Mysuru airport expansion stalled due to delay in land acquisition
AVIATION & AIRPORTS

Mysuru airport expansion stalled due to delay in land acquisition

Mysuru airport's expansion is delayed because of a lag in the land acquisition procedure. The farmers are interested in striking a deal with the government.

Besides the construction of a subway perpendicular to the runway alignment in addition to extending the terminal building, the expansion includes the extension of the runway Currently, the runway length is 1740 m, and breadth is 30 m, suitable for running an ATR-72 type of aircraft.

The proposal would increase the runaway length to 2750 m and breadth 45 m. So, it would help in operating bigger planes and enable direct long-distance flights from the city.

Airports Authority of India's (AAI) officials informed that the immediate land needed to begin the project is around 115 acres. However, to complete the entire project, overall 187 acres of land is required.

The officials revealed that the government has to do the land acquisition work. Even though the farmers are ready to settle for the current market rate, there is no progress. Due to the focus on fighting the pandemic and expenditure in the health industry, the work has been delayed.

On the other hand, farmers of Mandakalli and nearby areas close to the project location have reached out to the airport officials to know about the situation of the airport work.

The stakeholders in the industrial sector are also eager that the runway extension starts at the earliest because there is now an offer in front of the National Highways Authority of India (NHAI) to widen the Mysuru-Nanjangud highway from four lanes to six lanes.

The subway construction received approval by the Director-General of Civil Aviation (DGCA) after a ground study completion by technical experts.

The subway is entailed to take up the runway extension, which bisects the current Mysuru-Nanjangud highway, diverting which would be restrictive and unfeasible in terms of price.

Image Source


Also read: Ministry of Aviation plans large scale expansion by 2025

Mysuru airport's expansion is delayed because of a lag in the land acquisition procedure. The farmers are interested in striking a deal with the government. Besides the construction of a subway perpendicular to the runway alignment in addition to extending the terminal building, the expansion includes the extension of the runway Currently, the runway length is 1740 m, and breadth is 30 m, suitable for running an ATR-72 type of aircraft. The proposal would increase the runaway length to 2750 m and breadth 45 m. So, it would help in operating bigger planes and enable direct long-distance flights from the city. Airports Authority of India's (AAI) officials informed that the immediate land needed to begin the project is around 115 acres. However, to complete the entire project, overall 187 acres of land is required. The officials revealed that the government has to do the land acquisition work. Even though the farmers are ready to settle for the current market rate, there is no progress. Due to the focus on fighting the pandemic and expenditure in the health industry, the work has been delayed. On the other hand, farmers of Mandakalli and nearby areas close to the project location have reached out to the airport officials to know about the situation of the airport work. The stakeholders in the industrial sector are also eager that the runway extension starts at the earliest because there is now an offer in front of the National Highways Authority of India (NHAI) to widen the Mysuru-Nanjangud highway from four lanes to six lanes. The subway construction received approval by the Director-General of Civil Aviation (DGCA) after a ground study completion by technical experts. The subway is entailed to take up the runway extension, which bisects the current Mysuru-Nanjangud highway, diverting which would be restrictive and unfeasible in terms of price. Image Source Also read: Ministry of Aviation plans large scale expansion by 2025

Next Story
Resources

Workplace Solutions Company IndiQube, Surpasses 100 Properties Milestone

Workplace solutions company, IndiQube has surpassed the 100 properties milestone. The company that started nine years ago with a single property in Bengaluru has now expanded across 14 cities and caters to 700+ clients. Today, the company has a portfolio of over 7.2 million square feet with presence across major tier I cities including Bengaluru, Pune, Chennai, Hyderabad, Mumbai, Gurgaon and Noida. Also, post pandemic the company has made its foray into tier II cities including Coimbatore, Jaipur, Madurai, Kochi, Vijayawada, Calicut and Mohali. In Bengaluru, IndiQube has 59 properties cove..

Next Story
Infrastructure Transport

Ashoka Buildcon turns lowest bidder for Rs 27.91 billion NHAI projects

Ashoka Buildcon Ltd announced on November 18, 2024, that it has emerged as the lowest bidder (L-1) for two National Highways Authority of India (NHAI) projects in West Bengal, with a combined value of Rs 27.91 billion. These Engineering, Procurement, and Construction (EPC) projects will be executed under the Hybrid Annuity Model (HAM). The first project involves developing a four-lane economic corridor between Bowaichandi and Guskara-Katwa Road (Km 89.814 to Km 133) of NH 116A (Package-3). This project is valued at Rs 13.91 billion, excluding GST, and is expected to be completed within 910 d..

Next Story
Infrastructure Energy

Tata Power, Jakson, Ashoka Buildcon lead solar EPC market in 1H 2024

Tata Power Solar, Jakson Green, and Ashoka Buildcon have emerged as the top utility-scale solar engineering, procurement, and construction (EPC) providers in India during the first half (1H) of 2024, according to Mercom India’s Solar Market Leaderboard for 1H 2024. Gensol Engineering and InSolare Energy also secured spots in the top five. Tata Power Solar led the market with a 32.7% share, followed closely by Jakson Green at 32.1%, while Ashoka Buildcon claimed the third spot with 6.5%. Gensol Engineering and InSolare Energy accounted for 6.2% and 5.1% of the market, respectively. Together..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000