COVID-19 lockdown stalls construction activities
Real Estate

COVID-19 lockdown stalls construction activities

Image courtesy: Hindustan Times

  • More than 15.62 lakh units (launched between 2013 till 2019) are under construction in the top 7 cities.
  • Of this, MMR and NCR together comprise 57 per cent or approximately 8.90 lakh units.
  • Pune has nearly 2.62 lakh units under construction, followed by Bengaluru with 2.02 lakh units and Kolkata with approximately 90,670 units.
  • Chennai and Hyderabad together comprise just 8 per cent (approximately 1.18 lakh units) share of overall under-construction units.
  • With most top cities announcing a lockdown till at least March 31, homebuyers must brace themselves for project delays.
  • A lot is currently at stake for Indian residential real estate as cities go into complete lockdown mode to battle the spread of Covid-19. Developers tend to schedule project launches during the auspicious festivals of Gudi Padwa, Akshaya Tritiya, Navratri and Ugadi. The strict advisories for complete lockdown across cities will impact housing sales during the upcoming festivals, usually considered auspicious by several homebuyers to buy homes.


    Prashant Thakur, Director & Head-Research, Anarock Property Consultants, says, “Another fallout of the lockdown is that many key markets will have almost zero construction activity at the project sites. This will further strain several developers’ financial health. As many as 15.62 lakh units across the top 7 cities were in various stages of construction as on 2019 end, reveals Anarock research. These include all under-construction units launched between 2013 till 2019-end. Even this figure is conservative – the number of units will be higher once Q1 2020 data comes in.”

    “Further analysis reveals that out of these 15.62 lakh units under construction, nearly 57 per cent or nearly 8.90 lakh units are in MMR and NCR alone. Both these regions already have a backlog of lakhs of delayed or stalled units. With construction activity almost coming to a standstill, homebuyers will have to brace themselves for another wave of delayed project deliveries.”

    Under-construction stock - city-wise

  • MMR currently has the highest under-construction stock with nearly 4.65 lakh units – 30 per cent of the overall under-construction stock across the top 7 cities.
  • NCR is close behind with 27 per cent or over 4.25 lakh units in various stages of construction. All these units were launched between 2013 till 2019-end.
  • Pune has close to 2.62 lakh units in various stages of construction.
  • Among the three southern cities, Bengaluru has the maximum under-construction stock as on 2019-end with nearly 2.02 lakh units, followed by Hyderabad with nearly 64,250 units and Chennai with the least stock of nearly 54,200 units.
  • Kolkata currently has more than 90,650 units under construction.
  • The road to recovery
    Once the crisis is under control, the government will have to dole out various economic measures to bail out severely-hit sectors, reconsider its fiscal deficit targets and start spending. That said, since this is a crisis with pan-India ramifications, all impacted projects will have to be excused from construction delay penalties under the respective state RERA.

    Redefine the future of urban mobility! Join us at the Metro Rail Conference 2025 to explore groundbreaking ideas and insights. 👉 Register today!

    Image courtesy: Hindustan Times More than 15.62 lakh units (launched between 2013 till 2019) are under construction in the top 7 cities. Of this, MMR and NCR together comprise 57 per cent or approximately 8.90 lakh units. Pune has nearly 2.62 lakh units under construction, followed by Bengaluru with 2.02 lakh units and Kolkata with approximately 90,670 units. Chennai and Hyderabad together comprise just 8 per cent (approximately 1.18 lakh units) share of overall under-construction units. With most top cities announcing a lockdown till at least March 31, homebuyers must brace themselves for project delays. A lot is currently at stake for Indian residential real estate as cities go into complete lockdown mode to battle the spread of Covid-19. Developers tend to schedule project launches during the auspicious festivals of Gudi Padwa, Akshaya Tritiya, Navratri and Ugadi. The strict advisories for complete lockdown across cities will impact housing sales during the upcoming festivals, usually considered auspicious by several homebuyers to buy homes. Prashant Thakur, Director & Head-Research, Anarock Property Consultants, says, “Another fallout of the lockdown is that many key markets will have almost zero construction activity at the project sites. This will further strain several developers’ financial health. As many as 15.62 lakh units across the top 7 cities were in various stages of construction as on 2019 end, reveals Anarock research. These include all under-construction units launched between 2013 till 2019-end. Even this figure is conservative – the number of units will be higher once Q1 2020 data comes in.” “Further analysis reveals that out of these 15.62 lakh units under construction, nearly 57 per cent or nearly 8.90 lakh units are in MMR and NCR alone. Both these regions already have a backlog of lakhs of delayed or stalled units. With construction activity almost coming to a standstill, homebuyers will have to brace themselves for another wave of delayed project deliveries.” Under-construction stock - city-wise MMR currently has the highest under-construction stock with nearly 4.65 lakh units – 30 per cent of the overall under-construction stock across the top 7 cities. NCR is close behind with 27 per cent or over 4.25 lakh units in various stages of construction. All these units were launched between 2013 till 2019-end. Pune has close to 2.62 lakh units in various stages of construction. Among the three southern cities, Bengaluru has the maximum under-construction stock as on 2019-end with nearly 2.02 lakh units, followed by Hyderabad with nearly 64,250 units and Chennai with the least stock of nearly 54,200 units. Kolkata currently has more than 90,650 units under construction. The road to recovery Once the crisis is under control, the government will have to dole out various economic measures to bail out severely-hit sectors, reconsider its fiscal deficit targets and start spending. That said, since this is a crisis with pan-India ramifications, all impacted projects will have to be excused from construction delay penalties under the respective state RERA.

    Next Story
    Infrastructure Transport

    Anji Khad Bridge, India's First Cable-Stayed Rail Bridge Ready in J&K

    Indian Railways has completed the Anji Khad Bridge, India’s first cable-stayed rail bridge, located in the Reasi district of Jammu and Kashmir. A critical component of the ambitious Udhampur-Srinagar-Baramulla Rail Link (USBRL) Project, this engineering marvel connects Katra and Reasi, promising enhanced regional connectivity and economic growth.Spanning 725.5 metres, the bridge features a 193-metre-tall main pylon, soaring 331 metres above the riverbed. Its design allows it to withstand wind speeds of up to 213 km/h and safely support train operations at speeds of 100 km/h.Constructed in th..

    Next Story
    Infrastructure Urban

    Exporters Raise Logistics Costs Concerns with Piyush Goyal

    Exporters and freight agencies have voiced concerns over high terminal handling charges at ports and the underutilisation of dry ports, adding to India’s overall logistics costs. During a meeting with Commerce and Industry Minister Piyush Goyal, they highlighted that the fees charged by shipping terminals for container storage and positioning before loading exceed port charges by Rs 10,000-15,000 per consignment. The discussion focused on logistics and shipping challenges, with the government actively working to reduce costs across the supply chain, according to an official. India is targe..

    Next Story
    Infrastructure Transport

    Government to Revamp UDAN Scheme with Focus on Airport Readiness

    The Indian government is set to revamp its regional air connectivity scheme, UDAN (Ude Desh ka Aam Nagrik), by prioritising airport readiness before inviting airlines to bid for operating routes. Financial support for the development of unserved airports and airstrips across the country is expected to be a key focus in the upcoming budget, along with stricter assessments of route feasibility, according to sources. Launched in 2017 to boost air travel in the world’s fastest-growing aviation market, the UDAN scheme caps airfares and provides subsidies to airlines for operating on less frequen..

    Hi There!

    "Now get regular updates from CW Magazine on WhatsApp!

    Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

    Click the link below to join"

    +91 81086 03000