NGT orders razing Godrej Properties and Wonder projects in Bengaluru
Real Estate

NGT orders razing Godrej Properties and Wonder projects in Bengaluru

The National Green Tribunal has cancelled the environmental clearance (EC) of a high-rise luxury project by Wonder Projects Development Private Limited and Godrej Properties Limited in Bengaluru and ordered immediate demolition of the project.

The green panel told the media that they impose coverage for damage to the environment as 10% of the project cost. It ordered a penalty of Rs 31 crore on the project proponent. The amount will be used for the destruction of the buildings, renovation of the area to the original position, rejuvenation and reforestation of the Kaikondrahalli lake and its surrounding region.

A bench headed by NGT Chairperson Justice Adarsh Kumar Goel imposed Rs 10 lakh on Bruhat Bengaluru Mahanagara Palike (BBMP) that approved construction/alteration of Storm Water Drain passing through the project site illegally.

The order came on a petition registered by Bengaluru resident H P Rajanna against the project, Godrej Reflections, being constructed at Kasavanahalli village in Varthur Hobli in Battleground Urban district.

Godrej Properties spokesperson told the media that NGT passed an opposing order concerning one of their projects in Bengaluru. The order did not consider all assertions and arguments presented by them. It is the second time NGT has cancelled the EC.

The Supreme Court had earlier set aside the NGT order revoking the environmental clearance given to the project.

Noting that the construction raised by the project proponent began even before granting of approval to install by Karnataka State Pollution Control Board (KSPCB) and in infringement of provisions of EC, the NGT Friday ordered that the buildings made on-site should be razed immediately.

The tribunal told the media that the penalty would be used by preparing a restoration plan by the said authority with the help of the BBMP, KSPCB and Central Pollution Control Board (CPCB).

Restoration plan shall be implemented by State Wetland Authority, and BBMP which may also be managed by KSPCB and CPCB, it said.

NGT told the media that the restoration plan should be prepared within two months and implemented within a year while making it clear that if any amount remains available after undertaking the restoration work, it would be used by the Wetland Authority for maintenance and beautification of the lakes in question.

The bench said that BBMP would make up the deficiency amount if it is found to be deficient. If any question remains unsolved, but in the authorities, the National Wetland Authority is ordered to fix the same.

The tribunal said that the confidence of the project proponent in moving ahead at different levels without considering Statutory Provisions, Procedures and Environmental Laws, approved by some of the statutory authorities is visible by the direction of senior officers of various departments who were elected members of the Committee by Tribunal and Environment Ministry, yet they opposed the same.

The bench said that there is an evident absence of bonafide on the part of the officials and this conduct deserves to be strongly condemned. They requested the Secretary, MoEF (Ministry of Environment and Forest), to look into the case and take relevant action against such erring authorities.

Image Source


Also read: DTCP razes two illegal colonies in Gurugram

Also read: DTCP ramps up action against illegal constructions in Gurugram

The National Green Tribunal has cancelled the environmental clearance (EC) of a high-rise luxury project by Wonder Projects Development Private Limited and Godrej Properties Limited in Bengaluru and ordered immediate demolition of the project. The green panel told the media that they impose coverage for damage to the environment as 10% of the project cost. It ordered a penalty of Rs 31 crore on the project proponent. The amount will be used for the destruction of the buildings, renovation of the area to the original position, rejuvenation and reforestation of the Kaikondrahalli lake and its surrounding region. A bench headed by NGT Chairperson Justice Adarsh Kumar Goel imposed Rs 10 lakh on Bruhat Bengaluru Mahanagara Palike (BBMP) that approved construction/alteration of Storm Water Drain passing through the project site illegally. The order came on a petition registered by Bengaluru resident H P Rajanna against the project, Godrej Reflections, being constructed at Kasavanahalli village in Varthur Hobli in Battleground Urban district. Godrej Properties spokesperson told the media that NGT passed an opposing order concerning one of their projects in Bengaluru. The order did not consider all assertions and arguments presented by them. It is the second time NGT has cancelled the EC. The Supreme Court had earlier set aside the NGT order revoking the environmental clearance given to the project. Noting that the construction raised by the project proponent began even before granting of approval to install by Karnataka State Pollution Control Board (KSPCB) and in infringement of provisions of EC, the NGT Friday ordered that the buildings made on-site should be razed immediately. The tribunal told the media that the penalty would be used by preparing a restoration plan by the said authority with the help of the BBMP, KSPCB and Central Pollution Control Board (CPCB). Restoration plan shall be implemented by State Wetland Authority, and BBMP which may also be managed by KSPCB and CPCB, it said. NGT told the media that the restoration plan should be prepared within two months and implemented within a year while making it clear that if any amount remains available after undertaking the restoration work, it would be used by the Wetland Authority for maintenance and beautification of the lakes in question. The bench said that BBMP would make up the deficiency amount if it is found to be deficient. If any question remains unsolved, but in the authorities, the National Wetland Authority is ordered to fix the same. The tribunal said that the confidence of the project proponent in moving ahead at different levels without considering Statutory Provisions, Procedures and Environmental Laws, approved by some of the statutory authorities is visible by the direction of senior officers of various departments who were elected members of the Committee by Tribunal and Environment Ministry, yet they opposed the same. The bench said that there is an evident absence of bonafide on the part of the officials and this conduct deserves to be strongly condemned. They requested the Secretary, MoEF (Ministry of Environment and Forest), to look into the case and take relevant action against such erring authorities. Image Source Also read: DTCP razes two illegal colonies in Gurugram Also read: DTCP ramps up action against illegal constructions in Gurugram

Next Story
Infrastructure Transport

Anand Vihar and Punjabi Bagh Flyovers Ready

Work on two major road infrastructure projects, the Anand Vihar flyover and the Punjabi Bagh flyover, has been completed but are yet to be opened for public use, according to officials. Located in highly congested areas, work on these projects started around two years ago. "The work on the flyover is complete and it is ready for opening," said a PWD official on Wednesday. According to sources, both the flyovers are likely to be inaugurated closer to the assembly elections in Delhi, scheduled for early next year. During the time the work was under way, motorists faced heavy traffic congestion ..

Next Story
Infrastructure Transport

RDSO finalise oscillation trials on Indore Metro

Indore Metro Phase 1 advances with the completion of oscillation and brake performance trials on the Yellow Line through three coaches manufactured by Alstom conducted by Research Design and Standards Organisation (RDSO). The oscillation trials were conducted with an aim to evaluate the stability and performance of the three different coaches during the movement, ensuring that the commencement of operation on Indore metro meets the safety and performance standard. The Emergency Braking Distance (EBD) was also reviewed by the RDSO team to evaluate the efficient stopping of trains during the op..

Next Story
Infrastructure Urban

IIT Guwahati develops sustainable geopolymer

A research team at the Indian Institute of Technology Guwahati, led by Prof. Anil K. Mishra from the Department of Civil Engineering, has developed an innovative solution to two major global challenges: industrial waste management and sustainable construction. Their research focuses on creating a geopolymer using industrial byproducts and waste materials, such as water treatment sludge (WTS), fly ash (FA), and ground granulated blast furnace slag (GGBS). “With the rapid pace of urbanisation and industrialisation, managing industrial waste has become a critical global issue," said IIT Guwaha..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000