and railway electrification. At present, around 15 days are taken by the Ministry to reimburse all project expenditure incurred by our company. A joint procedure order is currently under modification to bring this time period down to three days. RVNL has already commissioned the Obulavaripalli-Krishnapatnam (125 km) new line, which is built on the PPP model. Another PPP project, the Haridaspur-Paradeep (82 km) new line, is being targeted for commissioning in FY 2019-20.  .tg {border-collapse:collapse;border-spacing:0;} .tg td{font-family:Arial, sans-serif;font-size:14px;padding:10px 5px;border-style:solid;border-width:1px;overflow:hidden;word-break:normal;border-color:black;} .tg th{font-family:Arial, sans-serif;font-size:14px;font-weight:normal;padding:10px 5px;border-style:solid;border-width:1px;overflow:hidden;word-break:normal;border-color:black;} .tg .tg-eohl{font-weight:bold;background-color:#ffcb2f;color:#343434;border-color:inherit;text-align:right;vertical-align:top} .tg .tg-v56s{font-weight:bold;background-color:#ffcb2f;color:#343434;border-color:inherit;text-align:left;vertical-align:top} .tg .tg-5agr{color:#343434;border-color:inherit;text-align:left;vertical-align:top} .tg .tg-39dc{color:#343434;border-color:inherit;text-align:right;vertical-align:top} Rail Vikas Nigam Net Sales EBITDA Reported PAT FY19 (Rs Billion) 100.68 8.03 7.05 Growth over FY18 (%) 32.52 32.30 23.83

Next Story
Infrastructure Energy

REC Transfers HVDC Project to Power Grid

REC Limited has successfully handed over the Special Purpose Vehicle (SPV) for a High-Voltage Direct Current (HVDC) transmission project to Power Grid Corporation of India Limited (PGCIL). This strategic move aligns with the nation's objectives to strengthen its power transmission network. Key Highlights: Project Overview: The HVDC project, under the inter-state transmission system (ISTS) initiative, is a critical component of India's push toward robust and efficient electricity transmission. It aims to handle bulk power transfer across long distances while ensuring minimal losses. Role of RE..

Next Story
Infrastructure Transport

NF Railway Collaborates with IIT Guwahati

The Northeast Frontier (NF) Railway has signed strategic Memorandums of Understanding (MoUs) with IIT Guwahati to foster technological advancements and improve railway operations in the region. This partnership focuses on innovative solutions to enhance safety, efficiency, and sustainability in rail infrastructure. Key Highlights: Purpose of MoUs: The collaboration aims to leverage IIT Guwahati's expertise in technology and research for implementing cutting-edge solutions across railway operations. Key areas of focus include: Automation and digitization in maintenance. Sustainability initiati..

Next Story
Infrastructure Transport

Danapur Division Modernization Plans Revealed

The Railway Board has unveiled ambitious plans for the expansion and modernization of the Danapur Division, a critical hub under the East Central Railway. The initiative focuses on infrastructure development, enhanced passenger amenities, and operational efficiency. Key Highlights: Scope of Modernization: The Railway Board's blueprint emphasizes: Upgrading existing infrastructure to accommodate more passenger and freight traffic. Improving station facilities, such as platforms, waiting areas, and connectivity. Introducing advanced signal systems for safer and smoother operations. Freig..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000