October sees Rs 4.31 trillion overruns in 411 infra projects
ECONOMY & POLICY

October sees Rs 4.31 trillion overruns in 411 infra projects

In October of this year, 411 infrastructure projects, each requiring an investment of Rs 1.5 billion or more, experienced cost overruns exceeding Rs 4.31 trillion. The Ministry of Statistics and Programme Implementation, responsible for monitoring projects valued at Rs 1.5 billion and above, disclosed that out of a total of 1,788 projects, 411 encountered cost overruns, and 837 projects faced delays.

The report highlighted that the initial cost of implementing the 1,788 projects amounted to Rs 24 trillion. The projected completion cost is expected to reach Rs 29 trillion, indicating an overall cost overrun of Rs 4.31 trillion, which is equivalent to 17.39% of the original cost. As per the ministry's latest report for October 2023, it stated that the expenditure on these projects until October 2023 reached Rs 15.27 trillion, constituting 52.49 percent of the anticipated project cost. Nonetheless, the report specified that the number of delayed projects decreases to 628 if the delay is calculated based on the most recent schedule of completion.

Various project implementing agencies have cited several reasons for time overruns. These include delays in land acquisition, obtaining forest and environment clearances, and a lack of infrastructure support and linkages. Additionally, other factors contributing to delays encompass challenges in securing project financing, finalizing detailed engineering, changes in scope, delays in tendering, ordering, and equipment supply, as well as issues related to law and order.

In October of this year, 411 infrastructure projects, each requiring an investment of Rs 1.5 billion or more, experienced cost overruns exceeding Rs 4.31 trillion. The Ministry of Statistics and Programme Implementation, responsible for monitoring projects valued at Rs 1.5 billion and above, disclosed that out of a total of 1,788 projects, 411 encountered cost overruns, and 837 projects faced delays. The report highlighted that the initial cost of implementing the 1,788 projects amounted to Rs 24 trillion. The projected completion cost is expected to reach Rs 29 trillion, indicating an overall cost overrun of Rs 4.31 trillion, which is equivalent to 17.39% of the original cost. As per the ministry's latest report for October 2023, it stated that the expenditure on these projects until October 2023 reached Rs 15.27 trillion, constituting 52.49 percent of the anticipated project cost. Nonetheless, the report specified that the number of delayed projects decreases to 628 if the delay is calculated based on the most recent schedule of completion. Various project implementing agencies have cited several reasons for time overruns. These include delays in land acquisition, obtaining forest and environment clearances, and a lack of infrastructure support and linkages. Additionally, other factors contributing to delays encompass challenges in securing project financing, finalizing detailed engineering, changes in scope, delays in tendering, ordering, and equipment supply, as well as issues related to law and order.

Next Story
Infrastructure Transport

Railway stations in Prayagraj undergo major passenger facility expansion

The Railway Board Chairman and CEO, Satish Kumar, conducted an extensive inspection on Saturday alongside the General Manager of Northern Railway and the officiating General Manager of North Central Railway. Their visit focused on various ongoing projects at multiple stations across the Northern and North Central Railway zones, with particular attention to enhancing facilities for the upcoming Maha Kumbh. During the inspection, Chairman Kumar reviewed the construction of a vital bridge over the River Ganga, specifically between Jhunsi and Prayagraj Rambagh. This bridge is expected to significa..

Next Story
Infrastructure Transport

Madurai-Thoothukudi broad gauge line works under review

The construction of the Madurai-Thoothukudi broad gauge line, which includes the crucial Melmarudur-Tiruparankundram project, is currently under careful review. This update comes from Southern Railway's assistant public information officer, J Kumarasubramanian, following an RTI inquiry made by a concerned citizen, Dayanand Krishnan. The new broad gauge line is projected to cover a total length of 143.5 km, with the initial 18 km stretch between Milavittan and Melmarudur completed and sanctioned by the Commission of Railway Safety on March 8, 2022. While substantial progress has been made on t..

Next Story
Real Estate

DLF expects Rs 26,000 cr from super luxury project in Gurugram

Realty giant DLF is projecting impressive revenue of Rs 26,000 crore from its newly unveiled super-luxury project, The Dahlias, situated in the heart of Gurugram. Ashok Tyagi, the Managing Director of DLF, shared these insights during a recent conference call with market analysts, highlighting the project's potential amidst rising demand for high-end residential properties. The Dahlias project spans an expansive 17 acres and is set to feature approximately 420 ultra-luxury apartments, each boasting a minimum size of 10,300 square feet. This ambitious development has already garnered significan..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000