NCDRC directs Godrej Projects to refund Rs 40 million to homebuyers
Real Estate

NCDRC directs Godrej Projects to refund Rs 40 million to homebuyers

The National Consumer Disputes Redressal Commission (NCDRC) has ordered Godrej Projects, a major real estate company, to refund over Rs 40 million to homebuyers in five separate cases due to its failure to meet promised commitments, including the construction of a 24-metre-wide road and other essential amenities, even seven years after the bookings were made. The homebuyers had purchased flats in the ‘Godrej Summit’ project located in Sector 104, Gurgaon.

The NCDRC also directed the builder to pay 9 per cent interest on the refund amount. A panel of the commission, led by presiding member Ram Surat Ram Maurya and member Bharat Kumar Pandya, held the builder responsible for "failing to deliver on its promises," particularly regarding the construction of the wide road and essential amenities.

The bench noted that although possession had been offered, seven years had passed without the promised road being built. Expensive flats were sold under the representation that the project would be connected to the Dwarka Expressway via the wide road. Separate entry and exit points were also promised for each of the three sections—A, B, and C—of the society. However, the builder had constructed an alternative entrance and exit gate for Parcel A on a 10.06-meter-wide road, which was under encroachment. Buyers of flats in Parcels B and C were required to enter through the gate of Parcel A and travel across a narrow road, a shortfall that the panel stated amounted to a "deficiency in services" and justified the homebuyers' decision to seek refunds, which was not considered a breach of contract.

The builder argued that it was actively working on the road's construction and had even filed a civil writ petition in the Punjab and Haryana High Court to expedite the process. However, the NCDRC found these efforts insufficient, stating that the builder could not evade responsibility by blaming government authorities. The commission ruled that it was the builder's duty to ensure the provision of the road as promised.

A spokesperson for Godrej Projects commented that the refund order was related to the non-construction of the 24-metre-wide road, even though the NCDRC had previously ruled that the developer was not responsible for constructing the road outside the project. The spokesperson also mentioned that the matter was still sub judice and that the company was confident in its case and was seeking legal advice on filing an appeal against the latest orders.

The National Consumer Disputes Redressal Commission (NCDRC) has ordered Godrej Projects, a major real estate company, to refund over Rs 40 million to homebuyers in five separate cases due to its failure to meet promised commitments, including the construction of a 24-metre-wide road and other essential amenities, even seven years after the bookings were made. The homebuyers had purchased flats in the ‘Godrej Summit’ project located in Sector 104, Gurgaon. The NCDRC also directed the builder to pay 9 per cent interest on the refund amount. A panel of the commission, led by presiding member Ram Surat Ram Maurya and member Bharat Kumar Pandya, held the builder responsible for failing to deliver on its promises, particularly regarding the construction of the wide road and essential amenities. The bench noted that although possession had been offered, seven years had passed without the promised road being built. Expensive flats were sold under the representation that the project would be connected to the Dwarka Expressway via the wide road. Separate entry and exit points were also promised for each of the three sections—A, B, and C—of the society. However, the builder had constructed an alternative entrance and exit gate for Parcel A on a 10.06-meter-wide road, which was under encroachment. Buyers of flats in Parcels B and C were required to enter through the gate of Parcel A and travel across a narrow road, a shortfall that the panel stated amounted to a deficiency in services and justified the homebuyers' decision to seek refunds, which was not considered a breach of contract. The builder argued that it was actively working on the road's construction and had even filed a civil writ petition in the Punjab and Haryana High Court to expedite the process. However, the NCDRC found these efforts insufficient, stating that the builder could not evade responsibility by blaming government authorities. The commission ruled that it was the builder's duty to ensure the provision of the road as promised. A spokesperson for Godrej Projects commented that the refund order was related to the non-construction of the 24-metre-wide road, even though the NCDRC had previously ruled that the developer was not responsible for constructing the road outside the project. The spokesperson also mentioned that the matter was still sub judice and that the company was confident in its case and was seeking legal advice on filing an appeal against the latest orders.

Next Story
Infrastructure Energy

REC Transfers HVDC Project to Power Grid

REC Limited has successfully handed over the Special Purpose Vehicle (SPV) for a High-Voltage Direct Current (HVDC) transmission project to Power Grid Corporation of India Limited (PGCIL). This strategic move aligns with the nation's objectives to strengthen its power transmission network. Key Highlights: Project Overview: The HVDC project, under the inter-state transmission system (ISTS) initiative, is a critical component of India's push toward robust and efficient electricity transmission. It aims to handle bulk power transfer across long distances while ensuring minimal losses. Role of RE..

Next Story
Infrastructure Transport

NF Railway Collaborates with IIT Guwahati

The Northeast Frontier (NF) Railway has signed strategic Memorandums of Understanding (MoUs) with IIT Guwahati to foster technological advancements and improve railway operations in the region. This partnership focuses on innovative solutions to enhance safety, efficiency, and sustainability in rail infrastructure. Key Highlights: Purpose of MoUs: The collaboration aims to leverage IIT Guwahati's expertise in technology and research for implementing cutting-edge solutions across railway operations. Key areas of focus include: Automation and digitization in maintenance. Sustainability initiati..

Next Story
Infrastructure Transport

Danapur Division Modernization Plans Revealed

The Railway Board has unveiled ambitious plans for the expansion and modernization of the Danapur Division, a critical hub under the East Central Railway. The initiative focuses on infrastructure development, enhanced passenger amenities, and operational efficiency. Key Highlights: Scope of Modernization: The Railway Board's blueprint emphasizes: Upgrading existing infrastructure to accommodate more passenger and freight traffic. Improving station facilities, such as platforms, waiting areas, and connectivity. Introducing advanced signal systems for safer and smoother operations. Freig..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000