2 out of 18 pillars set for Hebbal flyover's extra ramp in Bengaluru
ROADS & HIGHWAYS

2 out of 18 pillars set for Hebbal flyover's extra ramp in Bengaluru

The progress of Bangalore Development Authority's (BDA) ambitious plan to construct a ramp and alleviate congestion on the Hebbal flyover is currently facing significant delays. According to BDA, out of the 18 pillars originally proposed from the Baptist Hospital side to support the ramp, only two have been constructed. The blame for this delay has been placed on several factors, with the BDA specifically pointing to the need for clearance from the traffic police.
A BDA official stated, "The advancement of the construction work relies on obtaining clearance from the traffic police. Whenever we receive clearance from the police, we will proceed accordingly."
Sachin Ghorpade, the Deputy Commissioner of Police (DCP) in charge of traffic for the northern region, mentioned that the traffic police are actively assisting in the construction efforts. He stated, "Considering the high traffic volume on Ballari Road, it is imperative that we do not disrupt the flow of traffic on the main lanes. Therefore, any construction work must be confined to the service road. We have requested the BDA to widen the left lane of the service road by reconstructing the existing uneven footpath and drainage system, but they have yet to do so. If we can allocate one lane for traffic on the service road, it will not only benefit the general public but also provide sufficient space for the construction work to progress."

If you want to learn more about Indian Roads, make sure you sign-up for the India Roads Conference at the India Construction Festival on October 12th in New Delhi.

Click HERE and reserve your seats! Or call Deepali on 82919 95574....

The progress of Bangalore Development Authority's (BDA) ambitious plan to construct a ramp and alleviate congestion on the Hebbal flyover is currently facing significant delays. According to BDA, out of the 18 pillars originally proposed from the Baptist Hospital side to support the ramp, only two have been constructed. The blame for this delay has been placed on several factors, with the BDA specifically pointing to the need for clearance from the traffic police.A BDA official stated, The advancement of the construction work relies on obtaining clearance from the traffic police. Whenever we receive clearance from the police, we will proceed accordingly.Sachin Ghorpade, the Deputy Commissioner of Police (DCP) in charge of traffic for the northern region, mentioned that the traffic police are actively assisting in the construction efforts. He stated, Considering the high traffic volume on Ballari Road, it is imperative that we do not disrupt the flow of traffic on the main lanes. Therefore, any construction work must be confined to the service road. We have requested the BDA to widen the left lane of the service road by reconstructing the existing uneven footpath and drainage system, but they have yet to do so. If we can allocate one lane for traffic on the service road, it will not only benefit the general public but also provide sufficient space for the construction work to progress.If you want to learn more about Indian Roads, make sure you sign-up for the India Roads Conference at the India Construction Festival on October 12th in New Delhi.Click HERE and reserve your seats! Or call Deepali on 82919 95574....

Next Story
Infrastructure Urban

Budget 2025: Key Highlights

On February 1, 2025, Finance Minister Nirmala Sitharaman presented the Union Budget for the financial year 2025-26 in Parliament. This marks the eighth budget by Sitharaman, making her the first finance minister in India’s history to present so many budgets. It is also the first budget of Prime Minister Narendra Modi’s third term.Sitharaman emphasised that the budget focuses on driving growth towards a “Viksit Bharat” (Developed India), with the country maintaining its position as the fastest-growing major economy. She outlined the government’s commitment to inclusive development, im..

Next Story
Infrastructure Urban

Budget 2025-26: Industry reactions

Union Finance Minister, Nirmala Sitharaman announced Budget 2025-26 today. The government has planned a number of strategic initiatives which will drive inclusive growth, boost economic growth and provide an impetus to to India’s competitive edge on the global stage.Here’s what industry has to say about various announcements and initiatives announced in the budget:Real Estate“The Union Budget 2025 is a game-changer, reinforcing India's commitment to inclusive and sustainable urban growth. The SWAMIH Fund 2 with Rs 15,000 crore will accelerate the completion of stalled housing projects, b..

Next Story
Infrastructure Urban

Budget 2025: Key Announcements Impacting Real Estate

Key takeaways for the real estate sector include:• Income tax relief for the middle class: The finance minister announced zero income tax for individuals earning up to Rs 12 lakh annually, providing a major consumption boost. This move is also expected to strengthen demand for affordable housing. Additionally, the new income tax bill will retain nearly 50 per cent of existing provisions while introducing personal tax reforms and rationalising TDS and TCS regimes by streamlining rates and thresholds.• Tax benefits for residential property investors: Investors can now claim nil valuation for..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000