NCDRC directs Godrej Projects to refund Rs 40 million to homebuyers
Real Estate

NCDRC directs Godrej Projects to refund Rs 40 million to homebuyers

The National Consumer Disputes Redressal Commission (NCDRC) has ordered Godrej Projects, a major real estate company, to refund over Rs 40 million to homebuyers in five separate cases due to its failure to meet promised commitments, including the construction of a 24-metre-wide road and other essential amenities, even seven years after the bookings were made. The homebuyers had purchased flats in the ‘Godrej Summit’ project located in Sector 104, Gurgaon.

The NCDRC also directed the builder to pay 9 per cent interest on the refund amount. A panel of the commission, led by presiding member Ram Surat Ram Maurya and member Bharat Kumar Pandya, held the builder responsible for "failing to deliver on its promises," particularly regarding the construction of the wide road and essential amenities.

The bench noted that although possession had been offered, seven years had passed without the promised road being built. Expensive flats were sold under the representation that the project would be connected to the Dwarka Expressway via the wide road. Separate entry and exit points were also promised for each of the three sections—A, B, and C—of the society. However, the builder had constructed an alternative entrance and exit gate for Parcel A on a 10.06-meter-wide road, which was under encroachment. Buyers of flats in Parcels B and C were required to enter through the gate of Parcel A and travel across a narrow road, a shortfall that the panel stated amounted to a "deficiency in services" and justified the homebuyers' decision to seek refunds, which was not considered a breach of contract.

The builder argued that it was actively working on the road's construction and had even filed a civil writ petition in the Punjab and Haryana High Court to expedite the process. However, the NCDRC found these efforts insufficient, stating that the builder could not evade responsibility by blaming government authorities. The commission ruled that it was the builder's duty to ensure the provision of the road as promised.

A spokesperson for Godrej Projects commented that the refund order was related to the non-construction of the 24-metre-wide road, even though the NCDRC had previously ruled that the developer was not responsible for constructing the road outside the project. The spokesperson also mentioned that the matter was still sub judice and that the company was confident in its case and was seeking legal advice on filing an appeal against the latest orders.

The National Consumer Disputes Redressal Commission (NCDRC) has ordered Godrej Projects, a major real estate company, to refund over Rs 40 million to homebuyers in five separate cases due to its failure to meet promised commitments, including the construction of a 24-metre-wide road and other essential amenities, even seven years after the bookings were made. The homebuyers had purchased flats in the ‘Godrej Summit’ project located in Sector 104, Gurgaon. The NCDRC also directed the builder to pay 9 per cent interest on the refund amount. A panel of the commission, led by presiding member Ram Surat Ram Maurya and member Bharat Kumar Pandya, held the builder responsible for failing to deliver on its promises, particularly regarding the construction of the wide road and essential amenities. The bench noted that although possession had been offered, seven years had passed without the promised road being built. Expensive flats were sold under the representation that the project would be connected to the Dwarka Expressway via the wide road. Separate entry and exit points were also promised for each of the three sections—A, B, and C—of the society. However, the builder had constructed an alternative entrance and exit gate for Parcel A on a 10.06-meter-wide road, which was under encroachment. Buyers of flats in Parcels B and C were required to enter through the gate of Parcel A and travel across a narrow road, a shortfall that the panel stated amounted to a deficiency in services and justified the homebuyers' decision to seek refunds, which was not considered a breach of contract. The builder argued that it was actively working on the road's construction and had even filed a civil writ petition in the Punjab and Haryana High Court to expedite the process. However, the NCDRC found these efforts insufficient, stating that the builder could not evade responsibility by blaming government authorities. The commission ruled that it was the builder's duty to ensure the provision of the road as promised. A spokesperson for Godrej Projects commented that the refund order was related to the non-construction of the 24-metre-wide road, even though the NCDRC had previously ruled that the developer was not responsible for constructing the road outside the project. The spokesperson also mentioned that the matter was still sub judice and that the company was confident in its case and was seeking legal advice on filing an appeal against the latest orders.

Next Story
Infrastructure Energy

RECPDCL transfers Rajasthan-IV H-1 power transmission to Power Grid Corp

State-owned REC announced that its subsidiary, REC Power Development and Consultancy (RECPDCL), had transferred the Rajasthan-IV H-1 Power Transmission, a special purpose vehicle (SPV), to Power Grid Corporation of India (PGCIL). PGCIL had been selected as the transmission service provider (TSP) through a tariff-based competitive bidding (TBCB) process, which was organised by RECPDCL, acting as the Bid Process Coordinator (BPC), for the development of the transmission project on a Build, Own, Operate & Transfer (BOOT) basis, as mentioned in a company statement. The statement further indicate..

Next Story
Infrastructure Transport

BEML Secures Rs 8.67 Billion Deal to Build India’s First Bullet Train

State-owned BEML has been awarded a contract to build India’s first indigenously manufactured bullet train, with a total value of Rs 8.66 billion. According to a statement from BEML, Indian Railways' production unit, Integral Coach Factory (ICF), has placed an order for the design, manufacturing, and commissioning of two high-speed trainsets, each consisting of eight cars (coaches). BEML noted that each coach will cost Rs 270.86 million, with the total contract value including expenses for design, one-time development, non-recurring charges, and the cost of jigs, fixtures, tooling, and test..

Next Story
Infrastructure Urban

KBC Global to raise Rs 1 billion via equity share issuance

Construction and infrastructure company KBC Global announced its plan to raise up to Rs 1 billion through the issuance of equity shares. The company's board will review and approve a proposal for raising the funds through equity share issuance via various permissible methods, including preferential allotment and warrants, according to a statement by the company. The company indicated that the proceeds from the equity issue would be used to repay its debt. As of March 31, 2024, the company had an outstanding loan balance of Rs 750.86 million. KBC Global also mentioned that on September 21..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000