Around 438 infra projects show cost overruns of Rs 4.3 lakh cr
ECONOMY & POLICY

Around 438 infra projects show cost overruns of Rs 4.3 lakh cr

According to a report, about 438 infrastructure projects of over Rs 150 crore have been hit by cost overruns of over Rs 4.3 lakh crore. The Ministry of Statistics and Programme monitors projects worth Rs 150 crore or more.

From the total 1,670 infrastructure projects, 438 witnessed cost overruns, and 563 were delayed projects.

The Ministry said that the initial cost of implementation of 1,670 projects was Rs 21,66,048.11 crore, and their anticipation completion cost is expected to be Rs 25,96,907.70 crore, which reflects an overall cost overrun of Rs 4,30,859.59 crore, almost 20% of the original cost.

The overall expenditure incurred on these infrastructure projects till September is Rs 12,54,512.40 crore, which is 48.31% of the anticipated cost, said the report.

The report said that the delayed projects have decreased to 380 if the delay is calculated based on the latest completion schedule.

For 808 projects, neither the year of commissioning nor the tentative gestation period has been witnessed.

From the total delayed projects, 100 projects were delayed between 1-12 months, 120 for 13-24 months, 216 for 25-60 months, and 127 projects for 61 months or more.

The average time of cost overrun for delayed projects is 47 months.

According to the agencies, the cost overrun may be due to delayed land acquisition, getting forest and environmental clearances, and lack of infrastructure support and linkage.

Delay in project financing, finalisation in detailed engineering works, delay in tendering, change in scope of work, ordering and equipment supply, and other legal issues are other reasons for the delay.

As per the report, Covid-19 lockdowns were also a reason for the delay in project implementation.

Image Source


Also read: 470 infra projects show cost overruns worth Rs 4.38 lakh cr

According to a report, about 438 infrastructure projects of over Rs 150 crore have been hit by cost overruns of over Rs 4.3 lakh crore. The Ministry of Statistics and Programme monitors projects worth Rs 150 crore or more. From the total 1,670 infrastructure projects, 438 witnessed cost overruns, and 563 were delayed projects. The Ministry said that the initial cost of implementation of 1,670 projects was Rs 21,66,048.11 crore, and their anticipation completion cost is expected to be Rs 25,96,907.70 crore, which reflects an overall cost overrun of Rs 4,30,859.59 crore, almost 20% of the original cost. The overall expenditure incurred on these infrastructure projects till September is Rs 12,54,512.40 crore, which is 48.31% of the anticipated cost, said the report. The report said that the delayed projects have decreased to 380 if the delay is calculated based on the latest completion schedule. For 808 projects, neither the year of commissioning nor the tentative gestation period has been witnessed. From the total delayed projects, 100 projects were delayed between 1-12 months, 120 for 13-24 months, 216 for 25-60 months, and 127 projects for 61 months or more. The average time of cost overrun for delayed projects is 47 months. According to the agencies, the cost overrun may be due to delayed land acquisition, getting forest and environmental clearances, and lack of infrastructure support and linkage. Delay in project financing, finalisation in detailed engineering works, delay in tendering, change in scope of work, ordering and equipment supply, and other legal issues are other reasons for the delay. As per the report, Covid-19 lockdowns were also a reason for the delay in project implementation. Image SourceAlso read: 470 infra projects show cost overruns worth Rs 4.38 lakh cr

Next Story
Infrastructure Urban

BorgWarner to Supply Transfer Cases for SAIC Maxus Exports

BorgWarner is supporting SAIC Maxus by supplying its locally developed and manufactured transfer cases. BorgWarner will provide SAIC Maxus with two types of transfer cases: an on-demand transfer case with mechanical locking and a high-torque part-time transfer case. Mass production is expected to begin in Q3 2026. “BorgWarner’s relationship with SAIC Maxus spans more than a decade. Our transfer case technology not only supports SAIC Maxus in strengthening its position in the Chinese market but also empowers its expansion into overseas markets,” said Isabelle McKenzie, Vice President of ..

Next Story
Real Estate

Residential Supply Near Employment Hubs in NCR Soars

Magicbricks, India’s leading real estate platform, has revealed significant growth in residential demand and supply across key areas in the National Capital Region (NCR), particularly in locations near IT parks, industrial zones, and commercial hubs. These strategically located regions, benefiting from superior connectivity and infrastructure development, are attracting homebuyers and investors alike. According to the latest insights, Techzone 4, Greater Noida has recorded a remarkable 449 per cent Year-on-year (YoY) increase in supply, while Sector 89, New Gurugram has reported a 300% YoY ..

Next Story
Equipment

Ajax Engineering's IPO Marks a Milestone for Growth

Ajax Engineering, a key player in the concrete equipment industry, has announced its initial public offering (IPO) with a price band of Rs 599-629 per share, aiming to raise Rs 1,269 crore through an offer-for-sale (OFS) of 2.01 crore shares. The IPO, opening for public subscription from February 10 to 12, will allow anchor investors to bid starting February 7. As an OFS, Ajax Engineering will not receive any proceeds from the sale. Headquartered in Bengaluru, Ajax operates four advanced manufacturing facilities in Karnataka and is set to expand further with plans for a new plant by 2025. The..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?