443 infra projects hits cost overruns of Rs 4.45 lakh crore: Report
ECONOMY & POLICY

443 infra projects hits cost overruns of Rs 4.45 lakh crore: Report

A government report revealed that 443 infrastructure projects, with the cost of investment of over Rs 150 crore, have been hit by cost overruns totalling over Rs 4.45 lakh crore.

The Ministry of Statistics and Programme Implementation (MOSPI) monitors infrastructure projects of Rs 150 crore and above.

As per the report, till January 2022, expenditure incurred on these projects stood at Rs 13,16,293.63 crore or 48.76% of the estimated project cost.

From 1,671 such projects, 514 projects were delayed, and 443 reported cost overruns.

However, the number of delayed projects reduces to 381, based on the latest completion schedule.

Moreover, for 881 projects, neither the year of commissioning nor the tentative gestation period has been declared.

Out of the 514 delayed projects, 89 have a total delay of one to two months, 113 are delayed for 13-24 months, 204 for 25-60 months, and 108 projects have been delayed for over 61 months.

Overall estimated time overrun in these 514 delayed projects is 46.23 months.

Various agencies executing these projects notified reasons for time overrun, such as delay in land acquisition, delay in getting environment approvals, and shortage of infrastructure linkages and support.

Additional reasons include finalisation detail engineering delay, change in scope, law and order issues, and many other reasons.

According to the report, the state-wise lockdown due to the Covid-19 pandemic was one of the reasons for the delay.

It also mentioned that project agencies are not reporting revised cost estimates and schedule commissioning for various projects, which shows that time/cost overrun figures are under-reported.

Image Source

Also read: 445 infra projects hits cost overrun of Rs 4.4 lakh crore

A government report revealed that 443 infrastructure projects, with the cost of investment of over Rs 150 crore, have been hit by cost overruns totalling over Rs 4.45 lakh crore. The Ministry of Statistics and Programme Implementation (MOSPI) monitors infrastructure projects of Rs 150 crore and above. As per the report, till January 2022, expenditure incurred on these projects stood at Rs 13,16,293.63 crore or 48.76% of the estimated project cost. From 1,671 such projects, 514 projects were delayed, and 443 reported cost overruns. However, the number of delayed projects reduces to 381, based on the latest completion schedule. Moreover, for 881 projects, neither the year of commissioning nor the tentative gestation period has been declared. Out of the 514 delayed projects, 89 have a total delay of one to two months, 113 are delayed for 13-24 months, 204 for 25-60 months, and 108 projects have been delayed for over 61 months. Overall estimated time overrun in these 514 delayed projects is 46.23 months. Various agencies executing these projects notified reasons for time overrun, such as delay in land acquisition, delay in getting environment approvals, and shortage of infrastructure linkages and support. Additional reasons include finalisation detail engineering delay, change in scope, law and order issues, and many other reasons. According to the report, the state-wise lockdown due to the Covid-19 pandemic was one of the reasons for the delay. It also mentioned that project agencies are not reporting revised cost estimates and schedule commissioning for various projects, which shows that time/cost overrun figures are under-reported. Image Source Also read: 445 infra projects hits cost overrun of Rs 4.4 lakh crore

Next Story
Infrastructure Transport

NHAI to Upgrade Tamil Nadu Highways

To reduce congestion on key national highways in Tamil Nadu, the National Highways Authority of India (NHAI) has planned capacity upgrades for at least eight highway stretches. The improvements will include bypasses, flyovers, and four-laning in Salem, Coimbatore, Tiruppur, Nilgiris, and Cuddalore. NHAI has invited tenders to appoint consultants for preparing detailed project reports (DPRs) on these expansions. The affected highways include NH-181, NH-81, NH-532, NH-85, and NH-136. Proposed Upgrades Across Highways - NH-181 (Coimbatore-Gundlupet Route): This stretch will see four bypasses an..

Next Story
Infrastructure Transport

Ludhiana-Bathinda Highway Revived as NHAI Invites Bids

The Ludhiana-Bathinda highway project, initially stalled due to land acquisition issues, has been revived as the National Highways Authority of India (NHAI) invites fresh bids to resume construction. The project, part of the Ludhiana-Ajmer Economic Corridor, is estimated to cost Rs 24.61 billion and will be executed in two phases. Package 1, covering 30.03 km, has a budget of Rs 9.06 billion, while Package 2, spanning 45.25 km, is set to cost Rs 15.55 billion. The NHAI had previously withdrawn the project due to unavailability of land. However, intervention from Union Minister for Road Trans..

Next Story
Infrastructure Urban

Dilip Buildcon Wins Rs 460M Arbitration

Infrastructure major Dilip Buildcon has secured an arbitration award of Rs 460 million against the National Highways Authority of India (NHAI) over delays and breaches during the execution of a highway project in Karnataka. The dispute pertains to the Rehabilitation and Upgradation of the Kerala Border to Kollegala Section of NH 212, awarded to Dilip Buildcon under an Engineering, Procurement, and Construction (EPC) agreement dated June 6, 2014. The project involved two-lane expansion with paved shoulders and four-lane development under the National Highways Development Project (NHDP) Phase IV..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?