MahaRERA lists 1,824 housing projects as expired
Real Estate

MahaRERA lists 1,824 housing projects as expired

The Maharashtra Real Estate Regulatory Authority (MahaRERA) has listed down 1,824 housing projects across the state as ‘expired’ for exceeding completion deadlines set by the regulatory body.

The projects would now require approval from 51% buyers for obtaining an extension of the completion dates. 103 such projects overshot the completion deadline in 2017, 541 in 2018 and 1,180 in 2019.

According to Section 6 of the Real Estate (Regulation and Development) Act, many projects had failed to achieve even after an extension of one year.

As per the Act, the project developers are restricted from selling, advertising or marketing them before asking for an extension. Of the total 1,824 projects declared as expired by MahaRERA, extension applications of 350 projects have been presented.

MahaRERA had granted an extension to the deadlines till September for the projects that were supposed to be completed in March.

A MahaRERA official told the media that the remaining projects had deadlines before the pandemic year of 2020. Most of the projects are in Mumbai, Thane, Pune and Raigad. Another 1,500 projects might be under the scanner since their deadline got over in March 2021. The developers of these projects can now avail of a one-year extension under Section 6 of RERA.

Developers felt that the officials should take a considerate approach since the market had been down and there were challenges in getting documents within the deadline.

Anuj Puri, Anarock Property consultants chairman, told the media that the MahaRERA’s decision sent a strong signal to the errant developers delaying the projects.

Homebuyers have been waiting to get ownership of projects for the last three years.

Sunil Furde, CREDAI Maharashtra president, told the media that MahaRERA was correct in pointing out the status of the unfinished projects. However, many projects are displayed as incomplete due to technical errors.

He said projects of CREDAI members declared on the portal had been completed on time. The project completion certificate has been received from the municipal corporations before the listed dates. Some projects were achieved but the completion certificates were received later, he said.

Image Source


Also read: Out of 644 blacklisted realty projects in Maharashtra, 189 in Pune

Also read: More than 90 unfinished realty projects to shut down in UP: UP-RERA

Redefine the future of urban mobility! Join us at the Metro Rail Conference 2025 to explore groundbreaking ideas and insights. 👉 Register today!

The Maharashtra Real Estate Regulatory Authority (MahaRERA) has listed down 1,824 housing projects across the state as ‘expired’ for exceeding completion deadlines set by the regulatory body. The projects would now require approval from 51% buyers for obtaining an extension of the completion dates. 103 such projects overshot the completion deadline in 2017, 541 in 2018 and 1,180 in 2019. According to Section 6 of the Real Estate (Regulation and Development) Act, many projects had failed to achieve even after an extension of one year. As per the Act, the project developers are restricted from selling, advertising or marketing them before asking for an extension. Of the total 1,824 projects declared as expired by MahaRERA, extension applications of 350 projects have been presented. MahaRERA had granted an extension to the deadlines till September for the projects that were supposed to be completed in March. A MahaRERA official told the media that the remaining projects had deadlines before the pandemic year of 2020. Most of the projects are in Mumbai, Thane, Pune and Raigad. Another 1,500 projects might be under the scanner since their deadline got over in March 2021. The developers of these projects can now avail of a one-year extension under Section 6 of RERA. Developers felt that the officials should take a considerate approach since the market had been down and there were challenges in getting documents within the deadline. Anuj Puri, Anarock Property consultants chairman, told the media that the MahaRERA’s decision sent a strong signal to the errant developers delaying the projects. Homebuyers have been waiting to get ownership of projects for the last three years. Sunil Furde, CREDAI Maharashtra president, told the media that MahaRERA was correct in pointing out the status of the unfinished projects. However, many projects are displayed as incomplete due to technical errors. He said projects of CREDAI members declared on the portal had been completed on time. The project completion certificate has been received from the municipal corporations before the listed dates. Some projects were achieved but the completion certificates were received later, he said. Image Source Also read: Out of 644 blacklisted realty projects in Maharashtra, 189 in Pune Also read: More than 90 unfinished realty projects to shut down in UP: UP-RERA

Next Story
Real Estate

Colliers India Transacts 207,000 sq ft office space at Embassy TechVillage

Embassy Office Parks REIT, India’s first listed REIT and the largest office REIT in Asia by area, announced that it has signed an Agreement to Lease (‘ATL’) with global cyber security company Rubrik at Embassy TechVillage in Bengaluru.Colliers, a leading global diversified professional services company, specialising in commercial real estate services, engineering consultancy and investment management facilitated the transaction for Rubrik.Located on Bengaluru’s Outer Ring Road, Embassy TechVillage is one of Embassy REIT’s flagship office parks which offers world-class office spaces, ..

Next Story
Infrastructure Urban

Ensemble Infrastructure India Appoints Suman Saha as Director of Design

Ensemble Infrastructure India Ltd, a leading workplace design and build fit-out company, has appointed Suman Saha as its new Director of Design. With 25 years of experience in the industry, Suman is recognized for his innovative approach and excellence in design leadership.Working closely with the CEO, Suman’s appointment will enhance the company’s design communication across multiple touchpoints, ensuring smooth collaboration between clients, designers, and execution teams for superior project outcomes. Under his guidance, Ensemble will focus on creating workspaces and design labs that em..

Next Story
Products

Ribbon Vanity by Küche7: Fluid Design Meets Everyday Elegance

Küche7, pioneers in luxury stainless steel kitchens, have unveiled the Ribbon Vanity, a graceful creation that transforms bathroom spaces with its soft, flowing design and understated sophistication. Inspired by the fluid form of a ribbon, this vanity combines smooth finishes, clean lines, and gentle curves, offering a timeless aesthetic that seamlessly complements diverse interior styles.Available in a refined blush pink hue, the Ribbon Vanity effortlessly merges functionality with elegance. With thoughtfully designed storage options, it ensures that bathroom essentials are neatly organised ..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000