Bombay HC: Macrotech Developers Not Responsible for Delay, Rebate Still Valid
Real Estate

Bombay HC: Macrotech Developers Not Responsible for Delay, Rebate Still Valid

In a significant ruling, the Bombay High Court (HC) has absolved Macrotech Developers of any culpability for project delays, affirming the continued validity of a rebate. This decision comes as a relief to the real estate developer, known for its prominent projects, as it reaffirms their commitment to project timelines. The case revolved around a delay in the completion of a real estate project, and whether Macrotech Developers were responsible for it. The HC's verdict unequivocally states that the delay was not caused by the developer. This ruling is expected to have far-reaching implications on similar cases within the Indian real estate sector, as it underlines the importance of accurately attributing responsibility for project delays. With the rebate now confirmed, this outcome carries both financial and reputational significance for Macrotech Developers. The company can continue to offer the agreed-upon incentive to homebuyers, enhancing trust and credibility in the market. This decision reiterates the crucial role of the judiciary in resolving disputes within the real estate industry, promoting transparency, and upholding contractual obligations.
Redefine the future of urban mobility! Join us at the Metro Rail Conference 2025 to explore groundbreaking ideas and insights. 👉 Register today!

In a significant ruling, the Bombay High Court (HC) has absolved Macrotech Developers of any culpability for project delays, affirming the continued validity of a rebate. This decision comes as a relief to the real estate developer, known for its prominent projects, as it reaffirms their commitment to project timelines. The case revolved around a delay in the completion of a real estate project, and whether Macrotech Developers were responsible for it. The HC's verdict unequivocally states that the delay was not caused by the developer. This ruling is expected to have far-reaching implications on similar cases within the Indian real estate sector, as it underlines the importance of accurately attributing responsibility for project delays. With the rebate now confirmed, this outcome carries both financial and reputational significance for Macrotech Developers. The company can continue to offer the agreed-upon incentive to homebuyers, enhancing trust and credibility in the market. This decision reiterates the crucial role of the judiciary in resolving disputes within the real estate industry, promoting transparency, and upholding contractual obligations.

Next Story
Infrastructure Energy

Orb Energy Achieves Rs 3 Bn Milestone in Solar Financing Success

Orb Energy, a vertically integrated solar energy solutions provider, has achieved a significant milestone by surpassing Rs 3 billion in financing disbursements through its in-house finance facility that requires no collateral or down payment. This accomplishment underscores its dedication to supporting small and medium enterprises (SMEs) and micro, small, and medium enterprises (MSMEs) in India in transitioning to cost-effective solar energy solutions. The company has installed approximately 350 MW of solar photovoltaic systems nationwide, with a strong foothold in southern and western India...

Next Story
Infrastructure Energy

90% Defaulters Yet to Settle Rs 3.17 Bn Power Dues in Noida

Out of a total of 1.31 lakh defaulters in Noida, only 13,500 consumers availed of the one-time settlement (OTS) scheme during its first phase. The Uttar Pradesh Power Corporation (UPPCL) launched the scheme in three phases, from December 15, 2024, to January 31, 2025. These consumers cleared dues amounting to Rs 300.40 million out of a total Rs 3.47 billion owed. Officials emphasized that stricter enforcement of the scheme would be implemented in the coming phases. During a recent weekend meeting with the technical team of the power department, the Noida zone's chief engineer instructed that..

Next Story
Infrastructure Energy

NER Invites Bids for 10 MW Rooftop Solar Projects in Uttar Pradesh

The Varanasi division (electrical) of Northeastern Railway has recently issued four tenders for a total of 10.4 MW on-grid rooftop solar systems to be installed at various buildings in Gorakhpur, Uttar Pradesh. The tenders include different project capacities, with submission deadlines set between January 31 and February 3, 2025. Bidders are required to submit earnest money deposits (EMDs) ranging from Rs 0.89 million to Rs 1.2 million depending on the tender, with the expected project costs varying between Rs 148 million and Rs 174.08 million. The selected contractors will be tasked with sup..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000