470 infra projects show cost overruns worth Rs 4.38 lakh cr
ECONOMY & POLICY

470 infra projects show cost overruns worth Rs 4.38 lakh cr

According to a report by the Ministry of Statistics and Programme Implementation (MoSPI), as many as 470 infrastructure projects, each worth over Rs 150 crore have shown cost overruns of over Rs 4.38 lakh crore.

The report said the total original cost of implementation of 1,773 infrastructure projects was Rs 22,33,409.53 crore, however, the anticipated cost is likely to be around Rs 26,71,440.77 crore, indicating an overall cost overrun of 4,38,031.24 crore, 19.61% of the original cost.

An expenditure of 13,16,032.62 crore was incurred on these projects till April 2021, which is 49.26% of the expected cost of the projects.

The report also mentioned that the number of delayed projects would drop to 375 if the delay is estimated as per the latest schedule of completion. For 988 projects, neither the year of commissioning nor the tentative gestation period has been reported.

Out of 525 delayed projects, an overall delay has been noted for 106 projects in a range of 1-12 months, 123 projects in 13-24 months, 179 projects in 25-60 months and 117 projects in more than 61 months.

In these 525 delayed projects, the average time overrun is 45.63 months.

Various project implementing agencies have concluded that the reasons for time overruns are delay in -- land acquisition, obtaining forest, tie-up for project financing, finalisation of detailed engineering, tendering, ordering, equipment supply, environment clearances.

The reasons also include lack of infrastructure support and linkages, change in scope, and law and order problems.

Reports have also pointed to lockdowns due to Covid-19 as one of the reasons for the delay in the implementation of projects.

Many project agencies have also been found not disclosing revised cost estimates and commissioning timelines, implying that time/cost overrun statistics are underreported.

Image Source


Also read: 449 infra projects’ cost overruns total Rs 4 lakh cr

Also read: List of the companies that were able to bag some of the major infrastructural projects in May

According to a report by the Ministry of Statistics and Programme Implementation (MoSPI), as many as 470 infrastructure projects, each worth over Rs 150 crore have shown cost overruns of over Rs 4.38 lakh crore. The report said the total original cost of implementation of 1,773 infrastructure projects was Rs 22,33,409.53 crore, however, the anticipated cost is likely to be around Rs 26,71,440.77 crore, indicating an overall cost overrun of 4,38,031.24 crore, 19.61% of the original cost. An expenditure of 13,16,032.62 crore was incurred on these projects till April 2021, which is 49.26% of the expected cost of the projects. The report also mentioned that the number of delayed projects would drop to 375 if the delay is estimated as per the latest schedule of completion. For 988 projects, neither the year of commissioning nor the tentative gestation period has been reported. Out of 525 delayed projects, an overall delay has been noted for 106 projects in a range of 1-12 months, 123 projects in 13-24 months, 179 projects in 25-60 months and 117 projects in more than 61 months. In these 525 delayed projects, the average time overrun is 45.63 months. Various project implementing agencies have concluded that the reasons for time overruns are delay in -- land acquisition, obtaining forest, tie-up for project financing, finalisation of detailed engineering, tendering, ordering, equipment supply, environment clearances. The reasons also include lack of infrastructure support and linkages, change in scope, and law and order problems. Reports have also pointed to lockdowns due to Covid-19 as one of the reasons for the delay in the implementation of projects. Many project agencies have also been found not disclosing revised cost estimates and commissioning timelines, implying that time/cost overrun statistics are underreported. Image SourceAlso read: 449 infra projects’ cost overruns total Rs 4 lakh cr Also read: List of the companies that were able to bag some of the major infrastructural projects in May

Next Story
Infrastructure Transport

Ceigall 2.0 has begun and the journey ahead looks promising

"We are a nearly 23-year-old company and if I had to define Ceigall, it’s simple – what comes on the road, we build it,” said Ramneek Sehgal, Managing Director of Ceigall India, which is known for its ability to deliver complex projects on time, such as the successful completion of the Katra Expressway. “Ceigall is making its mark in India's construction landscape. From highways, expressways and elevated roads to railways, metro railways, runways and tunnels – you name it, we do it. Beyond roads, we’re also into utilities and solar energy projects. We've already installed thre..

Next Story
Infrastructure Urban

Hyderabad Ranked Fastest Growing City for Infra Development

Hyderabad has emerged as the fastest-growing city in India among the top six, excelling in key areas such as governance, socio-economic profile, physical infrastructure, and real estate. According to the latest India Prime City Index report by Knight Frank India, the city has experienced remarkable growth, driven by extensive infrastructure projects, a surge in real estate demand, and a rising population of ultra-high-net-worth individuals (UHNWIs) and high-net-worth individuals (HNWIs). Proactive policy initiatives have also played a role in enhancing the city’s socio-economic landscape. F..

Next Story
Infrastructure Energy

Tamil Nadu Explores PPP Route for Rs 4,500 Crore Power Transmission Project

In a pioneering move, the Tamil Nadu Transmission Corporation (Tantransco) is venturing into the tariff-based competitive bidding (TBCB) model to develop a new greenfield 765/400 kV substation in the Coimbatore region. This initiative, part of a larger power transmission project worth Rs 4,500 crore, also includes the development of 240 kilometers of transmission lines extending from Ariyalur to Tirupur, where the new facility will be established. This decision marks a significant shift from traditional state-funded projects to public-private partnership (PPP) models. The 765 kV substation, lo..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000