MahaRERA grants relief to over 70 Ruparel Skygreens buyers
Real Estate

MahaRERA grants relief to over 70 Ruparel Skygreens buyers

In a recent order, the MahaRERA granted relief to over 70 homebuyers who had booked flats in the Ruparel Skygreens project in Borivli. The promoter had failed to deliver possession to the allottees, including those who had booked under the subvention scheme and the construction link plan scheme, by the agreed dates as well as by the MahaRERA completion date of December 2021.

MahaRERA Chairman Ajoy Mehta directed the promoter to refund the entire amounts received to some of the allottees with interest, while others would receive refunds without interest. He also instructed the promoter to execute and register cancellation deeds, cancel allotment letters and agreements for sale, and refund the amounts paid by the allottees. Additionally, possession with an occupancy certificate (OC) was to be handed over to certain allottees, along with interest for the delay, depending on the various reliefs sought.

However, the regulatory authority dismissed some complaints due to maintainability and lack of evidence. MahaRERA vacated a previous order that had restrained Piramal Capital & Housing Finance Limited from taking any coercive action, stating that it had determined the rights of the allottees and fixed the obligations of the promoter. The authority clarified that it did not have the mandate to adjudicate on the tripartite agreement binding the allottee, promoter, and lender, but directed the parties to strictly adhere to the terms of that agreement. The allottees had complained that the finance company had initiated proceedings under the SARFAESI Act.

The MahaRERA order acknowledged the complexities involved in executing a real estate project but noted that developers undertaking such projects are well aware of these issues. One of the allottees filed a complaint seeking a refund of amounts paid to the promoter due to the significant delay in handing over possession of a flat booked in 2017. The complainant stated that, according to the agreement, possession was to be delivered on or before December 2021.

The promoter had informed the complainant about the subvention scheme, which stipulated that the liability for payment until the physical possession of the flat would rest with the promoter, thereby ensuring that the complainants would not be burdened with any payment obligations until that time.

In a recent order, the MahaRERA granted relief to over 70 homebuyers who had booked flats in the Ruparel Skygreens project in Borivli. The promoter had failed to deliver possession to the allottees, including those who had booked under the subvention scheme and the construction link plan scheme, by the agreed dates as well as by the MahaRERA completion date of December 2021. MahaRERA Chairman Ajoy Mehta directed the promoter to refund the entire amounts received to some of the allottees with interest, while others would receive refunds without interest. He also instructed the promoter to execute and register cancellation deeds, cancel allotment letters and agreements for sale, and refund the amounts paid by the allottees. Additionally, possession with an occupancy certificate (OC) was to be handed over to certain allottees, along with interest for the delay, depending on the various reliefs sought. However, the regulatory authority dismissed some complaints due to maintainability and lack of evidence. MahaRERA vacated a previous order that had restrained Piramal Capital & Housing Finance Limited from taking any coercive action, stating that it had determined the rights of the allottees and fixed the obligations of the promoter. The authority clarified that it did not have the mandate to adjudicate on the tripartite agreement binding the allottee, promoter, and lender, but directed the parties to strictly adhere to the terms of that agreement. The allottees had complained that the finance company had initiated proceedings under the SARFAESI Act. The MahaRERA order acknowledged the complexities involved in executing a real estate project but noted that developers undertaking such projects are well aware of these issues. One of the allottees filed a complaint seeking a refund of amounts paid to the promoter due to the significant delay in handing over possession of a flat booked in 2017. The complainant stated that, according to the agreement, possession was to be delivered on or before December 2021. The promoter had informed the complainant about the subvention scheme, which stipulated that the liability for payment until the physical possession of the flat would rest with the promoter, thereby ensuring that the complainants would not be burdened with any payment obligations until that time.

Next Story
Technology

AI-Enabled Workflows Lift Profitability and Productivity

Organisations modernising frontline workflows with artificial intelligence, automation and real-time data are reporting stronger financial performance, higher productivity and improved employee engagement, according to a global study by Zebra Technologies and Oxford Economics.The research covered 1,000 senior leaders across retail, manufacturing, transportation and logistics in the US, Mexico, the UK, Germany, India, Japan, Australia and New Zealand.In transportation and logistics, 54 per cent of companies that improved picking and packing operations reported faster operational performance, wh..

Next Story
Real Estate

India Leads Global AI Readiness but Implementation Lags

Indian companies lead global averages across all eight artificial intelligence readiness indicators tracked by JLL, but only 19 per cent have started making changes to their workplaces, according to the JLL 2026 Future of Work Survey.The study found that 77 per cent of Indian business leaders expect AI to change their office requirements, creating a 58-percentage-point gap between awareness and implementation. The survey covered more than 2,200 CEOs, CFOs and real estate leaders across 21 countries during the first quarter of 2026.Despite concerns over automation, 58 per cent of Indian leaders..

Next Story
Equipment

Three WOLFF Cranes Build Riyadh Cable-Stayed Bridges

Three WOLFF 180 B luffing jib cranes are supporting the construction of two cable-stayed bridges alongside the existing Wadi Laban Bridge in Riyadh, Saudi Arabia. The project is being developed for the Royal Commission for Riyadh City and executed by the ICRC joint venture comprising IC Ictas and Al Rashid Trading & Contracting Company.The cranes are handling lifting operations including formwork, reinforcement, concrete placement, work platforms, surveying equipment and other construction materials. Each crane is fitted with a 40 m jib, reaches a hook height of 157 m and offers a maximum ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement