TANGEDCO applies for new Environmental Clearance for Udangudi project
ECONOMY & POLICY

TANGEDCO applies for new Environmental Clearance for Udangudi project

TANGEDCO has submitted a request for a renewed Environmental Clearance (EC) for the 2X660 MW Udangudi Supercritical Thermal Power Station, aiming to bypass the necessity of public hearings. As the current EC is set to expire on October 13, 2024, TANGEDCO has urged the Ministry of Environment, Forests, and Climate Change to issue fresh terms of reference. The on-going construction of the Udangudi thermal power plant has seen significant progress, with approximately 82.85% of the main plant work completed and 90% of the coal jetty component finalised. To ensure the timely commissioning of the Udangudi power plant, TANGEDCO has requested permission from the MoEF and CC to continue construction activities beyond the validity period while simultaneously processing a fresh EC with new terms of reference for the main plant. Furthermore, TANGEDCO has sought exemption from public hearings in accordance with a notification from the MoEF and CC dated March 18, 2021.

In its communication, TANGEDCO highlighted the renewal of the EC and CRZ clearance obtained for the interlinked project of Captive Coal Jetty and pipe conveyor system in August 2022, following the expiration of the ten-year period stipulated by the Environment Impact Assessment notification 2006. The EC renewal involved conducting Rapid Marine and Terrestrial EIA/EMP studies by an accredited consultant from June to November 2021. As the marine baseline data's validity extends for three years, TANGEDCO proposed the continued use of existing marine baseline data in the EIA/EMP study for the power project.

Initially conceptualised as a joint venture between TANGEDCO and BHEL, the Udangudi project later transitioned into a state sector project. Delays arose during the bidding process initiated in July 2013, leading to a legal challenge by one of the bidders, subsequently addressed by the Madras High Court. Ultimately, the Engineering, Procurement, and Construction Contract was awarded to BHEL in December 2017 following the court's ruling. ITD Cementation India Ltd was tasked with establishing a captive coal jetty and pipe conveyor system for the Udangudi project in February 2018, but execution faced setbacks due to cyclones and the Covid-19 pandemic.

The 14th RAHSTA Expo, part of the India Construction Festival, will be held on October 9 and 10, 2024, at the Jio Convention Centre in Mumbai. For more details, visit: https://rahstaexpo.com

TANGEDCO has submitted a request for a renewed Environmental Clearance (EC) for the 2X660 MW Udangudi Supercritical Thermal Power Station, aiming to bypass the necessity of public hearings. As the current EC is set to expire on October 13, 2024, TANGEDCO has urged the Ministry of Environment, Forests, and Climate Change to issue fresh terms of reference. The on-going construction of the Udangudi thermal power plant has seen significant progress, with approximately 82.85% of the main plant work completed and 90% of the coal jetty component finalised. To ensure the timely commissioning of the Udangudi power plant, TANGEDCO has requested permission from the MoEF and CC to continue construction activities beyond the validity period while simultaneously processing a fresh EC with new terms of reference for the main plant. Furthermore, TANGEDCO has sought exemption from public hearings in accordance with a notification from the MoEF and CC dated March 18, 2021. In its communication, TANGEDCO highlighted the renewal of the EC and CRZ clearance obtained for the interlinked project of Captive Coal Jetty and pipe conveyor system in August 2022, following the expiration of the ten-year period stipulated by the Environment Impact Assessment notification 2006. The EC renewal involved conducting Rapid Marine and Terrestrial EIA/EMP studies by an accredited consultant from June to November 2021. As the marine baseline data's validity extends for three years, TANGEDCO proposed the continued use of existing marine baseline data in the EIA/EMP study for the power project. Initially conceptualised as a joint venture between TANGEDCO and BHEL, the Udangudi project later transitioned into a state sector project. Delays arose during the bidding process initiated in July 2013, leading to a legal challenge by one of the bidders, subsequently addressed by the Madras High Court. Ultimately, the Engineering, Procurement, and Construction Contract was awarded to BHEL in December 2017 following the court's ruling. ITD Cementation India Ltd was tasked with establishing a captive coal jetty and pipe conveyor system for the Udangudi project in February 2018, but execution faced setbacks due to cyclones and the Covid-19 pandemic.

Next Story
Real Estate

Singapore's CapitaLand Plans Major India Expansion

CapitaLand Investment Limited (CLI), one of Singapore's largest real estate investment managers, has announced plans to significantly expand its investments in India. The company aims to more than double its India portfolio by 2028, signaling its confidence in the country?s burgeoning real estate market. Current Portfolio and Growth Target: CLI currently manages assets worth USD 3.3 billion in India. With its sights set on future growth, the company is targeting a dramatic increase in its India investment kitty to over USD 7 billion by 2028. This move comes as part of a broader strategy to ca..

Next Story
Infrastructure Transport

Air India MRO Facility Key Hub

Air India has launched a state-of-the-art Maintenance, Repair, and Overhaul (MRO) facility at Bengaluru Airport City, establishing a crucial hub for aircraft servicing in India?s burgeoning aviation sector. This new MRO facility aims to enhance Air India?s operational capabilities, improve turnaround times for aircraft maintenance, and reduce reliance on overseas servicing. Strategic Importance of Bengaluru: The facility, located at the Kempegowda International Airport (KIA) in Bengaluru, is strategically positioned to serve as a critical aviation hub. Bengaluru is a key center for both domest..

Next Story
Infrastructure Transport

BMC Notifies Properties for Water Tunnel

The Brihanmumbai Municipal Corporation (BMC) has initiated a crucial step in Mumbai's infrastructure development by notifying several properties for its ambitious underground water tunnel project. This project aims to bolster the city's water supply system, ensuring a more reliable and efficient distribution network. Project Overview: The underground water tunnel project is designed to address Mumbai's increasing demand for water by creating a robust network of tunnels deep below the surface. This tunnel system will transport water from reservoirs directly to various parts of the city, signif..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000