Infra projects show huge cost overruns
ECONOMY & POLICY

Infra projects show huge cost overruns

As per recent reports, 437 infrastructure projects, each worth Rs 1.50 billion or more have been adversely affected due to cost overruns, amounting to over Rs 4.37 trillion. Of 1,663 such projects, 531 projects witnessed time escalation, and 437 projects have reported cost overruns. Cost overrun quantum. The incurred expenditure on the projects stood at Rs 11.62 trillion till September, which was 45.60% of the expected cost.

All infrastructure projects worth Rs 1.50 billion and above are monitored by the Ministry of Statistics and Programme Implementation (MoSPI). The Ministry's latest report for September 2020 reported that the original cumulative cost for the 1,663 projects was Rs 21.09 trillion. However, the anticipated cost of completion of the projects is probably going to be Rs 25.47 trillion. The overall cost overruns indicated by this is of Rs 4.37 trillion, which is more than 20 per cent of the initially calculated cost.

However, the report said that if the delay is assessed based on the latest schedule of completion, the number of delayed projects reduces to 430.

The report also mentioned that neither the tentative gestation period nor the year of commissioning was reported for 924 projects.

Time overruns quantum. Of the 531 projects that have been delayed, 121 projects reflect a delay of 61 months and more; 160 projects show a delay of any duration between 25 to 60 months; 128 projects reflect a delay in the range of 13-24 months; while 122 projects show an overall delay from anywhere between 1-12 months. The average time overrun in all the 531 projects is 43.89 months.

Several project-implementing agencies reported various reasons for the time overruns. The reasons varied from delay in acquiring environment and forest clearances, a delay in acquisition of land or even a lack of linkages and infrastructural support.

The report mentioned tendering delays, delay in ordering and supplying of equipment, delay in finalisation of detailed engineering, delays in project financing tie-ups and issues with law and order as some of the other reasons.

The report also stated that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are under-reported.

As per recent reports, 437 infrastructure projects, each worth Rs 1.50 billion or more have been adversely affected due to cost overruns, amounting to over Rs 4.37 trillion. Of 1,663 such projects, 531 projects witnessed time escalation, and 437 projects have reported cost overruns. Cost overrun quantum. The incurred expenditure on the projects stood at Rs 11.62 trillion till September, which was 45.60% of the expected cost. All infrastructure projects worth Rs 1.50 billion and above are monitored by the Ministry of Statistics and Programme Implementation (MoSPI). The Ministry's latest report for September 2020 reported that the original cumulative cost for the 1,663 projects was Rs 21.09 trillion. However, the anticipated cost of completion of the projects is probably going to be Rs 25.47 trillion. The overall cost overruns indicated by this is of Rs 4.37 trillion, which is more than 20 per cent of the initially calculated cost. However, the report said that if the delay is assessed based on the latest schedule of completion, the number of delayed projects reduces to 430. The report also mentioned that neither the tentative gestation period nor the year of commissioning was reported for 924 projects. Time overruns quantum. Of the 531 projects that have been delayed, 121 projects reflect a delay of 61 months and more; 160 projects show a delay of any duration between 25 to 60 months; 128 projects reflect a delay in the range of 13-24 months; while 122 projects show an overall delay from anywhere between 1-12 months. The average time overrun in all the 531 projects is 43.89 months. Several project-implementing agencies reported various reasons for the time overruns. The reasons varied from delay in acquiring environment and forest clearances, a delay in acquisition of land or even a lack of linkages and infrastructural support. The report mentioned tendering delays, delay in ordering and supplying of equipment, delay in finalisation of detailed engineering, delays in project financing tie-ups and issues with law and order as some of the other reasons. The report also stated that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are under-reported.

Next Story
Resources

TKIL Displays High-Performance Jaw Crushers at Odisha Expo 2025

TKIL Industries Pvt. Ltd. (formerly known as thyssenkrupp Industries India Pvt. Ltd.), a pioneer in mining and material handling solutions and engineering, recently participated in Odisha Mining & Infrastructure International Expo 2025, India’s largest mining and infrastructure exhibition. Recognising the Expo’s visibility and growth opportunities, TKIL Industries showcased its next-generation jaw crushers at the Expo held at Baramunda Ground, Bhubaneswar, Odisha from March 6th-9th, 2025. The company received an overwhelming response at Hall A, Stall 40, where an interactive demonstrat..

Next Story
Infrastructure Urban

Cargill Inaugurates New Corn Milling Plant to Meet Growing Demand

With a combined market value of $15 billion, these sectors are witnessing high annual compounded growth rates of between 6 and 11% over next five years1, leading to increased demand for starch derivatives which are used as thickening or stabilising agents to achieve desired texture, viscosity and mouthfeel in consumer products like gummies, jellies, fillings, yogurt, cheese, processed milk and infant formula. Cargill has a business arrangement with Saatvik who has established this dedicated production facility for starch derivatives with an initial output capacity of 500 tons per day, which ..

Next Story
Infrastructure Energy

India’s Thermal Coal Imports Drop Again Amid Manufacturing Slowdown

India’s thermal coal imports fell for the sixth consecutive month in February, marking a 15.3% drop to 12.16 million metric tonnes, according to ship tracking data. This is the longest decline streak since early 2022, driven by slowing manufacturing activity and rising domestic coal production. The world’s second-largest coal importer has seen muted growth in coal-fired power generation due to reduced industrial demand and increased renewable energy output. Despite expectations of higher electricity demand in the summer months, rising domestic production may keep imports subdued. ..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?