WOLFF cranes constructing high bridge over Neckar Valley
Equipment

WOLFF cranes constructing high bridge over Neckar Valley

When completed, this impressive 667-m-long and up to 90-m-high bridge will span the Neckar Valley near the small town of Horb in Baden-W'rttemberg. Thanks to this new bypass, traffic in the centre of Horb will be alleviated and the region's transport infrastructure will be upgraded. But until then, there will be plenty to do for the Porr GmbH & Co. KGaA construction company and the five WOLFF cranes that are in use at the enormous construction site. Their figures are also impressive: Two freestanding WOLFF cranes are operating on 96.4- and 100.9-m-high towers " a structural challenge for the Wolffkran team.

At present, the two WOLFF 7534.16 Clear cranes are drawing a lot of attention in the Neckar Valley: Both are around 100 m high and tower over the first 70-m elements of the new viaduct. Since the fall of 2023, they have been moving heavy freestanding steel components, formwork, reinforcements, and concrete buckets. With their 75-m jibs, they can lift a maximum of 16.5 tonne and 3.4 tonne at the top (4-strand operation). "This is normally not possible with a freestanding crane," explains Wolfgang Kavelius, Sales Manager at Wolffkran GmbH. "But the special design of the bridge piers meant that no tie-ins could be used, or they would have been disproportion-ately complex and expensive."

The technical WOLFF team makes it possible For this reason, Porr turned to the technical support team at Wolffkran, which not only developed a suitable crane concept but also a special structural solution for the two Porr-owned WOLFF cranes. "To ensure the necessary stability, the towers were assembled using three different tower elements," explains Peter Hegen-bart, Head of Sales Project Engineering at Wolffkran GmbH. The lower third of the towers is formed by the TV 33 tower element with a side length of 3.3 meters. Above this is a transition area composed of tower sections with a side length of 2.5 meters, which leads into the upper half of the tower made of 2x2-meter tower sections (TV 20). ?This specialized structure makes it possible to limit the maximum tower deformation to well under two meters, thus allowing the cranes to be operated safely as freestanding units," says Hegenbart.

?Thanks to Wolffkran's experience and technical expertise, we can use our own WOLFF 7534 Clear cranes as planned. This also allowed us to simply rent the additional 3.3-meter tower elements we needed for the project. We appreciate this flexibility, which goes above and beyond the normal standard, from our long-standing part-ner Wolffkran," says Markus Jahn, Project Manager at Porr.

Two-stage assembly in the narrow Neckar Valley In the inaccessible terrain of the Neckar Valley, which is also trav-ersed by an ICE railway line and a cycle path, the available space is very limited, which makes the construction site logistics particularly challenging. Because it was not possible to use a sufficiently large mobile crane to erect the two WOLFF 7534.16 Clear cranes to their ultimate heights, the assembly was carried out in two stages. After the mobile crane had assembled the tower to a height of around 60 meters, the cranes climbed the remaining 40 meters to the top using an external climbing mechanism. For space reasons, both cranes were placed on foundation anchors. As construction progresses, the complex assembly process, which takes two days per crane, will have to be repeated, as one of the two cranes will be moved to follow the progress of the expanding bridge.

The WOLFF 7534.16 Clear are currently being supported by a WOLFF 6031.12 Clear with a 65-meter jib and a 47.3-meter hook height. As the construction process moves forward, a WOLFF 7534.16 Clear and a WOLFF 6031.12 Clear from the Porr crane fleet will support the pack.

The 14th RAHSTA Expo, part of the India Construction Festival, will be held on October 9 and 10, 2024, at the Jio Convention Centre in Mumbai. For more details, visit: https://rahstaexpo.com

