MNRE directs the release of PBGs within 45 days after project completion
Real Estate

MNRE directs the release of PBGs within 45 days after project completion

Reportedly, the Ministry of New and Renewable Energy (MNRE) has instructed NTPC and Solar Energy Corporation of India (SECI) to release performance bank guarantees (PBGs) for all the commissioned wind and solar power projects. The PBGs can be released in the span of 45 days from the commercial operation date (COD), on the condition that all required submission of necessary documents is fulfilled.

 

Additionally, MNRE has also stated that under any circumstance developers find delay in the release of the PBGs, they should inform the ministry as well as the managing director of the respective procurer.

 

When wind or solar power developers successfully bid for certain projects, they are issued a letter of intent. Following 30 days from the time of its issuance, they must deposit a PBG, which is an irrevocable unconditional ban guarantee, to the SECI or NTPC.

In most situations, the PBG is released as soon as a renewable energy project is successfully commissioned, after considering issued related to liquidated damages or penalties arising from delay in commissioning in accordance to the provisions mentioned in a power purchase agreement.

As reported, however, most developers are troubled with issues relating to the timely release of bank guarantees. This is a worrying factor since any delay in the release of PBGs can lead to financial losses for these developers due to blockage of funds.

In one such case, the Central Electricity Regulatory Commission (CERC) ruled in the favor of three separate power producers against NTPC and declared that the retention of PBGs by the power corporation was illegal and arbitrary. 

Reportedly, the Ministry of New and Renewable Energy (MNRE) has instructed NTPC and Solar Energy Corporation of India (SECI) to release performance bank guarantees (PBGs) for all the commissioned wind and solar power projects. The PBGs can be released in the span of 45 days from the commercial operation date (COD), on the condition that all required submission of necessary documents is fulfilled.   Additionally, MNRE has also stated that under any circumstance developers find delay in the release of the PBGs, they should inform the ministry as well as the managing director of the respective procurer.   When wind or solar power developers successfully bid for certain projects, they are issued a letter of intent. Following 30 days from the time of its issuance, they must deposit a PBG, which is an irrevocable unconditional ban guarantee, to the SECI or NTPC. In most situations, the PBG is released as soon as a renewable energy project is successfully commissioned, after considering issued related to liquidated damages or penalties arising from delay in commissioning in accordance to the provisions mentioned in a power purchase agreement. As reported, however, most developers are troubled with issues relating to the timely release of bank guarantees. This is a worrying factor since any delay in the release of PBGs can lead to financial losses for these developers due to blockage of funds. In one such case, the Central Electricity Regulatory Commission (CERC) ruled in the favor of three separate power producers against NTPC and declared that the retention of PBGs by the power corporation was illegal and arbitrary. 

Next Story
Infrastructure Energy

REC Transfers HVDC Project to Power Grid

REC Limited has successfully handed over the Special Purpose Vehicle (SPV) for a High-Voltage Direct Current (HVDC) transmission project to Power Grid Corporation of India Limited (PGCIL). This strategic move aligns with the nation's objectives to strengthen its power transmission network. Key Highlights: Project Overview: The HVDC project, under the inter-state transmission system (ISTS) initiative, is a critical component of India's push toward robust and efficient electricity transmission. It aims to handle bulk power transfer across long distances while ensuring minimal losses. Role of RE..

Next Story
Infrastructure Transport

NF Railway Collaborates with IIT Guwahati

The Northeast Frontier (NF) Railway has signed strategic Memorandums of Understanding (MoUs) with IIT Guwahati to foster technological advancements and improve railway operations in the region. This partnership focuses on innovative solutions to enhance safety, efficiency, and sustainability in rail infrastructure. Key Highlights: Purpose of MoUs: The collaboration aims to leverage IIT Guwahati's expertise in technology and research for implementing cutting-edge solutions across railway operations. Key areas of focus include: Automation and digitization in maintenance. Sustainability initiati..

Next Story
Infrastructure Transport

Danapur Division Modernization Plans Revealed

The Railway Board has unveiled ambitious plans for the expansion and modernization of the Danapur Division, a critical hub under the East Central Railway. The initiative focuses on infrastructure development, enhanced passenger amenities, and operational efficiency. Key Highlights: Scope of Modernization: The Railway Board's blueprint emphasizes: Upgrading existing infrastructure to accommodate more passenger and freight traffic. Improving station facilities, such as platforms, waiting areas, and connectivity. Introducing advanced signal systems for safer and smoother operations. Freig..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000