470 infra projects show cost overruns worth Rs 4.38 lakh cr
ECONOMY & POLICY

470 infra projects show cost overruns worth Rs 4.38 lakh cr

According to a report by the Ministry of Statistics and Programme Implementation (MoSPI), as many as 470 infrastructure projects, each worth over Rs 150 crore have shown cost overruns of over Rs 4.38 lakh crore.

The report said the total original cost of implementation of 1,773 infrastructure projects was Rs 22,33,409.53 crore, however, the anticipated cost is likely to be around Rs 26,71,440.77 crore, indicating an overall cost overrun of 4,38,031.24 crore, 19.61% of the original cost.

An expenditure of 13,16,032.62 crore was incurred on these projects till April 2021, which is 49.26% of the expected cost of the projects.

The report also mentioned that the number of delayed projects would drop to 375 if the delay is estimated as per the latest schedule of completion. For 988 projects, neither the year of commissioning nor the tentative gestation period has been reported.

Out of 525 delayed projects, an overall delay has been noted for 106 projects in a range of 1-12 months, 123 projects in 13-24 months, 179 projects in 25-60 months and 117 projects in more than 61 months.

In these 525 delayed projects, the average time overrun is 45.63 months.

Various project implementing agencies have concluded that the reasons for time overruns are delay in -- land acquisition, obtaining forest, tie-up for project financing, finalisation of detailed engineering, tendering, ordering, equipment supply, environment clearances.

The reasons also include lack of infrastructure support and linkages, change in scope, and law and order problems.

Reports have also pointed to lockdowns due to Covid-19 as one of the reasons for the delay in the implementation of projects.

Many project agencies have also been found not disclosing revised cost estimates and commissioning timelines, implying that time/cost overrun statistics are underreported.

Image Source


Also read: 449 infra projects’ cost overruns total Rs 4 lakh cr

Also read: List of the companies that were able to bag some of the major infrastructural projects in May

According to a report by the Ministry of Statistics and Programme Implementation (MoSPI), as many as 470 infrastructure projects, each worth over Rs 150 crore have shown cost overruns of over Rs 4.38 lakh crore. The report said the total original cost of implementation of 1,773 infrastructure projects was Rs 22,33,409.53 crore, however, the anticipated cost is likely to be around Rs 26,71,440.77 crore, indicating an overall cost overrun of 4,38,031.24 crore, 19.61% of the original cost. An expenditure of 13,16,032.62 crore was incurred on these projects till April 2021, which is 49.26% of the expected cost of the projects. The report also mentioned that the number of delayed projects would drop to 375 if the delay is estimated as per the latest schedule of completion. For 988 projects, neither the year of commissioning nor the tentative gestation period has been reported. Out of 525 delayed projects, an overall delay has been noted for 106 projects in a range of 1-12 months, 123 projects in 13-24 months, 179 projects in 25-60 months and 117 projects in more than 61 months. In these 525 delayed projects, the average time overrun is 45.63 months. Various project implementing agencies have concluded that the reasons for time overruns are delay in -- land acquisition, obtaining forest, tie-up for project financing, finalisation of detailed engineering, tendering, ordering, equipment supply, environment clearances. The reasons also include lack of infrastructure support and linkages, change in scope, and law and order problems. Reports have also pointed to lockdowns due to Covid-19 as one of the reasons for the delay in the implementation of projects. Many project agencies have also been found not disclosing revised cost estimates and commissioning timelines, implying that time/cost overrun statistics are underreported. Image SourceAlso read: 449 infra projects’ cost overruns total Rs 4 lakh cr Also read: List of the companies that were able to bag some of the major infrastructural projects in May

Next Story
Products

Viva ACP Launches FR A1-Rated Honeycomb Panels for Fire Safety

Viva, Asia’s largest manufacturer and supplier of aluminium composite panels (ACP) introduced its FR A1-rated Honeycomb Panels, setting a new industry benchmark for fire safety and architectural excellence. Engineered to deliver exceptional performance, these panels combine advanced fire-resistance technology with aesthetic versatility, offering a revolutionary solution for safety-critical environments.The FR A1 rating represents the highest standard of fire resistance under the European Standard EN 13501-1, signifying non-combustibility and zero contribution to fire, smoke, or toxic emissio..

Next Story
Real Estate

Almal Real Estate Expands into Commercial, Global Markets

Almal Real Estate Development is soon to announce its upcoming expansion into new verticals and international markets as part of its strategic growth plans for 2030. The company, known for its innovative luxury residential and hospitality developments, is preparing to diversify into the commercial sector with the introduction of The Smart Space, a network of business centers in UAE featuring five-star amenities. Additionally, Almal is entering new markets in Bali and Thailand as a community developer, focusing on villa and townhouse projects.The expansion into the commercial real estate sector..

Next Story
Infrastructure Urban

NABARD Approves Rs 9.03 Billion for 127 Projects in Himachal

The Himachal Pradesh government has secured approval from the National Bank for Agriculture and Rural Development (NABARD) for 127 projects worth Rs 9.03 billion for the 2024-25 fiscal, Chief Minister Sukhvinder Singh Sukhu announced. During a meeting with MLAs from Kangra, Kullu, Kinnaur, Solan, Chamba, Bilaspur, and Lahaul-Spiti districts to discuss priorities for the 2025-26 budget, Sukhu said the approved projects include 50 MLA-priority schemes under the Public Works Department, valued at Rs 4.12 billion, and 23 MLA-priority schemes under the Jal Shakti Vibhag, costing Rs 1.79 billio..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?