When completed, this impressive 667-m-long and up to 90-m-high bridge will span the Neckar Valley near the small town of Horb in Baden-W'rttemberg. Thanks to this new bypass, traffic in the centre of Horb will be alleviated and the region's transport infrastructure will be upgraded. But until then, there will be plenty to do for the Porr GmbH & Co. KGaA construction company and the five WOLFF cranes that are in use at the enormous construction site. Their figures are also impressive: Two freestanding WOLFF cranes are operating on 96.4- and 100.9-m-high towers a structural challenge for the Wolffkran team. At present, the two WOLFF 7534.16 Clear cranes are drawing a lot of attention in the Neckar Valley: Both are around 100 m high and tower over the first 70-m elements of the new viaduct. Since the fall of 2023, they have been moving heavy freestanding steel components, formwork, reinforcements, and concrete buckets. With their 75-m jibs, they can lift a maximum of 16.5 tonne and 3.4 tonne at the top (4-strand operation). This is normally not possible with a freestanding crane, explains Wolfgang Kavelius, Sales Manager at Wolffkran GmbH. But the special design of the bridge piers meant that no tie-ins could be used, or they would have been disproportion-ately complex and expensive. The technical WOLFF team makes it possible For this reason, Porr turned to the technical support team at Wolffkran, which not only developed a suitable crane concept but also a special structural solution for the two Porr-owned WOLFF cranes. To ensure the necessary stability, the towers were assembled using three different tower elements, explains Peter Hegen-bart, Head of Sales Project Engineering at Wolffkran GmbH. The lower third of the towers is formed by the TV 33 tower element with a side length of 3.3 meters. Above this is a transition area composed of tower sections with a side length of 2.5 meters, which leads into the upper half of the tower made of 2x2-meter tower sections (TV 20). ?This specialized structure makes it possible to limit the maximum tower deformation to well under two meters, thus allowing the cranes to be operated safely as freestanding units, says Hegenbart. ?Thanks to Wolffkran's experience and technical expertise, we can use our own WOLFF 7534 Clear cranes as planned. This also allowed us to simply rent the additional 3.3-meter tower elements we needed for the project. We appreciate this flexibility, which goes above and beyond the normal standard, from our long-standing part-ner Wolffkran, says Markus Jahn, Project Manager at Porr. Two-stage assembly in the narrow Neckar Valley In the inaccessible terrain of the Neckar Valley, which is also trav-ersed by an ICE railway line and a cycle path, the available space is very limited, which makes the construction site logistics particularly challenging. Because it was not possible to use a sufficiently large mobile crane to erect the two WOLFF 7534.16 Clear cranes to their ultimate heights, the assembly was carried out in two stages. After the mobile crane had assembled the tower to a height of around 60 meters, the cranes climbed the remaining 40 meters to the top using an external climbing mechanism. For space reasons, both cranes were placed on foundation anchors. As construction progresses, the complex assembly process, which takes two days per crane, will have to be repeated, as one of the two cranes will be moved to follow the progress of the expanding bridge. The WOLFF 7534.16 Clear are currently being supported by a WOLFF 6031.12 Clear with a 65-meter jib and a 47.3-meter hook height. As the construction process moves forward, a WOLFF 7534.16 Clear and a WOLFF 6031.12 Clear from the Porr crane fleet will support the pack.

Next Story
Real Estate

Singapore's CapitaLand Plans Major India Expansion

CapitaLand Investment Limited (CLI), one of Singapore's largest real estate investment managers, has announced plans to significantly expand its investments in India. The company aims to more than double its India portfolio by 2028, signaling its confidence in the country?s burgeoning real estate market. Current Portfolio and Growth Target: CLI currently manages assets worth USD 3.3 billion in India. With its sights set on future growth, the company is targeting a dramatic increase in its India investment kitty to over USD 7 billion by 2028. This move comes as part of a broader strategy to ca..

Next Story
Infrastructure Transport

Air India MRO Facility Key Hub

Air India has launched a state-of-the-art Maintenance, Repair, and Overhaul (MRO) facility at Bengaluru Airport City, establishing a crucial hub for aircraft servicing in India?s burgeoning aviation sector. This new MRO facility aims to enhance Air India?s operational capabilities, improve turnaround times for aircraft maintenance, and reduce reliance on overseas servicing. Strategic Importance of Bengaluru: The facility, located at the Kempegowda International Airport (KIA) in Bengaluru, is strategically positioned to serve as a critical aviation hub. Bengaluru is a key center for both domest..

Next Story
Infrastructure Transport

BMC Notifies Properties for Water Tunnel

The Brihanmumbai Municipal Corporation (BMC) has initiated a crucial step in Mumbai's infrastructure development by notifying several properties for its ambitious underground water tunnel project. This project aims to bolster the city's water supply system, ensuring a more reliable and efficient distribution network. Project Overview: The underground water tunnel project is designed to address Mumbai's increasing demand for water by creating a robust network of tunnels deep below the surface. This tunnel system will transport water from reservoirs directly to various parts of the city, signif..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000