Liebherr 81 K.1 fast-erecting crane stands tall on Vancouver Island
Equipment

Liebherr 81 K.1 fast-erecting crane stands tall on Vancouver Island

A challenging job for a Liebherr fast-erecting crane in Canada: limited space on site resulted in a spectacular crane disassembly. The British Columbia-based crane hire company engaged in the project was particularly impressed by the fast-erecting crane's flexibility and efficiency.

An apartment complex is taking shape not far from Departure Bay in the Canadian coastal town of Nanaimo. The Liebherr 81 K.1 fast-erecting crane involved in the project was supplied by crane hire provider Bigfoot Crane Company Inc. Working in tight conditions, the machine proved what it is capable of in Vancouver Island's second largest city.

Construction of the Departure Bay apartment building presented Bigfoot Crane and the contractor Westurban Developments Ltd. with several challenges, largely due to the complex nature of the structure and the conditions on site. Meticulous planning beforehand, followed by precise implementation, was crucial for the crane's successful operation.

Challenging conditions expertly handled

Cale Anderson, managing director at Bigfoot Crane, describes the project's specific challenges, "It's easy to get a crane onto site when there isn't a building yet. But additional challenges arise once the building is erected because of its structure. When we're planning a project, we always start by looking at how to remove the crane at the end."

The site's access road was used for assembling the fast-erecting crane. But disassembling the 81 K.1 proved to be a tougher challenge. "The completed building was in the way as far as normal dismantling was concerned," explains Anderson. "This meant the fast-erecting crane had to be lifted over the newly constructed building. A large Liebherr mobile crane was used to safely set the 81 K.1 down on the other side of the building." This job was all about flexibility, technical expertise and being able to think outside the box. "As well as the challenges on site requiring the right equipment, we also needed a team willing to find creative and innovative solutions," adds Anderson.

Efficient performance through Liebherr technology

The Liebherr crane's work on the construction site in British Columbia demonstrates the efficiency and versatility of modern crane technology. Cale Anderson is impressed by the Liebherr crane's features and sees great potential for fast-erecting cranes in North America. The hoist rope's 2-fall operation and the Load Plus feature have particularly caught his attention. Both functions ensure fast lifting speeds and allow heavy loads to be lifted, "Our customers especially appreciate the crane's speed and performance that these features make possible," says Anderson. The fast-erecting crane has played an integral role in various construction tasks, including trailer unloading, concrete work and the installation of rooftop equipment. While working in British Columbia, the 81 K.1 proved to be the ideal lifting partner when used with several other cranes on site. Its maximum hook height of 38.9 metres combined with 2.4 metre tower sections meant it was able to maintain the necessary safety distance between other cranes and buildings in its vicinity, and to slew above or below other cranes, depending on the circumstances.

The 81 K.1 can lift up to 6,000 kilograms. It can reach a maximum radius of 48 metres and has a jib head lifting capacity of 1,350 kilograms.

Partnership providing innovation and quality

Bigfoot Crane has 36 cranes in its fleet, six of them are from Liebherr. Tailored Liebherr solutions make all the difference for the crane hire company. "The flexibility and adaptability of Liebherr cranes are key elements in our success. Liebherr understands what we need and works closely with us to ensure we always get the best equipment and service. The versatility of Liebherr cranes allows us to efficiently handle a broad range of projects," explains managing director Cale Anderson. "Liebherr offers innovation, quality and exceptional service, all of which are a perfect match for our requirements."

A challenging job for a Liebherr fast-erecting crane in Canada: limited space on site resulted in a spectacular crane disassembly. The British Columbia-based crane hire company engaged in the project was particularly impressed by the fast-erecting crane's flexibility and efficiency. An apartment complex is taking shape not far from Departure Bay in the Canadian coastal town of Nanaimo. The Liebherr 81 K.1 fast-erecting crane involved in the project was supplied by crane hire provider Bigfoot Crane Company Inc. Working in tight conditions, the machine proved what it is capable of in Vancouver Island's second largest city. Construction of the Departure Bay apartment building presented Bigfoot Crane and the contractor Westurban Developments Ltd. with several challenges, largely due to the complex nature of the structure and the conditions on site. Meticulous planning beforehand, followed by precise implementation, was crucial for the crane's successful operation. Challenging conditions expertly handled Cale Anderson, managing director at Bigfoot Crane, describes the project's specific challenges, It's easy to get a crane onto site when there isn't a building yet. But additional challenges arise once the building is erected because of its structure. When we're planning a project, we always start by looking at how to remove the crane at the end. The site's access road was used for assembling the fast-erecting crane. But disassembling the 81 K.1 proved to be a tougher challenge. The completed building was in the way as far as normal dismantling was concerned, explains Anderson. This meant the fast-erecting crane had to be lifted over the newly constructed building. A large Liebherr mobile crane was used to safely set the 81 K.1 down on the other side of the building. This job was all about flexibility, technical expertise and being able to think outside the box. As well as the challenges on site requiring the right equipment, we also needed a team willing to find creative and innovative solutions, adds Anderson. Efficient performance through Liebherr technology The Liebherr crane's work on the construction site in British Columbia demonstrates the efficiency and versatility of modern crane technology. Cale Anderson is impressed by the Liebherr crane's features and sees great potential for fast-erecting cranes in North America. The hoist rope's 2-fall operation and the Load Plus feature have particularly caught his attention. Both functions ensure fast lifting speeds and allow heavy loads to be lifted, Our customers especially appreciate the crane's speed and performance that these features make possible, says Anderson. The fast-erecting crane has played an integral role in various construction tasks, including trailer unloading, concrete work and the installation of rooftop equipment. While working in British Columbia, the 81 K.1 proved to be the ideal lifting partner when used with several other cranes on site. Its maximum hook height of 38.9 metres combined with 2.4 metre tower sections meant it was able to maintain the necessary safety distance between other cranes and buildings in its vicinity, and to slew above or below other cranes, depending on the circumstances. The 81 K.1 can lift up to 6,000 kilograms. It can reach a maximum radius of 48 metres and has a jib head lifting capacity of 1,350 kilograms. Partnership providing innovation and quality Bigfoot Crane has 36 cranes in its fleet, six of them are from Liebherr. Tailored Liebherr solutions make all the difference for the crane hire company. The flexibility and adaptability of Liebherr cranes are key elements in our success. Liebherr understands what we need and works closely with us to ensure we always get the best equipment and service. The versatility of Liebherr cranes allows us to efficiently handle a broad range of projects, explains managing director Cale Anderson. Liebherr offers innovation, quality and exceptional service, all of which are a perfect match for our requirements.

Next Story
Infrastructure Urban

Andhra Pradesh to Develop 30,000 Women-Led Enterprises by 2025

The Municipal Administration and Urban Development (MAUD) Department is accelerating efforts to create sustainable livelihoods for women in urban areas, in line with Chief Minister Nara Chandrababu Naidu’s goal of fostering one lakh women entrepreneurs by 2025. Under this initiative, the MAUD Department has set a target to establish 30,000 women-led enterprises across towns and cities in Andhra Pradesh. To support this vision, the department plans to establish Micro, Small & Medium Enterprises (MSMEs) for women in TIDCO housing complexes. Vacant plots across 163 colonies have been earmarked ..

Next Story
Infrastructure Energy

G Kishan Reddy discusses mining expansion, clearances with Chhattisgarh CM

Coal and Mines Minister G Kishan Reddy met Chhattisgarh CM Vishnu Deo Sai on Friday to expedite land acquisition and environmental clearances for mining projects. Reddy, who was on a two-day visit to review operations at South Eastern Coalfields Ltd (SECL), discussed measures to boost mining-led economic growth in the state. Key topics included speeding up land acquisition for mine expansions, obtaining quicker environmental approvals, and setting up integrated rehabilitation and resettlement sites. The minister also highlighted the importance of developing critical minerals in the region, alo..

Next Story
Infrastructure Urban

NITI Aayog's Vision for India's Auto Industry

NITI Aayog has launched the report titled "Automotive Industry: Powering India’s Participation in Global Value Chains," offering a roadmap for the country’s automotive future. Released by Shri Suman Bery, Vice Chairman, the report outlines key strategies to grow India’s automotive sector to $145 bn in component production by 2030. India is currently the fourth-largest automobile producer globally, but with only a modest three per cent share in the global automotive component market. The report emphasises the need to strengthen India’s position through competitive manufacturing, skill d..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?